ISO New England



- RC AGENDA -

NEPOOL Reliability Committee

Tuesday, September 16, 2014

TIME: 9:30 a.m. – 3:30 p.m.

LOCATION: Doubletree Hotel, Westborough, MA

DIAL IN NUMBER: 1-866-711-7475; Access Code 8562734

Item Description Time Allotted

1.0 Chair’s Remarks 09:30 – 09:35

2.0 Proposed Plan Applications (PPAs) Level II/III 09:35 – 09:50

Present Proposed Plan Applications for committee action on advisory recommendation

for ISO approval.

2.1 Jericho Wind Farm Expansion Project - Level III (Vote)

NU-14-G16 – Generator notification from Northeast Utilities Service Company (“NU”)

on behalf of Queue Position #437 for the installation of two 2.85 MW wind turbine

generators at the Jericho Wind Farm. Project will interconnect to the PSNH Jericho

Road 34/.5 kV Substation in Berlin, NH. Unit name plate capability is 5.7 MWs but

due to distribution system limitations, the combined total output of the project and

QP #415 will be limited by a wind farm controller 10 12.05 MWs, a 3.5 MW increase

from the original QP #415 project. Proposed in service date of the project is November 1, 2014.

(J. DiLuca September 2, 2014, Generator Notification and One Line Diagram, Approval Letter,

“Queue Position #437 System Impact Study Rev.3” dated July 3, 2014) (Jim DiLuca)

2.2 Southeast Substation Project – Level II (Vote)

NEP-14-T10 – Transmission notification from New England Power Company (“NEP”)

for the construction of a new Southeast Substation located in Pawtucket, RI. Project will

consist of two 115/13.8 kV 33/44/55 MVA LTC transformer supplied via taps off the X3

and T7 Lines. In addition, at Pawtucket No. 1 substation, move the T74 115/13.8 kV

transformer to the T71 transformer position and retire existing T71 115/13.8 kV transformer

and associated 13.8 kV indoor bus. Proposed in service date of the project is December 1, 2018.

(A. Kesete September 2, 2014 Cover Letter, Transmission Notification and One Line Diagram,

Approval Letter, “Southeast Substation – New 115/13.8 kV Substation – System Impact Study”

dated August 2014. (Jack Martin)

3.0 Proposed Plan Notifications (Level 0 & Level I – Informational Only) 09:50 – 10:00

Present application and notifications, receive committee review and concurrence

that the Plan requires Level 0 or I treatment.

3.1 Brewster Landfill Solar Project – Level 0 (Notification)

NU-14-G17 – Generator notification from Northeast Utilities Service Company (“NU”)

on behalf of CF CVEC Owner One LLC the installation of a 1.083 MW solar array

located in Brewster, MA and interconnecting to the NU Harwich Substation #968,

#118 transformer via the 23 kV feeder #89A. Proposed in service date of the project is

September 5, 2014.

(K. Jones September 9, 2014 Cover Letter, Generator Notification and One Line Diagram)

(Al Scarfone)

3.2 Ward Hill Transformer Replacement Project – Level I (Notification)

NEP-14-T11 – Transmission Notification from New England Power Company (“NEP”)

for the replacement of the existing 48/64/80 MVA 115/24 kV T1 transformer with a new

45/60/75 MVA 115/24 kV transformer due to unit conditions at the Ward Hill substation

located in Haverhill, MA. Proposed in service date of the project was June 2014.

(S. Sarkar September 9, 2014 Cover Letter, Transmission Notification and One Line Diagram)

(Subhadarshi Sarkar)

3.3 East Beverly Substation Transformer Replacement Project – Level I (Notification)

| NEP-14-T05 – Transmission notification from New England Power Company (“NEP”) |

|for the replacement of two existing 115/34.5 kV 24/32/40 MVA transformers with |

|115/34.5 kV 33/44/55 MVA transformers at the East Beverly Substation located in |

|Beverly, MA. Proposed in service date of the project is November 2016. |

|(S. Soko August 25, 2014 Cover Letter, Transmission Notification and One Line |

|Diagram) (Soma Soko) |

| |

|3.4 UI Seaside Renewable Solar Project – Level 0 (Notification) |

UI-14-G03 – Generator notification from United Illuminating Company (“UI”) for the

installation of a 2.2 MW solar array fuel cell generator located in Bridgeport CT and

interconnecting to the Pequonnock 115/13.8 KV Substation 13.8 kV bus #1, position #8,

circuit #2501. Proposed in service date of the project is July 1, 2015, 2015.

(A. Boutsioulis August 28, 2014 Cover Letter, Generator Notification and One Line Diagram)

(Alex Boutsioulis)

3.5 Pequonnock 115 kV Clearing Time Delay Project PPA Withdrawal (Notification)

PPA withdrawal notification from United Illuminating Company (“UI”) for the Pequonnock

115 kV Clearing Time Delay Project.

UI-12-T21 - Control House Rebuild at Pequonnock 115 kV Substation to allow for relay

upgrades and intentional clearing time delay.

(A. Boutsioulis September 25, 2014 Cover Letter, Transmission Notification and One

Line Diagram) (Alex Boutsioulis)

3.6 PV 20 Cable Line Replacement Project – Level I (Notification)

VELCO-14-T01 – Transmission notification from Vermont Electric Company (“VELCO”)

for replacement of the submarine cables along the PV 20 115 kV line connecting Plattsburgh,

NY substation and the Sand Bar VT substation. Proposed in service date of the project is

December 2017. 

3.7 Coventry Solar Project – Level 0 (Notification)

VELCO-14-GNF03 - Generator notification from Vermont Electric Company (“VELCO”)

on behalf of Coventry Photovoltaic LLC for the construction of a 2.2 MW solar array located

in Coventry, VT and interconnecting to the H17 45 kV line out of the Irasburg substation.

Proposed in service date of the project is July 9, 2014.

(F. Ettori July 14, 2014 Cover Letter, Generator Notification and One Line Diagram)

(Frank Ettori)

3.8 North Clarendon Solar Project – Level 0 (Notification)

VELCO-14-GNF04 - Generator notification from Vermont Electric Company (“VELCO”)

on behalf of Clarendon Solar Farm LLC for the construction of a 2.0 MW solar array located

in North Clarendon, VT and interconnecting to the 12.5 kV feeder out of North Brattleboro

supplied from the Vernon Road substation. Proposed in service date of the project is August 1, 2014.

(F. Ettori July 14, 2014 Cover Letter, Generator Notification and One Line Diagram) (Frank Ettori)

3.9 Technology Drive Solar Project – Level 0 (Notification)

VELCO-14-GNF05 - Generator notification from Vermont Electric Company (“VELCO”)

on behalf of WE 90 Technology Drive, LLC for the construction of a 2.0 MW solar array located

in Brattleboro, VT and interconnecting to the 12.5 kV feeder out of South Rutland

supplied from the Cold River substation. Proposed in service date of the project is July 1, 2014.

(F. Ettori July 14, 2014 Cover Letter, Generator Notification and One Line)

3.10 Charlotte Solar Project – Level 0 (Notification)

VELCO-14-GNF06 - Generator notification from Vermont Electric Company (“VELCO”)

on behalf of Charlotte Solar, LLC for the installation of a 2.0 MW solar array located in Charlotte,

VT and interconnecting to the Green Mountain Power pole #129 to a 12.47 kV distribution circuit.

(F. Ettori July 14, 2014 Cover Letter, Generator Notification and One Line Diagram)

(Frank Ettori)

4.0 Non-Price Retirement 10:00 – 10:15 2018/2019 Capacity Commitment Period Evaluation of Non-Price Retirements

4.1 Wallingford Refuse (Vote)

Non-Price Retirement request from Covanta Projects of Wallingford for Wallingford

Refuse Generator (Resource ID #623). The current summer Qualified Capacity as calculated

for the 2018/2019 Capacity Commitment Period for the resource is 5.993 MW.

(Non-Price Retirement Request Form, Reliability Determination Need, Presentation)

(MariahWinkler)

5.0 Planning Procedures 10:15 – 10:45

5.1 PP 10 (Future Vote)

Conforming changes associated with Non-Commercial Capacity Deferral Notifications

and other clarifications.

(Presentation) (Mariah Winkler)

6.0 HQICC and ICR Values for the FCA9 2018/2019 Capacity Commitment Period (Vote) 10:45 – 12:00

Review HQICC and ICR Values associated with FCA 9 2018/2019 Capability Period.

(Presentation) (Peter Wong/Maria Scibelli)

LUNCH 12:00 – 12:45

7.0 Price Responsive Demand (PRD) Reserve Auditing (Vote) 12:45 – 1:30

Review proposed market design and Tariff changes that will allow a demand response

resource to establish a CLAIM10/30 value to reflect its reserve capability.

(MC/RC Memo, MR 1 Section III) (Henry Yoshimura)

8.0 Operating Procedures 1:30 – 3:30

8.1 OP 12 – Voltage and Reactive Control (Future Vote)

Administrative revisions as part of annual review of document.

(OP 12 Clean and Redline) (Osman Bileya)

8.2 OP 12A, OP 12B, OP 12C, OP 12D – Voltage and Reactive Control Appendices

(Notification)

Administrative revisions as part of annual review of document.

(OP 12 Clean and Redline) (Osman Bileya)

8.3 OP 11 – Black Start Resource Administration (Future Vote)

Administrative changes as part of biennial review.

(OP 11 Clean and Redline) (Kory Haag)

8.4 OP 11E, OP 11F – Black Start Resource Administration Appendices (Notification)

Administrative changes as part of biennial review.

(OP 11E, OP 11F Clean and Redline) (Kory Haag)

8.5 OP 14 – Technical Requirements for Generators, Demand Resources and Asset

Related Demands (Future Vote)

Document revision for language clarifications regarding Governor Control.

(OP 14 Clean and Redline) (Dean LaForest)

8.6 OP 14A, OP 14E, OP 14G – Technical Requirements for Generators, Demand Resources and Asset

Related Demands Appendices (Vote)

Document revisions to support Winter Reliability Program.

(OP 14A, OP 14E, OP 14G Clean and Redlines) (Steve Jones)

8.7 NX-12, NX-12E, NX-12G – Generator Technical Data Form and Appendices (Notification)

Administrative changes to two forms (NX-12E for ARDs and NX-12G or ATRRs) and

addition of fields to the NX-12 for Generators to support Winter Reliability efforts by

collecting Fuel Information.

(NX-12, NX-12E, NX 12G Clean and Redline) (Steve Jones)

8.8 OP 14B – Generator Reactive Data Explanation of Terms and Instructions for Data

Preparation for ISO Form NX-12D (Future Vote)

Administrative revisions to support requirements for units required to supply NX-12D information.

(OP 14B Clean and Redline) (Kory Haag/Osman Bileya)

8.9 OP 23, OP 23G – Generator Resource Auditing and Appendices (Future Vote)

Documents revised to reflect added reactive capability testing program requirements from OP 12.

(OP 23, OP 23G Clean and Redline) (Kory Haag/Osman Bileya)

8.10 OP 17 – Load Power Factor Correction (Future Vote)

Administrative revisions and edits for 6 plot points and language addition to address how the

VTF will address instances when projects assumed in service in forecasted LPF are not placed

in service as planned.

(OP 17 Clean and Redline) (Osman Bileya)

8.11 OP 17A – Load Power Factor Correction Appendices (Notification)

Revisions to support various regional line additions or replacements.

(OP 17A Clean and Redline) (Osman Bileya)

8.12 OP 7A – Action in an Emergency – Instructions for Implementing Manual Load

Shedding (Notification)

Administrative revisions as part of annual review of document.

(OP 7A Clean) (Jerry Elliott)

9.0 Closing Remarks 3:30

................
................