Power Transformer 115kV/12.47kV

One-hour, 3-phase induced potential and corona test shall be performed. The first test voltage to be applied shall be 182 kV rms phase-to-phase and an enhancement voltage level of 208 kV with the transformer set on the maximum DETC tap. The test voltage shall be applied for a period of one (1) hour. ................
................