Data Center Design Guidelines

The UPS and standby generator will each have a capacity no less than ten percent greater than the maximum possible electrical load in the Data Center. When the Data Center is at full load, the UPS must run for a minimum of twenty minutes and the generator must run for a minimum of eight hours without refueling. 4.2 Monitoring Lights ................
................