The cost performance index (CPI) is a measure of the cost efficiency with which the project is being performed. The formula for determining the CPI is Cost performance index = F(Cumulative earned value, Cumulative actual cost) CPI = F(CEV,CAC) In the packaging machine project, the CPI as of week 8 is given by. CPI = F($54,000,$68,000) = 0.79 ................
................