Houston METRO Shuttle of the Future - Federal Transit Administration
=
ACCELERATING INNOVATIVE MOBILITY (AIM) GRANT
SHUTTLE OF THE FUTURE: MID-SIZE LEVEL 4 AUTONOMOUS ZERO EMISSION SHUTTLE BUS DEPLOYMENT
HOUSTON METRO
IN PARTNERSHIP WITH PHOENIX MOTORCARS, EASYMILE, AND AECOM
FTA Transit Bus Automation Factsheet:
Houston METRO
1
PROJECT SUMMARY
Automation Level(s): 4
This project will develop and test a Level 4 automated, all-electric shuttle bus, the EZ Zeus. This shuttle bus will be FMVSS, ADA, and Buy America compliant. It will be built on a proven E-450 Ford chassis. Houston METRO will use EZ Zeus to conduct a 12-month demonstration connecting METRO's high-capacity transit system via the Route 54 bus route and Purple Line light rail station.
PROJECT GOAL
Improve neighborhood mobility for first- and last-mile connectivity by providing a mid-size Level 4 autonomous zero-emission shuttle to serve as a first/last mile community connector to those areas with limited transit options
VEHICLE INFORMATION
This project will use the EZ Zeus 400, provided by Phoenix Motors, which is a shuttle bus built upon a proven E-450 Ford chassis. EasyMile will apply its automated driverless technology to finalize creation of the prototype autonomous Level 4 shuttle bus. The shuttle bus will be FMVSS, ADA, and Buy America compliant. The shuttle bus will be capable of carrying 12 passengers and two wheelchairs. The vehicle will also be all-electric and zeroemission.
DATA COLLECTION, MANAGEMENT, & SHARING
Houston METRO and AECOM will work with other project partners to evaluate the effectiveness of the pilot shuttle service from the perspective of the passengers and public. Together, they will collect the following types of information. All observations will be made while denoting time of day, day of week and weather conditions (temperature, real-feel temperature, wind speed/direction, dew point, humidity, barometric pressure, precipitation). Collected data will include: number of passengers; passenger pre- and post-ride observations/expectations; number of emergency stops; battery performance per route and day; battery charging rate; battery charging issues; vehicle heater/AC usage; number of instances when the driver must take manual control per route.
PROJECT STATUS & SCHEDULE
The project has not yet began, but is estimated to have a 33-month duration, starting in April 2021.
BUDGET
FTA AIM Grant Funding $1,473,435
Non-Federal Cost Share $884,000
Total Amount $2,357,435
FTA Transit Bus Automation Factsheet: Houston METRO
ACCELERATING INNOVATIVE MOBILITY (AIM) GRANT 2
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- metro commuter schedule freedom transit bus transportation service
- 16a e washington metropolitan area transit authority
- reduced schedule effective january 3 2021 9 arrive route metro bus
- n2 4 6 washington metropolitan area transit authority
- bear creek p r sammamish issaquah eastgate march 18 2022 mercer
- transportation technology and infrastructure committee houston
- 20 all trips accessible new printed schedules will not be go metro
- system route page 1 082118 v1 metro
- life cycle environmental impact of houston metro system lsu
- 08 bus rapid transit station at tidwell houston
Related searches
- future of the finance industry
- what s the future of technology
- the future of higher education in america
- workplace of the future conference
- roles of the administration department
- the future of nursing practice
- the future of college education
- future of the us navy
- skills of the future workforce
- the future of nursing leading change
- the future of college sports
- the future of teaching