MDLF EE PROCUREMENT MANUAL

Based on the lowest first cost method, Bidder 3 would have won the contract. However, the power rating of the appliance provided by Bidder 4 being lower, the annual and the lifetime energy costs of Bidder 4 are the lowest. The energy cost being a significant percentage of the total LCC, Bidder 4 would win the bid if the lowest LCC method is used. ................
................