BLT/4e CP 7-10



Chapter 17

Performance and Discharge

Case 17.1

129 N.E. 889

23 A.L.R. 1429

(Cite as: 230 N.Y. 239, 129 N.E. 889)

JACOB & YOUNGS, Inc.,

v.

KENT.

Court of Appeals of New York.

Jan. 25, 1921.

CARDOZO, J.

The plaintiff built a country residence for the defendant at a cost of upwards of $77,000, and now sues to recover a balance of $3,483.46, remaining unpaid. The work of construction ceased in June, 1914, and the defendant then began to occupy the dwelling. There was no complaint of defective performance until March, 1915. One of the specifications for the plumbing work provides that---- 'All wrought-iron pipe must be well galvanized, lap welded pipe of the grade known as 'standard pipe' of Reading manufacture.' The defendant learned in March, 1915, that some of the pipe, instead of being made in Reading, was the product of other factories. The plaintiff was accordingly directed by the architect to do the work anew. The plumbing was then encased within the walls except in a few places where it had to be exposed. Obedience to the order meant more than the substitution of other pipe. It meant the demolition at great expense of substantial parts of *241 the completed structure. The plaintiff left the work untouched, and asked for a certificate that the final payment was due. Refusal of the certificate was followed by this suit. The evidence sustains a finding that the omission of the prescribed brand of pipe was neither fraudulent nor willful. It was the result of the oversight and inattention of the plaintiff's subcontractor. Reading pipe is distinguished from Cohoes pipe and other brands only by the name of the manufacturer stamped upon it at intervals of between six and seven feet. Even the defendant's architect, though he inspected the pipe upon arrival, failed to notice the discrepancy. The plaintiff tried to show that the brands installed, though made by other manufacturers, were the same in quality, in appearance, in market value, and in cost as the brand stated in the contract--that they were, indeed, the same thing, though manufactured in another place. The evidence was excluded, and a verdict directed for the defendant. The Appellate Division reversed, and granted a new trial.

[1] We think the evidence, if admitted, would have supplied some basis for the inference that the defect was insignificant in its relation to the project. The courts never say that one who makes a contract fills the measure of his duty by less than full performance. They do say, however, that an omission, both trivial and innocent, will sometimes be atoned for by allowance of the resulting damage, and will not always be the breach of a condition to be followed by a forfeiture. Spence v. Ham, 163 N. Y. 220, 57 N. E. 412, 51 L. R. A. 238; Woodward v. Fuller, 80 N. Y. 312; Glacius v. Black, 67 N. Y. 563, 566; Bowen v. Kimbell, 203 Mass. 364, 370, 89 N. E. 542, 133 Am. St. Rep. 302. The distinction is akin to that between dependent and independent promises, or between promises and conditions. Anson on Contracts (Corbin's Ed.) s 367; 2 Williston on Contracts, s 842. Some promises are so plainly independent that they can never *242 by fair construction be conditions of one another. Rosenthal Paper Co. v. Nat. Folding Box & Paper Co., 226 N. Y. 313, 123 N. E. 766; Bogardus v. N. Y. Life Ins. Co., 101 N. Y. 328, 4 N. E. 522. Others are so plainly dependent that they must always be conditions. Others, though dependent and thus conditions when there is departure in point of substance, will be viewed as independent and collateral when the departure is insignificant. 2 Williston on Contracts, ss 841, 842; Eastern Forge Co. v. Corbin, 182 Mass. 590, 592, 66 N. E. 419; Robinson v. Mollett, L. R., 7 Eng. & Ir. App. 802, 814; Miller v. Benjamin, 142 N. Y. 613, 37 N. E. 631. Considerations partly of justice and partly of presumable intention are to tell us whether this or that promise shall be placed in one class or in another. The simple and the uniform will call for different remedies from the multifarious and the intricate. The margin of departure within the range of normal expectation upon a sale of common chattels will vary from the margin to be expected upon a contract for the construction of a mansion or a 'skyscraper.' There will be harshness sometimes and oppression in the implication of a condition when the thing upon which labor has been expended is incapable of surrender because united to the land, and equity and reason in **891 the implication of a like condition when the subject-matter, if defective, is in shape to be returned. From the conclusion that promises may not be treated as dependent to the extent of their uttermost minutiae without a sacrifice of justice, the progress is a short one to the conclusion that they may not be so treated without a perversion of intention. Intention not otherwise revealed may be presumed to hold in contemplation the reasonable and probable. If something else is in view, it must not be left to implication. There will be no assumption of a purpose to visit venial faults with oppressive retribution.

Those who think more of symmetry and logic in the development of legal rules than of practical adaptation to the attainment of a just result will be troubled by a classification *243 where the lines of division are so wavering and blurred. Something, doubtless, may be said on the score of consistency and certainty in favor of a stricter standard. The courts have balanced such considerations against those of equity and fairness, and found the latter to be the weightier. The decisions in this state commit us to the liberal view, which is making its way, nowadays, in jurisdictions slow to welcome it. Dakin & Co. v. Lee, 1916, 1 K. B. 566, 579. Where the line is to be drawn between the important and the trivial cannot be settled by a formula. 'In the nature of the case precise boundaries are impossible.' 2 Williston on Contracts, s 841. The same omission may take on one aspect or another according to its setting. Substitution of equivalents may not have the same significance in fields of art on the one side and in those of mere utility on the other. Nowhere will change be tolerated, however, if it is so dominant or pervasive as in any real or substantial measure to frustrate the purpose of the contract. Crouch v. Gutmann, 134 N. Y. 45, 51, 31 N. E. 271, 30 Am. St. Rep. 608. There is no general license to install whatever, in the builder's judgment, may be regarded as 'just as good.' Easthampton L. & C. Co., Ltd., v. Worthington, 186 N. Y. 407, 412, 79 N. E. 323. The question is one of degree, to be answered, if there is doubt, by the triers of the facts (Crouch v. Gutmann; Woodward v. Fuller, supra), and, if the inferences are certain, by the judges of the law (Easthampton L. & C. Co., Ltd., v. Worthington, supra). We must weigh the purpose to be served, the desire to be gratified, the excuse for deviation from the letter, the cruelty of enforced adherence. Then only can we tell whether literal fulfillment is to be implied by law as a condition. This is not to say that the parties are not free by apt and certain words to effectuate a purpose that performance of every term shall be a condition of recovery. That question is not here. This is merely to say that the law will be slow to impute the purpose, in the silence of the parties, where the significance *244 of the default is grievously out of proportion to the oppression of the forfeiture. The willful transgressor must accept the penalty of his transgression. Schultze v. Goodstein, 180 N. Y. 248, 251, 73 N. E. 21; Desmond-Dunne Co. v. Friedman-Doscher Co., 162 N. Y. 486, 490, 56 N. E. 995. For him there is no occasion to mitigate the rigor of implied conditions. The transgressor whose default is unintentional and trivial may hope for mercy if he will offer atonement for his wrong. Spence v. Ham, supra.

[2] In the circumstances of this case, we think the measure of the allowance is not the cost of replacement, which would be great, but the difference in value, which would be either nominal or nothing. Some of the exposed sections might perhaps have been replaced at moderate expense. The defendant did not limit his demand to them, but treated the plumbing as a unit to be corrected from cellar to roof. In point of fact, the plaintiff never reached the stage at which evidence of the extent of the allowance became necessary. The trial court had excluded evidence that the defect was unsubstantial, and in view of that ruling there was no occasion for the plaintiff to go farther with an offer of proof. We think, however, that the offer, if it had been made, would not of necessity have been defective because directed to difference in value. It is true that in most cases the cost of replacement is the measure. Spence v. Ham, supra. The owner is entitled to the money which will permit him to complete, unless the cost of completion is grossly and unfairly out of proportion to the good to be attained. When that is true, the measure is the difference in value. Specifications call, let us say, for a foundation built of granite quarried in Vermont. On the completion of the building, the owner learns that through the blunder of a subcontractor part of the foundation has been built of granite of the same quality quarried in New Hampshire. The measure of allowance is not the cost of reconstruction. 'There may be *245 omissions of that which could not afterwards be supplied exactly as called for by the contract without taking down the building to its foundations, and at the same time the omission may not affect the value of the building for use or otherwise, except so slightly as to be hardly appreciable.' Handy v. Bliss, 204 Mass. 513, 519, 90 N. E. 864, 134 Am. St. Rep. 673. Cf. Foeller v. Heintz, 137 Wis. 169, 178, 118 N. W. 543, 24 L. R. A. (N. S.) 321; Oberlies v. **892 Bullinger, 132 N. Y. 598, 601, 30 N. E. 999; 2 Williston on Contracts, s 805, p. 1541. The rule that gives a remedy in cases of substantial performance with compensation for defects of trivial or inappreciable importance has been developed by the courts as an instrument of justice. The measure of the allowance must be shaped to the same end. The order should be affirmed, and judgment absolute directed in favor of the plaintiff upon the stipulation, with costs in all courts.

Case 17.2

86 Conn.App. 71, 859 A.2d 959

Appellate Court of Connecticut.

Khalid SHAH

v.

COVER-IT, INC., et al.

No. 24314.

Submitted on briefs Sept. 16, 2004.

Decided Nov. 16, 2004.

SCHALLER, J.

The plaintiff, Khalid Shah, appeals from the judgment of the trial court, rendered after a trial to the court, in favor of the defendants Cover-It, Inc., and Brian Goldwitz. [FN1] On appeal, the plaintiff claims that the court improperly found that he materially breached the employment contract between the parties. We disagree and, accordingly, affirm the judgment of the trial court.

FN1. In his complaint, the plaintiff named Cover-It, Inc., J & L Sales, Inc., W.B. Supply, Inc., and Brian Goldwitz as defendants. The parties subsequently agreed that the court needed to address the claims against only the plaintiff's employer, Cover-It, Inc., and its sole owner and president, Goldwitz. All of the counts directed at J & L Sales, Inc., and W.B. Supply, Inc., were deemed waived by the court.

The following facts and procedural history are relevant to our discussion. On November 12, 1997, the parties entered into an employment contract by which the plaintiff became the structural engineering manager of Cover-It, Inc. Pursuant to the terms of the employment contract, the plaintiff was to receive an annual salary of $70,000, payable weekly, for a period of five years and subject to cost of living adjustments. In addition to his salary, the plaintiff was entitled to a commission of 2 percent of the sales generated from those products that he designed while employed, up to $1.5 million.

In addition to standard company benefits, the plaintiff also received three paid weeks of vacation on the completion of his first year of employment and the use of a company car. Furthermore, the plaintiff was permitted to work a flexible full-time schedule of thirty-five hours per week. He also was allowed to take time off from work to attend professional workshops and activities, and to resolve any prior professional obligations. The employment contract was subject to termination by either party with ninety days written notice. If the defendants terminated the contract, the plaintiff, on the completion of his first year of employment, was to receive monthly salary payments for the remainder of the five year period pursuant to a schedule. [FN2]

FN2. The contract provided that for up to two years of service, the plaintiff would be paid $20,000 per year, for three years of service, $30,000 per year and for four years of service, $40,000 per year.

In June, 1998, the plaintiff requested and received permission for a period of vacation time. Goldwitz approved the time off with the understanding that the plaintiff would be gone for several weeks. At the end of August, 1998, the plaintiff had not returned. Goldwitz believed that the plaintiff had abandoned the employment contract and sent him notice that his health benefits were cancelled. The plaintiff returned to work in early September, 1998, and continued working until the middle of October. During that time period, the plaintiff worked two or three days per week and spent long periods of time visiting Internet web sites that were unrelated to his employment duties. The plaintiff also refused to use a time clock to document his attendance; instead, he simply indicated on his time card that he was present. On October 14, 1998, Goldwitz asked the plaintiff if certain designs would be completed. The plaintiff stated that he was not sure when the designs would be completed and that he would take his time in completing them. Goldwitz then terminated the plaintiff's employment.

The plaintiff commenced the present action on October 6, 1999. By way of a fourteen count amended complaint filed on November 20, 2001, the plaintiff alleged various causes of action against the defendants, including breach of contract, breach of the implied covenant of good faith and fair dealing, failure to pay wages in violation of General Statutes § 31-72 and negligent misrepresentation. The defendants filed an answer and a two count counterclaim. With respect to the plaintiff's claims, the court found in favor of the defendants on all counts and rendered judgment accordingly. As to the counterclaim, the court concluded that the defendants had failed to prove damages and rendered judgment in favor of the plaintiff. This appeal followed.

On appeal, the plaintiff claims that the court improperly found that he had breached the contract or, in the alternative, that any breach was not material. Specifically, the plaintiff argues that the court failed to identify an express term or condition that was breached and instead merely found that certain acts, considered together, demonstrated a material breach prior to the termination of his employment. [FN3] Therefore, according to the plaintiff, the defendants were not relieved of their obligations, under the terms of the contract, to pay his full salary for ninety days and to pay his posttermination salary pursuant to the schedule set forth in the contract. We disagree.

FN3. The plaintiff also claims that the court's memorandum of decision contains an inconsistency with respect to the finding of a material breach. Specifically, the plaintiff cites the following language: "The court finds in favor of the plaintiff on the defendants' counterclaim for breach of the implied covenant of good faith and fair dealing and breach of contract." We believe that the plaintiff has taken that language out of context. That language appeared in the section of the court's memorandum of decision in which the defendants' counterclaim was discussed. The court focused solely on the issue of damages when discussing the counterclaim. The court noted that the defendants had failed to present any evidence as to damages and that they did not address that issue in their posttrial brief. It is well established that damages are a necessary element for a breach of contract action. See Rosato v. Mascardo, 82 Conn.App. 396, 411, 844 A.2d 893 (2004) (elements of breach of contract action are formation of agreement, performance by one party, breach of agreement by other party and damages.) Thus, although the defendants failed to introduce any evidence of damages to support their counterclaim, there was ample evidence that the plaintiff materially breached the employment agreement and thereby relieved the defendants of any further contractual obligations. The concept of a material breach is separate and distinct from a cause of action for breach of contract. In short, because there is no inconsistency, the plaintiff's claim is without merit and does not warrant further discussion.

[1][2] As a preliminary matter, we identify the applicable standard of review. "The determination of whether a contract has been materially breached is a question of fact that is subject to the clearly erroneous standard of review.... A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed." (Citations omitted; internal quotation marks omitted.) Efthimiou v. Smith, 268 Conn. 487, 493-94, 846 A.2d 216 (2004); see also Miller v. Guimaraes, 78 Conn.App. 760, 766-67, 829 A.2d 422 (2003). "Our authority, when reviewing the findings of a judge, is circumscribed by the deference we must give to decisions of the trier of fact, who is usually in a superior position to appraise and weigh the evidence." (Internal quotation marks omitted.) LaVelle v. Ecoair Corp., 74 Conn.App. 710, 716, 814 A.2d 421 (2003).

[3][4] "It is a general rule of contract law that a total breach of the contract by one party relieves the injured party of any further duty to perform further obligations under the contract." (Emphasis added.) Rokalor, Inc. v. Connecticut Eating Enterprises, Inc., 18 Conn.App. 384, 391, 558 A.2d 265 (1989); see also State v. Lex Associates, 248 Conn. 612, 624, 730 A.2d 38 (1999); 669 Atlantic Street Associates v. Atlantic-Rockland Stamford Associates, 43 Conn.App. 113, 125-26, 682 A.2d 572, cert. denied, 239 Conn. 949, 950, 686 A.2d 126 (1996); 2 Restatement (Second) Contracts § 237 (1981).

[5][6] In Bernstein v. Nemeyer, 213 Conn. 665, 672, 570 A.2d 164 (1990), our Supreme Court endorsed the use of the multifactor test set forth in the Restatement (Second) of Contracts, supra, § 241, when determining whether a breach is material. "Section 241 of the Restatement (Second) of Contracts provides: 'In determining whether a failure to render or to offer performance is material, the following circumstances are significant: (a) the extent to which the injured party will be deprived of the benefit which he reasonably expected; (b) the extent to which the injured party can be adequately compensated for the part of that benefit of which he will be deprived; (c) the extent to which the party failing to perform or to offer to perform will suffer forfeiture; (d) the likelihood that the party failing to perform or to offer to perform will cure his failure, taking account of all the circumstances including any reasonable assurances; [and] (e) the extent to which the behavior of the party failing to perform or to offer to perform comports with standards of good faith and fair dealing.' " Bernstein v. Nemeyer, supra, at 672 n. 8, 570 A.2d 164; Strouth v. Pools by Murphy & Sons, Inc., 79 Conn.App. 55, 60, 829 A.2d 102 (2003). "The standards of materiality [are] to be applied in the light of the facts of each case in such a way as to further the purpose of securing for each party his expectation of an exchange of performances. [Section 241] therefore states circumstances, not rules, which are to be considered in determining whether a particular failure is material. 2 Restatement (Second), supra, § 241, comment (a)." (Internal quotation marks omitted.) Strouth v. Pools by Murphy & Sons, Inc., supra, at 60, 829 A.2d 102.

In the present case, the court found that the plaintiff took a ten week vacation, which exceeded the time authorized. After the plaintiff returned, he reported for work only two or three days per week and spent long periods of time visiting Internet web sites that were unrelated to his professional duties. Additionally, after being instructed by the human resources manager to document his attendance by use of a time clock, the plaintiff refused and simply marked his time sheets with a "P" for present. Last, the court found that when Goldwitz asked when certain designs would be completed, the plaintiff responded that he was not sure and that he would take his time in completing them. When reviewing those findings in light of the factors set forth in § 241 of the Restatement (Second) of Contracts, we conclude that the court's finding of a material breach was not clearly erroneous.

[7] It is clear from the court's findings that the plaintiff failed to perform under the obligations of the employment contract. As the court properly stated: "[O]ne cannot recover upon a contract unless he has fully performed his own obligation under it, has tendered performance or has some legal excuse for not performing." See Automobile Ins. Co. v. Model Family Laundries, Inc., 133 Conn. 433, 437, 52 A.2d 137 (1947). As a result of the material breach by the plaintiff, the defendants were excused from further performance under the contract, and were relieved of the obligation to pay the plaintiff his full salary for ninety days and to pay his posttermination salary pursuant to the schedule set forth in the contract.

The judgment is affirmed.

In this opinion the other judges concurred.

Case 17.3

390 N.J.Super. 227, 915 A.2d 59

Superior Court of New Jersey,Appellate Division.

Leo FACTO and Elizabeth Facto, Plaintiffs-Appellants,

v.

Snuffy PANTAGIS, Pantagis Renaissance and Snuffy Pantagis Ent., Inc., Defendants-Respondents.

Argued Dec. 20, 2006.

Decided Jan. 29, 2007.

**60 , P.J.A.D.

*228 This is a breach of contract action arising out of the cancellation of a wedding reception due to a power failure.

Plaintiffs contracted with defendant Snuffy Pantagis Ent., Inc., t/a Pantagis Renaissance, a banquet hall in Scotch Plains, for a wedding reception for 150 people, to be held between 6 p.m. and 11 p.m. on Saturday, August 3, 2002. The total contract price was $10,578, all of which was to be paid in advance. The contract contained a force majeure clause, which stated: “Snuffy's will be excused from performance under this contract if it is prevented from doing so by an act of God (e.g., flood, power failure, etc.), or other unforeseen events or circumstances.”

*229 Less than forty-five minutes after the reception began, there was a power failure in the area where the Pantagis Renaissance is located. At the time, plaintiffs were in an upstairs room with the bridal party, and their guests were downstairs being served alcoholic beverages and hors d'oeuvres. The power failure caused all the lights, except emergency lights, to go out and the air conditioning system to shut off. In addition, the band plaintiffs had hired for the reception refused to play without lights or the electricity required to operate their instruments, and the lack of lighting impeded the wedding photographer and videographer from taking pictures.

On the day of the reception, the temperature was in the upper 80s or low 90s and the humidity was high. As a result, plaintiffs and their guests became extremely uncomfortable within a short time after the power failure. According to plaintiffs, some of the guests resorted to pouring water over their heads to keep cool.

When it became evident that electricity would not be restored quickly, the manager of the Pantagis Renaissance offered to reschedule the reception. However, many of plaintiffs' guests had traveled a substantial distance to attend the wedding and would not have been able to return on another date. Therefore, plaintiffs declined the offer.

There was some dispute regarding the services provided after the power failure. Plaintiffs testified that the Pantagis Renaissance stopped serving alcoholic beverages around 7:30 p.m. and that the only food it served in addition to hors d'oeuvres was salad. However, the banquet hall's general manager testified that the facility continued to serve alcoholic beverages until after 9 p.m. and that it served plaintiffs and their guests salad and pasta and started to serve them dinner.

Shortly after 9 p.m., there was some kind of altercation between one of plaintiffs' guests and an employee of the Pantagis Renaissance. As a result, the banquet hall called the police, who arrived around 9:30 p.m. By this time, the batteries operating the emergency lights had begun to run out of power, and the only illumination*230 was provided by candelabras on the tables. Therefore, the manager of the Pantagis Renaissance asked the police to evacuate the facility, which was then occupied not only by plaintiffs and their guests but also the attendees at four other wedding receptions.

Plaintiffs subsequently brought this breach of contract action seeking recovery of the $10,578 they prepaid for the wedding reception plus the $6,000 paid to the band, $3,810 paid to the wedding photographer and $3,242.09 paid to the videographer. Plaintiffs' complaint also asserted a negligence claim.

The case was tried in a half-day bench trial. The trial court concluded in a brief oral opinion that plaintiffs' breach of contract claim was barred by the force majeure**61 clause of the contract because the power failure was an “unusual extraordinary unexpected circumstance” that could not be avoided by “reasonable human foresight.” The court dismissed plaintiffs' negligence claim on the ground there was no evidence the Pantagis Renaissance was responsible for the power failure or failed to take reasonable measures to respond to this unforeseen circumstance. Accordingly, the court entered judgment dismissing plaintiffs' complaint.

On appeal, plaintiffs challenge the dismissal of both their negligence and contract claims. Plaintiffs' arguments in support of their negligence claim are clearly without merit and do not warrant extended discussion. R. 2:11-3(e)(1)(E). Plaintiffs failed to present any evidence that could support a finding that defendants were negligent. Moreover, even if defendants had been negligent, their liability for failure to perform the contract would still be governed solely by the law of contracts. See .

Plaintiffs' contract claim presents more difficult issues. We agree with the trial court's conclusion that the power failure relieved the banquet hall of the obligation to provide plaintiffs with a wedding reception. Therefore, the banquet hall's failure to perform the contract due to the absence of electricity did not *231 constitute a breach. But even though there was no breach, the banquet hall's inability to perform the contract also relieved plaintiffs of their obligation to pay the contract price. Consequently, plaintiffs are entitled to recovery of the $10,578 they prepaid the banquet hall, less the value of the services they did receive.

Even if a contract does not expressly provide that a party will be relieved of the duty to perform if an unforeseen condition arises that makes performance impracticable, “a court may relieve him of that duty if performance has unexpectedly become impracticable as a result of a supervening event.” cmt. a (1981); see . In deciding whether a party should be relieved of the duty to perform a contract, a court must determine whether “the existence of a specific thing is necessary for the performance of a duty” and “its ... destruction, or ... deterioration ... makes performance impracticable[.]” ; see . As explained in Corbin: “If the contract contains no words of express condition to either party's duty of performance, the court may have to fill the gap and determine whether the continued availability of certain means of performance should be deemed a constructive or implied condition.” 14 Corbin on Contracts § 75.7 (Perillo rev.2001). One court has recognized that even in the absence of a force majeure clause, a power failure is the kind of unexpected occurrence that may relieve a party of the duty to perform if the availability of electricity is essential for satisfactory performance. See (power failure that prevented safe performance of concert).

A force majeure clause, such as contained in the Pantagis Renaissance contract, provides a means by which the parties may anticipate in advance a condition that will make performance impracticable. See 8 Corbin on Contracts § 31.4 (Perillo rev. *232 1999). Such a clause conditions a party's duty to perform upon the non-occurrence of some event beyond its control**62 and serious enough to interfere materially with performance. Ibid.

A force majeure clause must be construed, like any other contractual provision, in light of “the contractual terms, the surrounding circumstances, and the purpose of the contract.” . When an unforeseen event affecting performance of a contract occurs, such a clause will be given a reasonable construction in light of the circumstances. See 8 Corbin, supra, § 31.4.

The force majeure clause in the Pantagis Renaissance contract provided: “Snuffy's will be excused from performance under this contract if it is prevented from doing so by an act of God (e.g., flood, power failure, etc.), or other unforeseen events or circumstances.” Thus, the contract specifically identified a “power failure” as one of the circumstances that would excuse the Pantagis Renaissance's performance. We do not attribute any significance to the fact the force majeure clause refers to a power failure as an example of an “act of God.” This term has been construed to refer not just to natural events such as storms but to “comprehend[ ] all misfortunes and accidents arising from inevitable necessity which human prudence could not foresee or prevent[.]” ; see also 14 Corbin, supra, § 74.4 (noting that “[t]he kinds of impossibility that [excuse performance under a contract] in many instances are caused by human beings, although the court might still refer to the event as an ‘act of God.’ ”). Furthermore, the force majeure clause in the Pantagis Renaissance contract excuses performance not only for “acts of God” but also “other unforeseen events or circumstances.” Consequently, even if a power failure caused by circumstances other than a natural event were not considered to be an “act of God,” it still would constitute an unforeseen event or circumstance that would excuse performance.

*233 The fact that a power failure is not absolutely unforeseeable during the hot summer months does not preclude relief from the obligation to perform. Indeed, even in the absence of a force majeure clause, absolute unforeseeability of a condition is not a prerequisite to the defense of impracticability. See . The party seeking to be relieved of the duty to perform only needs to show that “the ‘destruction, or ... deterioration’ of a ‘specific thing necessary for the performance’ of the contract ‘makes performance impracticable.’ ” (quoting ). In this case, the Pantagis Renaissance sought to eliminate any possible doubt that the availability of electricity was a “specific thing necessary” for the wedding reception by specifically referring to a “power failure” as an example of an “act of God” that would excuse performance.

It is also clear that the Pantagis Renaissance was “prevented from” substantial performance of the contract. The power failure began less than forty-five minutes after the start of the reception and continued until after it was scheduled to end. The lack of electricity prevented the band from playing, impeded the taking of pictures by the photographer and videographer and made it difficult for guests to see inside the banquet hall. Most significantly, the shutdown of the air conditioning system made it unbearably hot shortly after the power failure began. It is also undisputed that the power failure was an area-wide event that was beyond the Pantagis Renaissance's control. These are precisely the kind of circumstances under which the parties agreed, by inclusion of **63 the force majeure clause, that the Pantagis Renaissance would be excused from performance. Therefore, the trial court correctly concluded that defendants did not breach the contract.

However, the court erred in concluding that because defendants did not breach the contract, plaintiffs are not entitled to recover the money they prepaid for the wedding reception. Where one party to a contract is excused from performance as a *234 result of an unforeseen event that makes performance impracticable, the other party is also generally excused from performance. , , . As explained in Corbin:

A promisor should not be compelled to give something for nothing. The parties agreed upon an exchange of performances, and an exchange cannot now take place. Even if not stated in express terms, the promisor's duty is constructively conditional on the return performance by the promisee. Even though the nonperforming promissee is not in default because the impossibility doctrine discharges the duty, it cannot demand something for nothing from the other party.

[14 Corbin, supra, § 78.2.]

The same rule applies if a party to a contract is excused from performance by a force majeure clause that expressly sets forth certain categories of unforeseen events that will render performance impracticable. See 8 Corbin, supra, § 31.4 at 62. Therefore, the power failure that relieved the Pantagis Renaissance of the obligation to furnish plaintiffs with a wedding reception also relieved plaintiffs of the obligation to pay the contract price for the reception.

Nevertheless, since the Pantagis Renaissance partially performed the contract by starting the reception before the power failure, it is entitled, under principles of quantum meruit, to recover the value of the services it provided to plaintiffs. See (noting that “where an express contract for work or services is abortive for ... impossibility, or invalidity for other reasons, the plaintiff not being at fault ... may have recovery for the value of his services[.]”); see also . The measure of damages is the benefit conferred upon the party against whom the quantum meruit claim is asserted. See .

Accordingly, the final judgment dismissing plaintiffs' complaint is reversed and the case is remanded to the trial court for further proceedings in conformity with this opinion.

................
................

In order to avoid copyright disputes, this page is only a partial summary.

Google Online Preview   Download