(1806) EXTENSION OF CONTRACT TIME

Jan 11, 2012 · Unless otherwise directed in writing by the Engineer, whenever an Update Schedule indicates negative Total Float greater than 5 percent of the remaining calendar days before a Milestone, but in no case greater than negative 40 working days, the Contractor shall submit, within 7 calendar days, a Revised Schedule. ................
................