TENANT INFORMATION HANDBOOK - Simon



[pic]

[pic]

REV 7/20/22

VACAVILLE PREMIUM OUTLETS

Tenant Manual

Table of Contents

GENERAL PROJECT INFORMATION

• Project Fact Sheet

TENANT IMPROVEMENT CONSTRUCTION INFORMATION

• Tenant Improvement Construction Information

• Food Tenant Design Requirements

To obtain a copy of the Tenant Handbook, Contractor Rules & Regulations, Storefront Criteria & Signage Criteria, please go to and follow the steps below:

• Click on the ‘BUSINESSES’ tab along the top right.

• Type the name of your property in the ‘Search by Property Name or Location’ search engine, and select from the drop down menu.

• This link will lead you to the Property Overview page.

• Scroll down, and look for the Tenant Info Package link along the right hand side. This link contains the Tenant Manual, Sign Criteria & Site Specific Manuals.

VACAVILLE PREMIUM OUTLETS

PROJECT FACT SHEET

LANDLORD: SIMON Premium Outlets

60 Columbia Road

Bldg. B, 3rd Floor

Morristown, NJ 07960

Phone (973) 228-6111

MANAGEMENT Vacaville Premium Outlets

OFFICE ADDRESS: 321-2 Nut Tree Road

Vacaville, CA 95687

Phone (707) 447-2255

Fax (707) 447-5946

(Project is in City of Vacaville within the County of Solano.)

VACAVILLE PREMIUM OUTLETS

Tenant Improvement Construction Information

1. All tenants are required to provide Landlord with one (1) electronic set (PDF/DWG) for the plan review/approval process. You can email the file directly to SimonPOTenantPlans@. Your tenant improvement drawings must be approved by Landlord prior to commencing work. Please allow 5-10 working days for Landlord review.

2. Please note that Tenant is required to provide Landlord with one (1) electronic (PDF/DWG) set of as-built tenant improvement drawings, including any plan check corrections or engineered plans, upon completion of the store construction.

3. All tenant contractors must provide Landlord with an original signed copy of the Construction Rules. The tenant contractor obtaining the tenant improvement permit is the contractor responsible for submitting all required information and certificates of insurance to the Landlord.

4. Due to structural engineering design of the roof system, Tenants and/or their contractors cannot attach to or construct anything on the bottom of the roof structure unless approved by Landlord.

5. Prior to designing its tenant improvement plans, Tenants must verify all applicable State of California and Building and Fire Codes. Verify the applicable California Fire Sprinkler Code and "Hazard level" classification for Tenant's merchandise, and Tenant's intended stockroom shelving design. Tenants are responsible for all changes to the existing fire sprinkler system, including any upgrades required to increase fire sprinkler coverage. Verify intended stockroom shelving design and seismic calculations related to California Building Code. Tenants are advised to consult with their California licensed architect on the local jurisdiction requirements and on all building code issues

ASBESTOS!!!!

The local City, County, State of California or other local jurisdiction will require incoming Tenants to provide an asbestos survey as part of Tenant’s building permit submittal package. New reports are required, as any/all prior reports will not be accepted! There are also no waivers granted. As this asbestos survey would be a requirement for Tenant to obtain its TI permit, said survey is Tenant’s responsibility. Tenant should contact Tenant Manager immediately if any asbestos material is discovered during its survey.

Tenant Improvement Construction Information

6. The address for Vacaville Premium Outlets is as follows:

Vacaville Premium Outlets

(Street Address) Nut Tree Road

Vacaville, CA 95687

Please use your individual address number for deliveries!! Contact the management office to confirm your specific address. DO NOT have deliveries of store supplies or your tenant improvement construction materials made prior to your store turnover date. A representative of your company must be onsite to receive any deliveries for your store. The Landlord cannot accept any deliveries for your store. No provision has been made for on-site storage until your suite is ready for turnover.

7. KNOX BOXES - Local jurisdiction requires keys to every suite be placed in Knox boxes. Please make certain you have an extra key(s) made to meet this requirement. NO waivers allowed!

8. Tenants and their contractors will be responsible for removal of all construction and store set up debris generated from their tenant improvement construction. A trash bin must be ordered from landlord required local hauler and location of the bin must be approved by the General Manager prior to drop off.

9. Tenants are to order their utility services (electricity, gas and telephone) to begin on their turnover date or their construction start date, whichever is the earlier.

10. Tenant shall make application for electrical service in Tenant’s name prior to start of Tenant’s work. If permanent electrical meters are not installed prior to start of tenant improvement construction, Tenant’s electrical contractor shall be responsible to provide temporary power and lighting for the Demised Premises, per code, with ground fault protection. Upon completion of the permanent system of electrical power furnished by the Landlord, Tenant’s contractor may utilize the permanent power from the Tenant’s panelboard.

11. All Tenants must provide regular maintenance for their HVAC system. Each Tenant is to provide a copy of their maintenance contract to the General Manager within one (1) month of their turnover date.

12. Protection for the HVAC unit(s) (construction filter) must be in place prior to the start of Tenant’s construction. The HVAC unit must also be cleaned when tenant construction is complete. This is the responsibility of Tenant, NOT the Landlord. If painting ceiling, HVAC unit must be off – not running.

13. Relocation of thermostat controls shall be at the Tenant’s expense and any repairs or failed installations resulting from incomplete or inadequate relocation shall be the Tenant’s responsibility.

Tenant Improvement Construction Information

14. KIOSK STRUCTURE CHANGES: Tenants are to submit preliminary design drawings ONLY and should not commence working drawings until the design is approved by Landlord.

15. A one-hour, fire rated exit corridor is typically required per current State of California and Building and Fire Codes if the sales area of your space is larger than 1500 square feet. The width of fire corridor must be adequate to meet ADA code requirements. Tenants are advised to consult with their California licensed architect on this and all building code issues.

16. The City of Vacaville requires a building permit for all tenant improvement construction. Your architect or contractor will need to submit three (3) complete sets of tenant improvement plans. You will need to allow at least four (4) weeks for the plan check and permit issuance of your tenant improvement plans.

17. Your tenant improvement plans must be stamped and signed by an architect licensed in the State of California prior to applying for a building permit. If you or your architect have any questions, please contact the City of Vacaville Building Department at 650 Merchant St., Vacaville, CA 95688, (707) 449-5152. A list of architects is included in this section.

18. All contractors and their sub-contractors performing work within your store must have a valid State of California Contractors License. Applications for said license can be obtained from the State of California Contractors License Board, 9835 Goethe Road, Sacramento, CA 95826. The phone number is (800) 321-2752.

19. A Business License will be required for all Tenants, Contractors, and their Subcontractors working in the city. The City of Vacaville issues the business license. Please call them to request the type and cost of your business license. The City of Vacaville Building Department requires each tenant contractor to provide a list of all sub-contractors working in that store and their business license numbers. The city requires this form to be completed prior to issuance of tenant's certificate of occupancy and before the store opens.

NOTE: City of Vacaville Building Dept. may require an asbestos survey for Tenant’s suite as part of the building permit submittal package. As this asbestos survey would be a requirement for Tenant to obtain its TI permit, said survey is Tenant’s responsibility. Tenant should contact Tenant Manager immediately if asbestos material is discovered during its survey.

20. Burglar Alarms/Perimeter Intrusion Security Devices – All such devices must be approved by the Landlord prior to installation, including application of “riot glass” or any type of film to doors and/or windows. No exterior alarms, strobe lights or other enunciator devices may be mounted on storefronts. Due to potential interference with the Center’s fire alarm system, “Smoke Cloak” or similar systems, which generate smoke, are prohibited. Application of any decals to storefronts referencing security protection must be done in compliance with the Storefront Criteria.

21. A Tenant may not open for business without a signed, executed lease.

Tenant Improvement Construction Information

22. Visitor Name Badges

No contractor is allowed on our property without wearing a visitor badge. A contractor may pick up badges for his entire crew at the mall office. These badges self destruct within 24 hours, thus every day you must get new ones. Everyone working in the suite must wear a badge. If security sees and expired badge, you will be asked to obtain a new one at the office before any other work can be performed.

23. Landlord strongly prefers the use of ENERGY STAR products and/or equipment whenever possible during Tenant design & build out, which can reduce energy consumption. For additional information, please visit: products

VACAVILLE PREMIUM OUTLETS

Food Tenant Design Requirements

Below is the minumum design requirements that must be used by ALL Food and Food Court Tenants for all kitchen prep areas.

This requirement is to prevent any mositure or dampness penetrating the demising wall(s) that can lead to damage to the food space and/or adjoining spaces.

Demising and/or concrete walls:

1. Demising walls must be moisture resistant gypsum board w/ Sporgard™ (National Gypsum) on metal studs. Other wall options acceptable by landlord would be Hardibacker prior to installing wall finishes or Ultracode drywall, by USG.

All concrete walls, rear or demising, must be furred out with the above specs, no exceptions.

2. Install water proof membrane a minumum of 24” above floor.

3. FRP applied to all walls to a minumum height or 48” above wall base tile, and caulked with a silicone sealant.

4. Metal or PVC corner guard must be applied to all corners and caulked with a silicone sealant.

Flooring area:

1. Floor tile and flooring base installed must be sealed. This application should be re-applied semi-annually.

2. Floor drains must be installed in any food preparation area that require cleaning methods of hosing or washing walls. It is the tenant responsibility to make certain that all flooring is sloped for proper drainage to the floor drain(s).

Tile/Grout: Must have Durock and /or equal applied to studs.

................
................