STATEMENT OF WORK

Surface Off-board Passive Decoy System

Version: 1.4 1

07 June 2016

TABLE OF CONTENTS

Annex C To: W8472-165643

1 SCOPE .................................................................................................................................................................4

1.1 OBJECTIVE ...................................................................................................................................................4 1.2 BACKGROUND.............................................................................................................................................4 1.3 LIST OF ACRONYMS.......................................................................................................................................5

2 APPLICABLE DOCUMENTS..........................................................................................................................7

2.1 APPLICABILITY..............................................................................................................................................7 2.2 DND PUBLICATIONS .....................................................................................................................................7 2.3 OTHER PUBLICATIONS ...................................................................................................................................8

3 REQUIREMENTS..............................................................................................................................................9

3.1 GENERAL.......................................................................................................................................................9 3.2 DELIVERABLE LIST .......................................................................................................................................9 3.3 PROJECT MANAGEMENT (PM)....................................................................................................................9 3.4 QUALITY MANAGEMENT..............................................................................................................................10 3.5 CONFIGURATION MANAGEMENT .....................................................................................................11 3.6 INTELLECTUAL PROPERTY.................................................................................................................11 3.7 INSTALLATION ............................................................................................................................................11 3.8 TEST AND TRIALS.....................................................................................................................................11 3.9 MAINTENANCE PLAN ...................................................................................................................................13 3.10 TRAINING AND TRAINING MATERIALS .........................................................................................................13 3.11 INTEGRATED LOGISTIC SUPPORT (ILS)............................................................................................13 3.12 TECHNICAL PUBLICATIONS .....................................................................................................................14 3.13 TECHNICAL SUPPORT ..............................................................................................................................14 3.14 DELIVERY OF EQUIPMENT............................................................................................................................14 3.15 AMMUNITION SAFETY & SUITABILITY BOARD DATA....................................................................................15

3

07 June 2016

1 SCOPE

Annex C To: W8472-165643

1.1 OBJECTIVE

1.1.1

This Statement of Work (SOW) defines the work to be performed by the Contractor which will provide six (6) complete Surface Off-board Passive Decoy systems to be fitted on Halifax-class ships and six (6) sets of ancillary components of the Surface Off-board Passive Decoy systems to be fitted-for-but-not-with on the remaining Halifax-class ships. This work will require the Contractor to manufacture, deliver, test and trial, train, and support the Surface Off-board Passive Decoy systems for the Halifax-class.

1.2 BACKGROUND

1.2.1

In support of national operational commitments, Department of National Defence (DND) has a requirement to acquire Surface Off-board Passive Decoy capability for the Halifaxclass ships. DND plans to fit six (6) Halifax-class ships with complete Surface Off-board Passive Decoy systems and the remaining six (6) Halifax-class ships with fitted-for-butnot-with Surface Off-board Passive Decoy capability.

1.2.2

For the purpose of this SOW, a Surface Off-board Passive Decoy system is defined as an integrated set of components designed and built to provide decoy capability against AntiShip Missile threats. The components of a Surface Off-board Decoy system must include, but is not limited to:

1.2.2.1 Decoy

1.2.2.2 Decoy launcher

1.2.2.3 Equipment necessary for local control capability

1.2.2.4 Equipment necessary for remote control capability

1.2.2.5 Mounting assembly

1.2.3 Furthermore, the ancillary components of a Surface Off-board Decoy system are defined as all components of a Surface Off-board Passive Decoy system, other than Decoy and Decoy Launcher.

4

07 June 2016

1.3 LIST OF ACRONYMS

Annex C To: W8472-165643

CA CDRL CEIL CFB CFITES CI CMS DID DND ECP EMC EMI FAT FMECA FMF FSR HAT HCM ILS IP ISS LLTIL LORA LRU LSA MACA MCN

Contract Authority Contract Data Requirement List Contract End Item List Canadian Forces Base Canadian Forces Individual Training and Education System Configuration Item Combat Management System Deliverable Item Description Department of National Defence Engineering Change Proposal Electromagnetic Compatibility Electromagnetic Interference Factory Acceptance Test Failure Mode Effect and Criticality Analysis Fleet Maintenance Facility Field Service Representative Harbor Acceptance Trial Halifax-class Modernization Integrated Logistic Support Intellectual Property In-Service Support Long Lead Time Item List Level of Repair Analysis Lowest Replaceable Unit Logistic Support Analysis Months After Contract Award Materiel Change Notice