Minutes of Conference held at JMP on 02.09.11 and 03.09.11

for 140T Crane (Gottwald Design) spares requirement and repair requirement

Present:

Rly. Board Representative: Jamalpur Representative:

Sri Manish Jain/ DME (P)-II Sri Animesh Kr. Sinha/CWM/JMP

Sri C. P. Sharma/ Dy.CME/Cr/JMP

Sri G. C. Rao/ AWM/Crane/JMP RDSO/LKO Representative:

Sri Pankaj Saxena/ADE/RDSO/LKO

ER HQ Representative:

Sri S. K. Biswas/ Dy.CME/HQ/ER

Sri J. K. Pal/ SME/HQ-I/ER

Firm’s Representative

Mr. Anmol Batra/Cummins/Kol.

Mr. J.D.Petkar/Mechanica/Pune

Mr. Binod Kumar/ Hi-tech/Delhi

Crane User Representative:

1) Sri B. Lakra, CMPE/NFR (2) Sri Satish Kumar, CMPE/NER

(3) Sri A. K. Gupta, CMPE/SECR (4) Sri A. K. Shivhare, Dy.CME/HQ/NCR

(5) Sri A. K. Gautam, Sr. DME (O&F)/ALD (6) Sri K. N. S. Yadav, Sr. DME (P)/DHN

(7) Sri S. N. Roy, Sr.DME (C&W)/SEE (8) Sri N. N. Sarkar, Dy.CME (OP)/SDAH

(9) Sri B. K. Pandey, Sr.DME/Gonda (10) Sri C.S. Yadav,DME(P)/NR/LKO

(11) Sri P.K. Mukhopadhyayay,DME(P)/ER/ASN (12) Sri K.L. Saini, DME/WR/RTM

(13) Sri A. Gupta, DME/NFR/NJP (14) Sri C.H.V. Ramanna, DME/ECoR/VSKP (15) Sri B. Nath, DME/NFR/NBQ (16) Sri Shivaji Kadam, DME/CR/Ajni

(17) Sri A.K. Srivastava, DME/NR (18) Sri G.S.Reddy, AME/ECoR/BBS

(19) Sri S. C.Behra, SME (HQ)/SER/GRC (20) Sri B.Sampat Kumar, AM E/SCR/PAU

(21) Sri S.K. Tiwari, AME/ER/SBG (22) Sri A.K.Gupta, ADME/ECR/SEE

(23) Sri J.P. Singh, AME/NFR/NGC (24) Sri K.K.Deva, ADME/NFR/TSK

(25) Sri R. Rangarao, ADME/SECR/BIA (26) Sri D. Kumar, ADME (P)/ECR/MGS

(27) Sri Chintamani, ADME/SECR/BSP (28) Sri P. Behra, ADME/ECoR

(29) Sri P.S. Kumar, AME/NED (30) Sri K. Raja, ADME/SR/TVC

(31) Sri B.K.Saha, ADME/Gondia

This meeting conducted as follow-up to Crane Review Meeting conducted at RDSO on 29-7-11.

1. CAMC of Cummins Engine:

(Item-4, decision-4 of RDSO-MOM)

M/s Cummins was represented by Mr. Anmol Batra (Cummins/Eastern Zone/Kol).

Points discussed were as follows:

|S.N. |POINT |EXISTING PROPOSAL |TO BE REVISED AS |

|1 |No of visits |8 visits per annum |4 Regular visits + 1B check visit +1C check visit per |

| | | |annum to be equally inter-spread to the extent |

| | | |possible |

|2 |Payment terms |Pro rata on annual basis for AMC& bi-monthly |Actual basis. Billing per visit or bi-monthly as |

| | |submission of bills |suitable for firm. |

|3 |Response time to | ................
................