10_Contractors/Lettings/080131/080131r.htm



West Virginia Department Of Transportation

Division of Highways

Bid Results - Letting of September 21, 2010

|CALL |PROJECT NUMBER & BIDDERS |COUNTY |BID |DBE |

| | | | | |

|001 |IM-0792(142)D (S304-79-71.40) |Braxton | |5.00 |

| |J F Allen Company | |1,798,561.53 |5.00 |

| |Meadows Stone & Paving, Inc. | |1,839,356.59 |5.00 |

| |West Virginia Paving, Inc. | |2,017,563.20 |5.00 |

| | | | | |

|002 |NHG-0022(053)D (U305-22-0.00) |Brooke | |2.00 |

| |Bayliss & Ramey, Inc. | |2,104,657.50 |2.00 |

| | | | | |

|003 |STP-0060(259)D (S306-60-23.76) |Cabell | |3.00 |

| |Blacktop Industries & Equipment Co. | |388,729.22 |3.00 |

| |West Virginia Paving, Inc. | |389,652.29 |3.00 |

| | | | | |

|004 |HSIP-0010(194)D (U306-10-1.00) |Cabell | | |

| |West Virginia Paving, Inc. | |88,835.00 | |

| | | | | |

|005 |STP-0010(205)D (S306-10-2.81) |Cabell | |3.00 |

| |West Virginia Paving, Inc. | |244,884.88 |3.00 |

| |Blacktop Industries & Equipment Co. | |252,542.76 |3.00 |

| | | | | |

|006 |STP-0060(260)D (S306-60-12.57) |Cabell | | |

| |West Virginia Paving, Inc. | |199,577.14 | |

| |Blacktop Industries & Equipment Co. | |205,916.18 | |

| | | | | |

|007 |ER-0310(026)D (E310-9-0.05) |Fayette | | |

| |Bilco Construction Co., Inc. | |190,436.00 | |

| |Marks Drilling | |239,956.48 | |

| |Thaxton Construction Company, Inc. of Sissonville | |284,110.00 | |

| |Alan Stone Co., Inc. | |284,157.00 | |

| | | | | |

| | | | | |

| | | | | |

| | | | | |

|008 |NHG-0050(270)D (S317-50-15.48) |Harrison | |2.00 |

| |Bayliss & Ramey, Inc. | |1,606,933.00 |2.00 |

| | | | | |

|009 |STP-0115(078)D (S319-115-2.30) |Jefferson | |4.00 |

| |Jefferson Asphalt Products Co., Inc. | |361,848.37 |4.00 |

| |W & L Construction & Paving, Inc. | |368,959.49 |4.00 |

| |P & W Excavating, Inc. | |418,412.19 |4.00 |

| | | | | |

|010 |STPG-0060(238)D (U320-60-14.84) |Kanawha | |2.00 |

| |Bayliss & Ramey, Inc. | |693,503.75 |2.00 |

| | | | | |

|011 |STP-0033(340)D (S321-33-17.38) |Lewis | |4.00 |

| |J F Allen Company | |648,946.81 |4.00 |

| |Mountaineer Contractors, Inc. | |697,739.28 |4.00 |

| |West Virginia Paving, Inc. | |748,017.05 |4.00 |

| | | | | |

|012 |ER-0610(002)D (E324-7-G06.10) |McDowell | | |

| |Thaxton Construction Company, Inc. of Sissonville | |110,531.00 | |

| |Bilco Construction Co., Inc. | |117,074.00 | |

| |Marks Drilling | |139,893.62 | |

| |Claude Erps Construction, Inc. | |144,632.30 | |

| |BBR Drilling Company, Inc. | |162,928.50 | |

| | | | | |

|013 |ER-0610)02)D (E324-7-G06.12-02) |McDowell | | |

| |Thaxton Construction Company, Inc. of Sissonville | |98,253.50 | |

| |Bilco Construction Co., Inc. | |113,850.00 | |

| |Marks Drilling | |129,626.72 | |

| |Claude Erps Construction, Inc. | |132,534.70 | |

| | | | | |

|014 |NH-0083(051)D (S324-83-1.87) |McDowell | |5.00 |

| |West Virginia Paving, INC. | |708,378.50 |5.00 |

| | | | | |

| | | | | |

| | | | | |

| | | | | |

| | | | | |

| | | | | |

|015 |BR-0028(068)D (S338-28-24.78) |Pocahontas | |4.00 |

| |SMH Construction Company, Inc. | |598,515.86 |4.00 |

| |C L Belt Construction, Inc. | |611,000.00 |4.00 |

| |Triton Construction, Inc. | |668,600.00 |4.00 |

| |Teays River Construction Company | |712,474.75 |4.00 |

| |Bilco Construction Company, Inc. | |718,442.00 |4.00 |

| |Bear Contracting, LLC | |788,623.25 |4.00 |

| |MEC Construction, LLC | |796,641.60 |4.00 |

| |A L L Construction, Inc. | |868,240.20 |4.00 |

| | | | | |

|016 |NHG-02016(190)D (U341-16-12.00) |Raleigh | | |

| |Deferred to September 28th | | | |

| | | | | |

|017 |NH-0219(259)D (U342-219-39.35) |Randolph | |6.00 |

| |West Virginia Paving, Inc. | |541,229.45 |6.00 |

| |J F Allen Company | |548,643.71 |6.00 |

| | | | | |

|018 |BR-00527(004)D (S344-52/7-1.21) |Roane | |4.00 |

| |C L Belt Construction, Inc. | |329,000.00 |4.00 |

| |Bilco Construction Co., Inc. | |329,513.00 |4.00 |

| |R K Construction, Inc. | |356,425.69 |4.00 |

| |Hoke Brothers Contracting, Inc. | |366,616.77 |4.00 |

| |SMH Construction Company, Inc. | |375,848.61 |4.00 |

| |Teays River Construction Company | |385,196.00 |4.00 |

| |Alan Stone Co., Inc. | |425,449.00 |4.00 |

| |Meadows Stone & Paving, Inc. | |548,769.00 |4.00 |

| |Velotta Company, The | |555,104.20 |4.00 |

| | | | | |

|019 |STP-0152(044)D (S350-152-8.30) |Wayne | | |

| |Blacktop Industries & Equipment Co. | |239,123.20 | |

| |West Virginia Paving, Inc. | |242,961.20 | |

| | | | | |

|020 |NH-0097(086)D (S355-97-33.29) |Wyoming | |4.00 |

| |NH-0097(085)D (S355-97-30.23) | | | |

| |West Virginia Paving, Inc. | |1,152,552.35 |4.00 |

| | | | | |

| | | | | |

| | | | | |

| | | | | |

|021 |ER-0610(001)D (E355-7/2-G06.10) |Wyoming | | |

| |Bilco Construction Company, Inc. | |64,312.00 | |

| |Thaxton Construction Company, Inc. of Sissonville | |68,262.50 | |

| |BBR Drilling Company, Inc. | |84,682.50 | |

| |Marks Drilling | |104,712.50 | |

| |Claude Erps Construction, Inc. | |105,003.40 | |

| | | | | |

|022 |ER-0610(001)D 9E355-14-G06.10- |Wyoming | | |

| |Bilco Construction Company, Inc. | |78,888.00 | |

| |Thaxton Construction Company, Inc. of Sissonville | |97,878.00 | |

| |BBR Drilling Company, Inc. | |116,476.40 | |

| |Marks Drilling | |124,684.23 | |

................
................