MGT 3110: Exam 3 Study Guide - The University of Tennessee ...

b.The longest time sequence of activities in a project. c.when both earliest and latest times are the same. d.The difference in time length of any path and the critical path. e.The statistical distribution used to describe variability of an activity time. f.The statistical distribution used to describe path variability. ................
................