Question - Seattle

[Pages:4]

The following is additional information regarding Request for Proposal #SCL-961, titled Skagit Tug Boats released on 10/9/09. The due date and time for responses is updated to as 12/09/09, 2:00 PM (Pacific). This addendum includes both questions from prospective proposers and the City’s answers, and revisions to the RFP. This addendum is hereby made part of the RFP and therefore, the information contained herein shall be taken into consideration when preparing and submitting a proposal.

|Item # |Date Received |Date Answered |Vendor’s Question |City’s Answer |ITB/RFP Revisions |

|2 |10/19/09 |11/3/09 |Will the City make an exception to the minimum | |See answer to #4. |

| | | |requirement of having built 2 aluminum-hull boats in | | |

| | | |the past 5 years? | | |

|3 |10/27/09 |11/3/09 |Is a bid bond required? |No | |

|4 |10/27/09 |11/3/09 |Do vendors have to have built two boats that have met |Yes |Page 2 of RFP, Section 2. Minimum Qualifications bullets are replaced with: |

| | | |USCG, ABS and ABYC to meet the minimum qualification? | |Must have designed, constructed, and delivered two (2) aluminum hull boats OR|

| | | | | |two (2) tug boats within the past 5 years. |

| | | | | |Must have constructed two (2) vessels meeting USCG, ABS, and ABYC |

| | | | | |specifications within the past 5 years. |

| | | | | |Must provide a Letter of Commitment from a qualified bond company with the |

| | | | | |bid, equal to 100% of the offer. |

|5 |10/27/09 |11/3/09 |Is there an upfront payment made to the Vendor at the |No, see RFP, page 6, | |

| | | |time of contract award? |“Notice to proceed and | |

| | | | |progress of work”, Item A.| |

|6 |10/27/09 |11/3/09 |RFP, page 8, “Payments/Invoicing”, Item #2 – What’s the|See RFP, page 9, Paragraph| |

| | | |breakdown? |after Item 4. Also, if | |

| | | | |items have a long lead | |

| | | | |time, the City may | |

| | | | |negotiate payment. | |

|7 |10/27/09 |11/3/09 |What is the period of time City Light|SCL will have up to 2 weeks to |Page 5 of the RFP, PRE-BUILD MEETING is revised as follows: The pre-build |

| | | |has to approve design? |approve the design without impacting |meeting will be held in Newhalem Washington at a date mutually agreeable to |

| | | | |the delivery date. |the Vendor and SCL. At a minimum, the lead designer and a shipyard |

| | | | | |representative shall be in attendance. SCL will have two weeks following the|

| | | | | |pre-build meeting to provide final approval or rejection of the design |

| | | | | |documents without impacting the final delivery date of the vessels. If the |

| | | | | |design documents meet with SCL approval, A Notice to Proceed with |

| | | | | |construction, fabrication and procurement will be issued as described below. |

|8 |10/27/09 |11/13/09 |Do we have to pay Prevailing Wage? |Yes, per LNI, prevailing wage is | |

| | | | |required. | |

|9 |10/27/09 |11/3/09 |Will the City lower the amount |No. 100% bond or letter of credit is|See RFP, page 14, “Contract Bond”, Add the following paragraph – At the City |

| | | |required for the contract bond? |still required; however we have now |of Seattle’s option, prior to execution of the purchase contract, the City of|

| | | | |added language that we reserve the |Seattle may waive the bond requirement. (The cost of the bond will be part of|

| | | | |option of waiving the bond after |the price evaluation.) |

| | | | |contract award. | |

|10 |10/27/09 |11/3/09 |Will you lower the amount on the |See answer #9 | |

| | | |letter of credit? | | |

|11 |10/27/09 |11/3/09 |What is the maximum height for the |The vendor is responsible for | |

| | | |trailer? |arranging transportation, including | |

| | | | |use of the most appropriate trailer.| |

| | | | |As stated in the RFP, two tunnels | |

| | | | |must be navigated on SR20. It is up| |

| | | | |to the vendor to verify the | |

| | | | |dimensions of each tunnel, however, | |

| | | | |WaDOT has provided the dimensions | |

| | | | |presented in #14 below. | |

|12 |10/27/09 |11/3/09 |What is the height of the elevated |The elevated wheelhouse on the | |

| | | |wheelhouse? |Diablo Lake vessel must be tall | |

| | | | |enough to see over our barge (from 1| |

| | | | |– 3ft above the water line depending| |

| | | | |on the load) plus the load, which is| |

| | | | |typically a standard semi truck with| |

| | | | |trailer. | |

|13 |10/27/09 |11/3/09 |What is the height of the barge when |See answer to #12. | |

| | | |empty? When full? | | |

|14 |10/27/09 |11/3/09 |What is the dimension of the tunnels |It is the responsibility of the | |

| | | |located on SR 20? |vendor to research the dimension of | |

| | | | |the tunnels. However, WADOT has | |

| | | | |provided the following dimensions: | |

| | | | |Tunnel #1 at MP 122.43 is 16’ 8” and| |

| | | | |tunnel 2 at mp 124.07 is 17’ 8”. | |

| | | | |During the winter, road and tunnel | |

| | | | |ice may change these dimensions. In| |

| | | | |addition, the Ross Lake vessel will | |

| | | | |need to transit a tunnel on our | |

| | | | |access road which has an approximate| |

| | | | |clearance height of 11 ft. | |

|15 |10/27/09 |11/3/09 |Pilot house, Detachable or hinged? |As per the specifications, Ross lake| |

| | | | |vessel wheelhouse can be either | |

| | | | |detachable or hinged. Diablo Lake | |

| | | | |vessel wheelhouse is not to be | |

| | | | |hinged. It will only be removed | |

| | | | |during initial delivery and for | |

| | | | |major repairs. | |

|16 |10/27/09 |11/3/09 |Do you know the lead time of the |No, however based on the size, we | |

| | | |engines? |believe them to be readily available| |

|17 |10/27/09 |11/3/09 |Besides the engines, are any other |No | |

| | | |items on the specifications brand |This answer has been changed via | |

| | | |specific? |item #48 | |

|18 |10/27/09 |11/3/09 |Where will the Sea Trials take place? |At the vendors location. | |

| | | | |This answer has been changed via | |

| | | | |line item #50 | |

|19 |10/27/09 |11/3/09 |During the demonstration at Diablo |No, the City of Seattle’s insurance | |

| | | |Lake, who will operate the boat? If |will not cover the boat until we | |

| | | |City Light employees operate the boat,|take ownership of it. | |

| | | |will the City’s insurance cover it? | | |

|20 |10/27/09 |11/3/09 |What sort of response time can |During fabrication, the City agrees |Page 6 of the RFP, C Inspection is revised as follows: |

| | | |builders expect from the City? |to inspect or approve items within |The inspection of work in progress will be performed by the City, or other |

| | | | |one week of notification from the |authorized representative of the City of Seattle. The City will perform |

| | | | |Vendor. As described in the RFP, |inspections or approvals within one week of notification from the Vendor. |

| | | | |the vendor is responsible for |The Vendor is to use the progress reports described above to provide advance |

| | | | |preparing complete and accurate |notification of any needed inspections or approvals. Deficiencies noted |

| | | | |progress reports which are intended |during inspection shall be corrected immediately. Failure to correct the |

| | | | |to ensure that the City is appraised|defects shall be considered a material breach of this contract. |

| | | | |ahead of time of major inspections | |

| | | | |or approvals. | |

|21 |10/27/09 |11/3/09 |Is the change order process stated in |See RFP, page 9, “Expansion Clause” | |

| | | |the RFP? | | |

|22 |10/27/09 |11/3/09 |Are as built drawings required? |Yes. As-built drawings are required|Page 7 of the RFP , DELIVERY AND DEMONSTRATION is revised as follows: |

| | | | | |This is the final phase of the project and includes loading, transportation, |

| | | | | |and final assembly/attachment of wheelhouse, launch, and successful operation|

| | | | | |of each boat. Training on operating equipment and delivery of O&M a |

| | | | | |warrantee information is also included in this phase. At a minimum, two O&M |

| | | | | |manuals shall be delivered for each vessel. At a minimum, the O&M manuals |

| | | | | |are to include: as-built drawings, contact names and addresses for all |

| | | | | |subcontract installers, suppliers and vendors, product data for all |

| | | | | |components that require periodic maintenance with maintenance schedules and |

| | | | | |procedures. Instructions for proper operations of specific equipment or |

| | | | | |systems within the vessel. Information on any special manufacturers |

| | | | | |warranties beyond the required two-year warrantee |

|23 |10/27/09 |11/3/09 |Are owner’s manuals required? |Yes, see answer to #22 |See answer to #22 |

|24 |10/27/09 |11/3/09 |Are there liquidated damages? |No | |

|25 |10/27/09 |11/3/09 |RFP, page 9, “Audit”, can this be |No, this is stipulated by State law,| |

| | | |revised? |as in the required minimum of six | |

| | | | |years. | |

|26 |10/27/09 |11/3/09 |Do both boats need to be delivered at |Slightly staggered delivery dates | |

| | | |the same time? |may be negotiated if efficiencies or| |

| | | | |significant cost savings can be | |

| | | | |obtained. However, the bond or | |

| | | | |letter of credit must be obtained | |

| | | | |for both boats. | |

|27 |10/27/09 |11/3/09 |Does there need to be a naval |As stated in the specifications, the| |

| | | |architect involved? Do all drawings |final fabrication drawings and | |

| | | |need to be stamped? |specifications are to be stamped by | |

| | | | |a professional Naval Architect. | |

| | | | |This includes all drawings. | |

|28 |10/27/09 |11/3/09 |Who is responsible for transportation |See RFP, page 8, “Warranties” – it | |

| | | |for warranty work? |is the responsibility of the vendor.| |

|29 |10/27/09 |11/3/09 |Can the warranty work be done at |Warranty work at Diablo must be | |

| | | |Diablo? |mutually agreed upon. | |

|30 |10/30/09 |11/3/09 |Is the $600K budget firm? |Yes, the $600K budget is firm. | |

| | | | |However, a bid does not need to be | |

| | | | |within that budget to be considered | |

| | | | |a responsive bid. The City | |

| | | | |reserves the right to award a | |

| | | | |contract for one boat or to cancel | |

| | | | |the RFP in its entirety. | |

|31 | |11/3/09 | | |The deadline for questions has been extended until 11/6/09, 4:00 PM |

|32 |11/3/09 |11/9/09 |The specifications ask for an elevated|The Barge is 78ft long and 42 ft | |

| | | |pilot house for visibility over barge |wide.  the remaining information is | |

| | | |cargo.  Can we get some information |provided in previous answers. | |

| | | |about the barge?  How Long & Wide & | | |

| | | |Deep?  How high off of the water is | | |

| | | |the cargo?  How much change in draft | | |

| | | |is there between loaded and unloaded? | | |

|33 |11/3/09 |11/9/09 |Is 25’ the max length of the boat or |The Diablo boat can be longer, | |

| | | |could a few more feet in length be |however, the Ross boat is limited to| |

| | | |tolerated? |25' long | |

|34 |11/3/09 |11/9/09 |Taxes:  It appears that the boat |The boat builder will be responsible| |

| | | |builder is not responsible to collect |to collect Washington State Sales | |

| | | |Washington State Sales Tax.  The City |Tax, it will be added to the | |

| | | |of Seattle will pay the tax if |Purchase Order. Your base price | |

| | | |necessary.  Is this correct?  The base|should not include taxes. | |

| | | |bid price would not include any WSST? | | |

|35 |11/3/09 |11/13/09 |Prevailing Wages:  It appears the |Per LNI, the fabrication of the tug |See RFP, page 31, Attachment #4, 1st Icon with the following, also revise the|

| | | |Metal Fabrication in Shop is the |boats would fall under Shipbuilding |heading to read: Prevailing Wages – Updated 9/2/09: |

| | | |closest trade that describes what we |& Ship Repair. If you have |[pic] |

| | | |do.  Is this correct? |questions regarding the specific | |

| | | | |rates, contact LNI directly. | |

|36 |11/3/09 |11/9/09 |Follow up question to Item 12 on the |The barge load may include either | |

| | | |11/3/09 addendum:  When you say |type of truck/van.  Yes, we have | |

| | | |standard semi truck and trailer do you|been anticipating the cab would be | |

| | | |mean a flat bed & cab meaning about |high enough to put the captain's | |

| | | |10’ or a van type trailer about 13’ |eyes about 14' - 17' off the water. | |

| | | |high.  Is City Light suggesting they | | |

| | | |want the cab of this boat 15’ - 20’ | | |

| | | |off the water? | | |

|37 |11/3/09 | |Regarding Letter of Credit:  Our bank |Answer pending | |

| | | |is too small to be rated by Moody’s | | |

| | | |but is rated AAA by the Federal Home | | |

| | | |Loan Bank.  Will this meet your | | |

| | | |requirements? | | |

|38 |11/5/09 |11/16/09 |The electrical specifications call out|Bilge pump requirement remains |See new specifications issued via line item #48 |

| | | |for 3-2000 gph bilge pumps.  These are|unchanged | |

| | | |significant pumps that will require a | | |

| | | |good deal of power.  Please re-visit | | |

| | | |the need for pumps of this substantial| | |

| | | |capacity. | | |

|39 |11/5/09 |11/16/09 |Would you please be more specific in | | |

| | | |identifying the standard to which |ABS standards are required |See new specifications issued via line item #48 |

| | | |these boats are to be built.  The ABS | | |

| | | |standards call for a good deal more | | |

| | | |structure (and weight) than seems | | |

| | | |necessary for boats of this size and | | |

| | | |duty requirements.  USCG regulations | | |

| | | |do not cover vessels of this small | | |

| | | |size and application, but it seems | | |

| | | |that USCG rules that apply for vessels| | |

| | | |somewhat larger than these tugs are a | | |

| | | |better fit for these particular boats.| | |

|40 |11/6/09 |11/16/09 |Regarding the bilge pumps, there is |The electrical specifications have |See revised specifications issued in line item# 48 |

| | | |other equipment specified that will |been revised. | |

| | | |draw significant amounts of electrical| | |

| | | |energy.  This includes the 40,000 BTU | | |

| | | |cabin heater and the 600,000 cp search| | |

| | | |light.  With these power needs to | | |

| | | |consider, we question whether the | | |

| | | |on-board 12 volt DC 100 amp system and| | |

| | | |the 120V AC 30 amp system are | | |

| | | |adequately sized. | | |

|41 | |11/9/09 | | |Revisions to Schedule of Events: |

| | | | | |Revised Specifications released: 11/16/09 Deadline for Questions: 11/18/09,|

| | | | | |4:00 PM |

| | | | | |Sealed Proposals Due to the City: 12/2/09, 2:00 PM |

| | | | | |RFP Interviews: Week of 12/7//09 |

| | | | | |Announcement of Successful Proposer: Week of 12/14/09 |

| | | | | |Contract Award and Start Date: Week of 12/28/09 |

|42 |11/10/09 |11/16/09 |Would the City be willing to accept a |Rudder specifications have been |See revised specifications in line item 48 |

| | | |spade style rudder instead of a pintle|revised. | |

| | | |style for both tugs? | | |

|43 |11/12/09 |11/16/09 |I can’t seem to obtain accurate |The Ross Lake access road and tunnel| |

| | | |dimensions for the 3rd tunnel |are private and not part of the | |

| | | |mentioned in the package. The only |WADOT system. Assume that a load 12| |

| | | |reference is that it is 11 ft high. We|ft wide and 11 ft tall will fit | |

| | | |need to know exact dimensions and |through the tunnel. | |

| | | |style; oval dome, square with flat | | |

| | | |ceiling, etc. WADOT can’t seem to | | |

| | | |locate it and pointed me to Whatcom | | |

| | | |county - they too have been unable to | | |

| | | |help.  I know assume that this last | | |

| | | |tunnel might be on the Skagit power | | |

| | | |property? Do you have any other | | |

| | | |information you can provide? | | |

|44 |11/12/09 |11/16/09 |Can you give us an order of priority |Propulsion specifications have been |See new specifications in line item 48 |

| | | |on the following: |revised. | |

| | | |Bollard pull | | |

| | | |Speed without barge load | | |

| | | |Speed with barge load | | |

| | | | | | |

| | | |Are the spec requirements on these | | |

| | | |items approximate or minimums? | | |

|45 |11/12/09 |11/16/09 |If 11,500 lbs bollard pull can’t be |Propulsion specifications have been |See new specifications in line item 48 |

| | | |generated with the specified engine |revised | |

| | | |horsepower ratings, do we need to | | |

| | | |increase engine size or just state | | |

| | | |what our predicted estimates are with | | |

| | | |the engine and reduction gear we | | |

| | | |choose? | | |

|46 |11/12/09 |11/13/09 |Per RFP, page 5, |The subcontractor is required to |See RFP, page 5, “Subcontracts/Assignment”, replace the paragraph with the |

| | | |“Subcontracts/Assignment” – Are the |carry insurance that is appropriate |following Language: |

| | | |sub contract required to carry the |to their scope of work that they are|Assignment and Subcontracting |

| | | |same insurance? |performing. |Contractor shall not assign or subcontract any of its obligations under this |

| | | | | |Contract without Seattle’s written consent, which may be granted or withheld |

| | | | | |in Seattle’s sole discretion. Any subcontract made by Contractor shall |

| | | | | |incorporate by reference all the terms of this Contract except for Equal |

| | | | | |Benefit provisions. Contractor shall ensure that all subcontractors comply |

| | | | | |with the obligations and requirements of the subcontract, except for Equal |

| | | | | |Benefit provisions. Seattle’s consent to any assignment or subcontract shall|

| | | | | |not release the Contractor from liability under this Contract, or from any |

| | | | | |obligation to be performed under this Contract, whether occurring before or |

| | | | | |after such consent, assignment, or subcontract. |

|47 | |11/13/09 | | |Revisions to Schedule of Events: |

| | | | | |Revised Specifications released: 11/16/09 Deadline for Questions: 11/23/09,|

| | | | | |4:00 PM |

| | | | | |Sealed Proposals Due to the City: 12/9/09, 2:00 PM |

| | | | | |RFP Interviews: Week of 12/14/09 |

| | | | | |Announcement of Successful Proposer: Week of 12/21/09 |

| | | | | |Contract Award and Start Date: Week of 01/04/10 |

|48 | |11/16/09 | | |City is issuing revised specifications for both vessels, see attached |

| | | | | |document. These new specifications modify answers previously provided in |

| | | | | |questions 13, 17 and 18. |

| | | | | |[pic] |

|49 | |11/16/08 | | |Proposal Response has been revised, see attached document. |

| | | | | |[pic] |

|50 | |11/16/09 | | |Line Item #18 above answer has been revised to the following “Sea Trials will|

| | | | | |be conducted at a freshwater location to be determined by mutual agreement of|

| | | | | |both the vendor and the City” |

|51 | |11/16/09 | | |Evaluation Criteria have been revised, see attached document: |

| | | | | |[pic] |

|52 | |11/16/09 | | |Delivery date: Preferred delivery date is revised to May 31, 2010. |