2013 Summer Projects - Muni



2016 Summer Projects Completed and 2017 & Beyond projects

Winter Maintenance:

□ Applied 977 yards of traction E-chips to the service area

□ Cold patched roads that where asphalt potholing was constant from the warm and wet winter

□ Plowed and stored snow

□ Steam thaw

Spring projects:

□ Advanced pothole patching before spring grading of all dirt roads

□ Back fill lamp post in Townsquare with pea gravel to keep garbage out

□ Spring street sweeping of all paved roads, week of April 26th

□ Dust control, calcium chloride application all dirt roads, started May1st

□ Vac-truck all storm water system intakes

□ Removed Junk cars for the Fire Department

□ Brushing of bike paths and roadways shoulders

□ Crack sealed 7,111 linear feet of asphalt roads

□ Remove abandon cars around town

Fall Projects:

□ Sweep streets

□ Clean up leaves and clean out storm intakes

□ Grade and compact all roads before freeze

□ Bring in winter sanding chips

□ Grind up brushings

Airport Side:

Arlberg Avenue:

□ Patch repair road with asphalt, completed June 2016

□ Crack seal, completed June 2016

□ Grade and repair shoulders, completed June 2016

□ Clean debris out from under the guard rails to improve drainage, completed June 2016

□ Removed dirt and winter debris build up from Guardrails, completed 6-14

□ Shoulder and drainage repair, completed July 2017

□ Grind Asphalt and repaved 27,000 sq. ft. of roadway, completed 9-1-16

□ Culvert replacement or clean out and ditch clean out from 304 to 450, completed 8-30-16

Alyeska View

□ Remove old steel cross culvert between Cortina and Brighton, completed 6-24

□ Replace cross- Culvert at Cortina and Alyeska View, completed 6-24

□ RAP spread, graded and compacted at the Garmisch intersection, completed 8-18

351 Davos

□ Replace and lower driveway culvert, completed 6-24

Donnner and Davos intersection

□ Spread RAP, Grade and compact, completed 9-27-16

Cortina

□ Install new driveway culverts and ditching at 245 and 257 Cortina, completed 6-29

Alpine Meadows

□ Replace and clean up ditching at 1030 Alpine Meadows, completed 7-5-16

Mt. Hood

□ Clean out drainage area from cross culvert of Mt Hood., completed 6-18-16

Bike path

□ Crack sealing from Alyeska T to Hotel

□ Brushing on bike path, completed Spring 2016

Projects for 2017:

Arlberg

□ Repave the last two remaining section between Nina’s wall and intersection with Tram Way

□ Grade and compact shoulders to maintain drainage

Alyeska View

□ Improve drainage between Davos and Cortina

□ Brushing

Challenge/Mountain Side:

Taos

□ New driveway culverts at 200 & 224 Taos, completed June 2016

Veriber

□ Remove rock out ditch line and reshape ditch to control water, completed June 2016

□ Stabilize bank of ditch to support bike path. , completed June 2016

□ Clean around Beehive in-take and mark beehive for winter, completed June 2016

□ Vac-truck drainage system. Complete 2017

Alyeska Condo’s drainage:

□ Remove all drainage pipe that causing the ground to fail, completed 6-27

Olympic Mountain Loop

□ Installed new berms to control traffic and parking, completed 8-10-16

White Pass

□ Tied ditch into new drainage storm system inlet, completed 7-27-16

□ Removed old abandon storm system culvert behind Alyeska West Condos, completed 7-27-16

Projects for 2017:

Taos

□ Replace cross culvert at intersection of Chrystal mountain

Brighton

□ Dig out road bed and remove organic/wood material that causes constant potholing

□ Ditch both sides of the road and collect water off Chrystal Mt road to send it directly to Alyeska creek

Chrystal Mountain

□ Ditching improvements on several aspects of the road

□ Clean out cross culvert at White pass intersection

Timberline side:

Alyeska View:

□ Removed all pipe and installed new Curtain drain at 244 Alyeska View, completed 6-2

□ RAP spread, graded and compacted at the Garmisch intersection

Alpine Meadows:

□ Build new headwall on Tanka creek culvert, completed 8-8-16

Garmisch:

□ Install new drainage system from Alyeska Daylodge parking lot to Alyeska View, completed 7-22

Loveland:

□ Build new headwall on Tanka creek culvert, completed 8-9-16

Timberline

□ Asphalt pavement repair from Alyeska Highway to Church, Completed Oct 2016

Culvert markings

□ Mark major culverts, especially ones prone to freezing

172 Kitzbueal

□ New Culvert

□ Improved ditching

Timberline

□ Ditching up on the upper portion of Timberland

□ Brushing Virgin Creek to Turn

Projects for 2017 and beyond:

Alta

□ Remove old culvert closest to 260 Alta and replace with new, creates an overall drainage if the main line plugs up

Alyeska View to Higher Terrace

□ Might need another cross culvert further down the hill

□ Install curtain drain for spring water in front of 270 Alyeska View

□ Alyeska View (Northland to Upper Terrace hill needs ditching improvements)

Alpine Meadows

□ Ditching down left side between Northland and Loveland

□ Cross Culvert at corner of Megeve

□ Several Driveway culverts along this stretch

Bursiel

□ Exam glaciations problem from natural spring at Alyeska Highway, spoke with Right of Away and property owner

Deb’s Way Trailhead

□ Finish Path Improvements

□ Re-set bollards

Townsquare:

□ Brushed alders on Holgrem and park and ride, completed 8-18-16

□ Towed several junk cars, completed over the summer

□ Aphalt repair and cracksealing on all streets, especially to the school, completed June 2016

2017 Project and Beyond

Girdwood Park and Tennis court parking lot area

□ Improve drainage

□ Improve parking surface

Mine Roads:

Ruane Road

□ Brushed both sidehills on each direction of the road, completed 7-7-16

Jewel Mine Road

□ Brought in new road bed material and capped it with RAP to rise the road and improve drainage, completed 6-20-16

Gunnysack Mine and Sproat intersection:

□ New cross culvert installed, completed 8-19-16

2017 Project and Beyond

Gunnysack Mine

□ Replace culvert at intersection

□ Ditch down both sides of the hill to connect with new DOT drainage system

Sproat

□ Ditch and possible culvert replacements from Gunnysack to 383 Sproat

Old Girdwood:

West St

□ Cut back east bank of the road, straighten the road and returned road to the platted right of way, installed a 2 inch layer of recycled Asphalt, completed 8-17-16

Old Dawson:

□ Replace cross culvert at 245 Old Dawson, completed 9-19-16

□ Graded and compacted 3” of new RAP on the entire Old Dawson including the intersection at Gold, completed 9-20-16

Billy’s Alley

□ Brushed entire alley, completed 4-2-16

2017 Project and Beyond

□ Brush dike road

□ Add RAP to Main between Gold and end of road

Road maintenance industrial lot:

□ Built a new Winter chip storage out of cement blocks

□ Started the relocation of the Fire Department to their new lot

2017 Project and Beyond

□ Electric to Bull rail

□ Lights installed

□ Hydroseed

□ Build fence

□ Continue relocating GFD to their new lot

□ Continue stockpile of RAP and high quality road material as it becomes available

................
................