1

(Weeks) Crash cost per week A - 7 4 6000 B - 8 5 8000 C A 9 7 15000 D A, B 8 E B 9 8 2000 F C 10 8 17000 G D, E 5 H E 10 8 4000 I F, G 5 4 7000 Develop an LP model for crashing the project completion time as much as possible. Modify the LP model for maximum crashing within a budget of $65,000 for crashing activities. ................
................