PDF Common Core Technology Project Update

[Pages:30]COMMON CORE TECHNOLOGY PROJECT UPDATE

"Helping transform teaching and learning via 21st century technology"

November 19, 2013

1

Procurement Questions

2

LOS ANGELES UNIFIED SCHOOL DISTRICT

Procurement Questions

Do we have access to Pearson content for as long as the device is still working after our Apple contract ends? What about updates to the curriculum? Are those included during the 3-year contract? Will we have to pay for that after the 3 years is up? We will need to purchase licenses after the 3-year contract expires if we want to continue to use the content.

Updates to content will be available at no cost for three years from the date of the delivery of the content. (Apple Contract Exhibit D, page 2 of 3)

Will we still get 4th gen iPad even though there is a new iPad on the market? Our contract is for the purchase of the 4th generation iPad.

Did we ask the vendors if they could retrofit the iPads so they could be connected by wire, instead of wirelessly? No, we did not.

3

LOS ANGELES UNIFIED SCHOOL DISTRICT

Procurement Questions

Can we see the names of the other vendors and curriculum options?

Proposing Vendors

? Apple, Inc. ? Arey Jones Educational Solutions ? McGraw Hill Education ? Technology Integration Group ? A+ Interactive Solutions ? AT&T ? IBM Corp ? SHI International Corp ? Manage Mobility ? Google ? MNJ Technologies ? Smarty Ants, Inc ? AVNET

Curriculum

? Pearson ? McGraw Hill Education ? Houghton Mifflin Harcourt ? Discovery Education ? Compass Learning ? Netrekker Search

4

LOS ANGELES UNIFIED SCHOOL DISTRICT

Procurement Questions

When did the three-year contract start? The first day of the rollout? July 16, 2013

How was the curriculum piece presented by various bidders? Did they say, "We'll provide X amount of lessons," or did they say, "We'll provide X amount of percent of curriculum," during Phase 1, and the rest at what point in time? Typically it was stated that "X is a comprehensive core curriculum from K-12 in ELA and Math written to CCSS. The curriculum covers the entire school year and helps prepare students for the Smarter Balanced Assessments."

Some of the Publisher's Criteria was not published, so the response we received would be stated, "Once the high school mathematics Publisher's Criteria is available the program will be developed." The RFP was issued on March 1, 2013 and the 9-12 Publishers Criteria for Mathematics was to be released in mid-2013.

5

Updates

6

LOS ANGELES UNIFIED SCHOOL DISTRICT

Number of Schools Deployed per Week

Number of School Deployed

45

42

40

40

38 36

35

30

30

26

25

21

20

15

12

10

4

5

4

8

9

5

4

6

2

0

August 26th September September September September October 7th October

9th

16th

23rd

30th

14th

2

2

October November

21st

4th

Number of Schools Per Week

Total number of schools deployed

7

LOS ANGELES UNIFIED SCHOOL DISTRICT

Number of Devices Deployed per Week

Number of Device Deployed

30,000

25,000

20,000

22,160

22,939

23,771

24,253

19,188

17,007

15,000

12,395

10,000

6,190

5,000

1,322

1,322

4,868

6,205

4,612

2,181

2,972

779

--

Aug. 26 Sept. 9 Sept.16 Sept. 23 Sept. 30 Oct. 7 Oct. 14

832

Oct. 21

482

Nov. 4

Number of Devices Deployed per Week

Total Number of Devices Deployed

8

................
................