SECTION 104

Utility Sheet Approximate Stations Utility Work Required Duration of Utility Relocation Work (Working Days) Enstar F2 "ML" 98+50 RT to 100+50 RT Existing 4" plastic main retirement and new 4" plastic main construction 3 Enstar F4 "ML" 123+00 Lowering of existing 2" plastic main in place. 1 Enstar F4 "ML" 124+50 RT to 126+20 RT Lowering of ... ................
................