San Diego Unified School District
San Diego Unified School District
Project Stabilization Agreement (PSA)
Pre-Job Conference Form
|General Contractor Information |
|Prime Contractor: Soltek Pacific Construction |
|Address: 2424 Congress Street, San Diego, CA 92110 |
|Phone: (619) 296-6247 |
|Fax: (619) 296-5761 |
|Contractor’s License Number: 886641 |
|Project Information |Meeting Information |
|Project Name: O’Farrell Charter School |Meeting Date: 12/17/14 |
|Contract Number:CZ-15-0292-57 |Meeting Time: 11:00 a.m. |
|Contract Amount: $18,376,200 |Meeting Location: |
| |IBEW Training Facility |
| |4675 Viewridge, Suite 101 |
| |San Diego, CA 92123 |
|Construction Start Date: 11/24/14 | |
|Construction End Date: 12/1/15 | |
|The Scope of Work to Be Performed |
| |
|General Contractor – No Work To Be Performed. |
| |
|Equipment to Be Utilized on Job |
| |
| |
| |
|Jobsite Information |
|Address: 6130 Skyline Drive, San Diego, CA 92114 |
|Phone: To Be Determined |Jobsite Labor Rep: N/A |
|Fax: To Be Determined |Jobsite Safety Rep: Mike Hagler |
|Project Manager: Robert Thompson |Manpower to be Ordered By: N/A |
|Job Superintendent: John Robbins | |
|Jobsite Scheduling Information |
|Number of Shifts: One Shift |Start / Stop Times: 7:00 a.m. to 3:30 p.m. |
|Pay Day: N/A |Ending Day of Pay Period: N/A |
|Jobsite Facilities |
|Location(s) of First Aid Facilities: In Job Site Trailer |
|Location(s) of Sanitary Facilities: On Job Site |
|Location(s) of Drinking Water Facilities: In Job Site Trailer |
| Description of Jobsite Parking: Parking To Be Determined |
|Name of Selected Hospital: US Health Works |
|Address: 102 Mile of Cars Way, National City, CA 91950 |
|Phone Number: 619-474-9211 |
|Manpower Estimates |
|Craft |Peak |Average |
|Boilermakers | | |
|Bricklayers | | |
|Carpenters |11 |7 |
|Cement Mason |6 |6 |
|Drywall Finishers |15 |6 |
|Electricians |8 |4 |
|Elevator Constructors | | |
|Fire Sprinkler Fitter | | |
|Floor Covers |3 |2 |
|Glaziers | | |
|Heat and Frost Insulators |4 |3 |
|Iron Workers |9 |11 |
|Laborers | | |
|Landscape, Irrigation, Underground and Specialty | | |
|Piping | | |
|Laborers’ International Union of N.A. Highway & |13 |8 |
|Street Stripers’ | | |
|Operating Engineering |18 |12 |
|Painters |5 |3 |
|Pipefitters | | |
|Plumbers |7 |4 |
|Sheet Metal Workers |10 |5 |
|Plasterers | | |
|Plaster Tenders | | |
|Roofers and Water proofers |9 |8 |
|Teamsters |2 |1 |
|Tile / Marble / Terrazzo | | |
T
|Referrals and Jurisdictional Assignments |
|Referral procedures will be in accordance with Article 3 of the Project Stabilization Agreement. We ask the unions to have these referral procedures|
|posted at their hiring halls cx xin order to be in full compliance with the law. |
| |
|All work assignments below are proposed assignments. Any craft in disagreement with proposed assignments may submit written documentation, within 14|
|days after the Pre-job Conference, to justify their claim to the work involved. The contractors will review all responses, if any. |
| |
|After the review, the contractor(s) shall make all assignment permanent. Any craft who has a disagreement with these final assignment(s) may file a |
|jurisdictional dispute consistent with Article 8, Work Assignments and Disputes of the Project Stabilization Agreement. |
|Jurisdictional Assignments |
|Type of Work |Work Assignment |
|Rough Carpentry-Abdellatif |Southwest Carpenters Local 547 |
|HVAC Sheet Metal Ductwork-Able Heating |SMWIA Local 206 |
|HVAC Equipment on Roof-Able Heating |Operating Engineers Local 12 |
|HVAC Ductwork-Able Heating |Heat & Frost Local 5 |
|Test & Balance-Able Heating |SMWIA Local 6 |
|Plumbing and Site Utilities-Advance Plumbing |Plumbers/Pipefitters 230 |
|Equipment Operation |Operating Engineers 12 |
|Hot Water Insulation |Heat & Frost Local 5 |
|Metal Decking-Anning Johnson |Iron Workers Local 229 |
|Testing, Adjusting, Balancing-Assoc Air Balance |Sheet Metal Local 105 |
|Electrical-Baker Electric |Local IBEW 569 |
|Trenching-Baker Electric |Operating Engineers Local 12 |
|Install Chainlink and Gates-FenceCorp. |Laborers Local 801 |
|Dig Holes-FenceCorp. |Operating Engineers Local 12 |
|Grading-FJ Willert |Operating Engineers Local 12 |
|Water Trucks-FJ Willert |Teamsters Local 36 |
|Laborers-FJ Willert |Laborers Local 89 |
|Metal Framing and Drywall-Johnson Finch & McClure |SW Regional Carpenters Local 547/1506 |
|Lath and Plaster-Johnson Finch & McClure |Plaster Tenders of SoCal Local 1414 |
|Waterproofing Membrane and Install-King Construction |Roofers/Water Proofers Local 45 |
|Doors-McKernan |Carpenters 547 |
|Drilling Caissons-Pacific Drilling |Operating Engineers Local 12 |
|Electrical-Power Plus |IBEW-Electrical Workers Local 569 |
|Masonry-Precision Masonry |Bricklayers & Allied Craftsman Local 4 |
|Masonry-Precision Masonry |Laborers Local 89 |
|Reinforcing Steel-Quality Reinforcing |Ironworkers Local 229 |
|Paving-RAP Engineering |Operating Engineers Local 12 |
|Paving-RAP Engineering |Laborers Local 89 |
|Install Wood Floors-Roy’s Flooring |Southwest Carpenters Local 547 |
|Refinish Gymnasium Floor-Roy’s Flooring |Floor Covers Local 1399 |
|Walking Canopies-Sal Cal Constr. |Iron Workers Local 229 |
|Gymnasium Columns, Roof Framing-Sal Cal Constr. |Iron Workers Local 229 |
|Installation of Forms-SD Steel Solutions |Southwest Carpenters Local 547 |
|Placement of Concrete-SD Steel Solutions |Cement Mason Local 500 |
|Grading, Clean-Up-SD Steel Solutions |Laborers Local 89 |
|Earth Moving-SD Steel Solutions |Operating Engineers Local 12 |
|Install Insulation-Scot-Therm Insulation |Heat & Front Local 5 |
|Panels and Devices, Pulling Wire, Assembling Fire Alarm and Security |Soundman IBEW Local 569 |
|Systems-Simplex Grinnell | |
|Instrumentation and Controls for HVAC-Sunbelt |Local 230 |
|Roofing-Sylvester Roofing |Roofers Water Proofers Local 45 |
|Interior/Exterior Painting-Triumph Painting |Painters Local SCPC 775 |
|Low Voltage System-World Bridge |Soundsman Local 569 |
|Construction surveying-XYZ Consulting |Party Chief Local 12 |
| | |
|Subcontractors to Be Utilized |
|Subcontractor Name: ABDELLATIF Enterprises, Inc. |
|Type/Scope of Work: Carpentry |
|Address: 26400 La Alameda, Mission Viejo, CA m 92694 |
|Phone Number: 949-215-4790 |License Number: 662128 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Hazem Abdellatif |
| |
|Subcontractor Name: Able Heating & Air Conditioning |
|Type/Scope of Work: HVAC |
|Address: 1020 Colorado Avenue, Suite A, Chula Vista, CA 91911 |
|Phone Number: 619-409-9100 |License Number: 466861 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Andrew Moreno |
| |
|Subcontractor Name: Advance Plumbing Co. |
|Type/Scope of Work: Plumbing |
|Address: 9423 Bond Avenue, El Cajon, CA 92022 |
|Phone Number: 619-447-4770 |License Number: 272557 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Mike Shrivanek |
| |
|Subcontractor Name: Anning-Johnson Company |
|Type/Scope of Work: Steel Deck |
|Address:13250 Template Avenue, Industry, CA 91746 |
|Phone Number: 626-369-7131 |License Number: 652825 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Emilio Armenta Jr. |
| |
|Subcontractor Name: Baker Electric, Inc. |
|Type/Scope of Work: Electrical |
|Address: 1298 Pacific Oaks Place, Escondido, CA 92029 |
|Phone Number: 760-745-2001 |License Number: 161756 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Todd Poelstra, Sr. |
| |
| |
|Subcontractor Name: FenceCorp. |
|Type/Scope of Work: Chain Link Fencing |
|Address: 2401 Industry Street, Oceanside, CA 92054 |
|Phone Number: 760-721-2101 |License Number: 886544 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Brian Jarvis |
| |
|Subcontractor Name: F.J. Willert Contracting Co., Inc. |
|Type/Scope of Work: Earth Work/Demolition |
|Address: 1869 Nirvana Avenue, Chula Vista, CA 91911 |
|Phone Number: 619-421-1980 |License Number: 402473 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Brian Fathera |
| |
|Subcontractor Name: Johnson Finch & McClure Construction, Inc. |
|Type/Scope of Work: Plaster and Gypsum Board |
|Address: 9749 Cactus Street, Lakeside, CA 92040 |
|Phone Number: 619-938-9727 |License Number: 3932277 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Gary Berger |
| |
|Subcontractor Name: King Construction |
|Type/Scope of Work: Sheet Waterproofing |
|Address: 1155 Oak Avenue, Carlsbad, CA 92008 |
|Phone Number: 760-720-5201 |License Number: 716883 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Mike Hammond |
| |
|Subcontractor Name: McKernan Contractors Inc. |
|Type/Scope of Work: Door, Frames and Finish Hardware |
|Address: Post Office Box 8984, Redlands, CA 92375 |
|Phone Number: 909-307-5650 |License Number: 913333 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Bryan McKernan |
| |
| |
|Subcontractor Name: Power Plus |
|Type/Scope of Work: Temporary Power |
|Address: 436 North Quince Street, Escondido, CA 92025 |
|Phone Number: 760-839-9430 |License Number: 980589 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: John Downey |
| |
|Subcontractor Name: Precision Masonry Builders, Inc. |
|Type/Scope of Work: Masonry |
|Address: 9880 Magnolia Avenue, Suite 363, Santee, CA 92071 |
|Phone Number: 619-749-6543 |License Number: 903167 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Blasé Anzalone Jr. |
| |
|Subcontractor Name: Quality Reinforcing Inc. |
|Type/Scope of Work: Concrete Reinforcement |
|Address: 13275 Gregg Street, Poway, CA 92064 |
|Phone Number: 858-748-8400 |License Number: 683317 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Tim Pitner |
| |
|Subcontractor Name: RAP Engineering, Inc. |
|Type/Scope of Work: Asphalt Paving |
|Address: 420 Olive Avenue, Vista, CA 92083 |
|Phone Number: 760-233-2980 |License Number: 880956 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Robert Perez |
| |
|Subcontractor Name: Roy’s Flooring |
|Type/Scope of Work: Wood Athletic Flooring |
|Address: 13659 Victory Boulevard, #395, Van Nuys, CA 91401 |
|Phone Number: 818-982-8394 |License Number: 637480 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Roy Garcia |
| |
|Subcontractor Name: Sal Cal Construction, Inc. |
|Type/Scope of Work: Structural Steel, Pipe and Tubing, Steel Fences and Gates |
|Address: 1320 Grand Avenue #7, San Marcos, CA 92078 |
|Phone Number: 760-812-0014 |License Number: 897158 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Salvador Caldera |
| |
|Subcontractor Name: San Diego Steel Solutions Inc. |
|Type/Scope of Work: Structure and Site Concrete |
|Address: 579 Enterprise Street, Escondido, CA 92029 |
|Phone Number: 760-489-9990 |License Number: 932783 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Roberto Alvarez |
| |
|Subcontractor Name: Silver Creek Industries Inc. |
|Type/Scope of Work: Modular Buildings |
|Address: 2830 Barrett Avenue, Perris, CA 92571 |
|Phone Number: 951-943-5393 |License Number: 855259 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Sandra Adame |
| |
|Subcontractor Name: Simplex Grinnell |
|Type/Scope of Work: Fire Alarm |
|Address: 3568 Ruffin Road South, San Diego, CA 92123 |
|Phone Number: 858-633-9080 |License Number: 986047 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Mark Walker |
| |
|Subcontractor Name: Sunbelt Controls Inc. |
|Type/Scope of Work: HVAC Controls |
|Address: 9570 Ridgehaven Court, Suite B, San Diego, CA 92123 |
|Phone Number: 858-292-8642 |License Number: 800423 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Jon Rice |
| |
|Subcontractor Name: Sylvester Roofing Co., Inc. |
|Type/Scope of Work: Roofing |
|Address: 306 West El Norte Parkway, Suite N, Escondido, CA 92026 |
|Phone Number: 760-743-0048 |License Number: 516696 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Tony Naffuto |
| |
|Subcontractor Name: Triumph Painting & Coatings |
|Type/Scope of Work: Painting |
|Address: 3234 Orange Street, Riverside, CA 92501 |
|Phone Number: 951-680-9930 |License Number: 440957 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Ted Krupp |
| |
|Subcontractor Name: World Bridge Technologies Inc. |
|Type/Scope of Work: Low Voltage Work: Communication Cable, Data Comm |
|Address: 1050 Pioneer Way, Suite G, El Cajon, CA 92020 |
|Phone Number: 619-792-1260 |License Number: 848495 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Kerry Hannigan |
| |
|Subcontractor Name: XYZ Consulting, Inc. |
|Type/Scope of Work: Surveying |
|Address: 34024 Lydia Court, Temecula, CA 92592 |
|Phone Number: 951-553-0021 |License Number: PLS 8517 |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: Jay Ramos |
| |
|Subcontractor Name: |
|Type/Scope of Work: |
|Address: |
|Phone Number: |License Number: |
|Estimated Starting Date: |Estimated Ending Date: |
|Manpower to Be Order By: |
| |
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- benefits of participating
- members of the hall of fame
- application valley paving
- biographical data
- dear colleague auburn university
- road safety management global comparative analysis and
- heavy construction contractors association highlights
- san diego unified school district
- volume ii broward county public schools
Related searches
- los angeles unified school district website
- kansas unified school district map
- davis unified school district calendar
- stockton unified school district directory
- clovis unified school district calendar 2021
- riverside unified school district jobs
- stockton unified school district office
- unified school district jobs
- clovis unified school district calendar 2020
- stockton unified school district email
- chico unified school district calendar
- central unified school district calendar