CONSTRUCTION SCHEDULE TEMPLATE



CONSTRUCTION SCHEDULE TEMPLATETASKSSTART DATEFINISH DATE?Surveyor staking foundation?location?(1/2 day)?Excavation and, if necessary, clearing and tree removal (1-2 days)Footing and foundation work, including time for curing concrete, installing drain tile, waterproofing, back filling, etc. (2-3 weeks)??Framing (1-3 weeks)??Roofing and flashing work, chimney installation (1-2 weeks)??Window, exterior door installation, siding, trim (2-4 weeks)Electrical,?plumbing, other rough-ins. Note that this step overlaps with step 6 (1-2 weeks)??Walls and ceilings (2 weeks)??Finish work: interior trim, doors, floors, cabinets,?painting, set fixtures, etc. (2-8 weeks)??Punch list, final inspection, etc. (1 week) ................
................