Preparing and Presenting Cost Estimates for Projects and ...
Financial Management Technical Guidance Note
Lanka February 2014
Preparing and Presenting Cost Estimates for Projects and Programs Financed by the Asian Development Bank
ABBREVIATIONS
ADB ADF CPS DMC DMF eC-LAS EMP ERD FCDI IDC LAR LIBOR OCR PAI PAM PCR PPAR PPP PPTA RRP SAI TOR USD VAT
? Asian Development Bank ? Asian Development Fund ? country partnership strategy ? developing member country ? design and monitoring framework ? enhanced calculator for loan accounting and servicing ? environmental management plan ? Economics and Research Department ? financial charges during implementation ? interest during construction ? land acquisition and resettlement ? London interbank offered rate ? ordinary capital resources ? project administration instruction ? project administration manual ? project completion report ? project performance audit report ? purchasing power parity ? project preparatory technical assistance ? report and recommendation of the President to the Board ? supreme audit institution ? terms of reference ? United States dollar ? value-added tax
GLOSSARY
Cap or interest rate cap. A ceiling that sets an upper limit for a floating interest rate. Collar or interest rate collar. A combination of a ceiling and a floor that set an upper
and lower limit for a floating interest rate. Components. A collection of costs grouped for finance or administrative purposes
(e.g., a wastewater treatment plant, or road rehabilitation and upgrading). Components are not necessarily outputs. Country cost-sharing ceilings. Financing parameters that indicate the maximum share of aggregate costs ADB will finance with respect to the portfolio of projects in a DMC, over the period of the prevailing CPS for that DMC. Expenditure category. The classification of project inputs according to expenditure type. Expenditure categories might include civil works, equipment and materials, land acquisition and rights-of-way, recurrent costs, and consulting services. Financial charges during implementation. The interest, commitment charges, and premium on cap and collar, if any, on ADB loans or loans from cofinanciers to an ADB-financed project. Financing plan. The financing plan will identify the different sources of financing for the project, the amounts to be provided by each financier, and the overall percentage of total project cost that each financier will finance. The summary financing plan is included in the report and recommendation of the President.
Foreign exchange costs. The sum of (i) direct foreign exchange costs--payments made in currencies other than the currency of the borrower for goods and services; and (ii) indirect foreign exchange costs--the cost of the imported components of goods, works, and services purchased locally. Some examples are the cost of petroleum products used on a construction site and purchased locally, the cost of imported iron ore in locally manufactured and processed steel, and the depreciation cost of imported machinery in manufacturing cement produced locally.
Implementation period or construction period. The period of project implementation; it is also the period before major benefits of the project begin to accrue.
Local currency costs. The local currency value of all goods and services that are procured for the project within the country, and which exclude indirect foreign exchange costs.
Nominal prices. The expression of monetary amounts (revenues and costs) in future price values that include the effects of expected general price inflation.
Outputs. The physical and/or tangible goods and/or services delivered by the project. Physical contingency. An allowance to reflect possible increases in the base cost
estimates of a project due to changes in quantities, methods, and/or implementation period. Price contingency. An allowance to reflect forecast increases in the base cost estimates of a project due to changes in unit costs for the various components and/or elements after the date of the preparation of base cost estimates. Purchasing power parity. The theory that exchange rates between currencies are in equilibrium when their purchasing power is the same in each of the two countries. As a result, the exchange rate between two countries should equal the ratio of the two countries' price level of a fixed based basket of goods and services. Therefore, to maintain equilibrium, the exchange rate between two countries will change by the ratio in the inflation rates between these two countries. Real prices. The expression of monetary amounts (revenues and costs) in which any expected change in the general price level is omitted. When applied to project costs, all costs are expressed on the price basis prevailing as of a single date. Expected changes in relative prices are incorporated into the cost estimates through the application of price contingencies. An alternative expression for real prices is "constant prices". Recurrent costs. Costs incurred during project implementation for goods and services consumed during a budget year, and which must be regularly replaced. Retroactive financing. ADB's financing of expenditures incurred and paid for by the borrower of loan or recipient of grant financing before the related loan, grant, or technical assistance letter of agreement becomes effective. Taxes and duties. For cost estimates' purposes, local taxes and duties include valueadded tax (VAT), gross sales taxes (GST), customs charges, import tariffs, and other similar types of taxes and duties that are identifiable and determinable as the final tax amount at the time of transaction. Local taxes and duties exclude income taxes and other taxes and duties that are not identifiable and determinable as a final tax amount at the time of transaction.
CONTENTS
Page
I.
PURPOSE
1
II. COST ESTIMATES: GUIDING PRINCIPLES AND STRUCTURE
1
A. Introduction
1
B. Guiding Principles
2
C. Main Project Cost Elements
3
D. Base Cost Estimates
3
E. Contingencies
6
F. Financial Charges During Implementation
7
III. PREPARING, REVIEWING, MONITORING AND UPDATING THE COST ESTIMATES 11
A. Steps for Preparing the Cost Estimates
11
B. Reviewing Cost Estimates
12
C. Monitoring and Updating Cost Estimates
13
D. Reporting Cost Estimates at Completion
14
IV. PRESENTING THE COST ESTIMATES
15
A. Presenting the Summary Cost Estimates in the Report and Recommendation of
the President
15
B. Presenting Detailed Cost Estimates in the Project Administration Manual
15
C. Presenting Cost Estimates in the Project Completion Report
15
D. Other Presentational Requirements
16
V. PREPARING AND PRESENTING FINANCING PLANS
16
A. Preparing the Summary Financing Plan
16
B. Presenting the Financing Plan
17
VI. CONCLUSION
17
APPENDIXES
1. References
18
2. Example of Cost Analysis Categories for an Infrastructure Project
19
3. Computing Price Contingencies
21
4. Project Cost Estimates Review Checklist
23
5. Example of an Expenditure Monitoring Report
26
I.
PURPOSE
1. This Technical Guidance Note has been prepared in response to ADB's Procurement Governance Review1 (PGR). The PGR concluded, among other things, that the quality of cost estimates for ADB-financed sovereign-guaranteed projects was affected by a lack of sufficient guidance on preparing, reviewing and monitoring cost estimates throughout the project cycle. The purpose of this note is to provide guidance to executing agencies, consultants, and ADB staff on preparing and maintaining cost estimates, and how cost estimates should be presented in ADB documents. The note offers an approach and methodology, based on international good practice, that if consistently applied should lead to the preparation of more robust cost estimates and should facilitate oversight of ADB-financed projects.
II.
COST ESTIMATES: GUIDING PRINCIPLES AND STRUCTURE
A. Introduction
2. A cost estimate approximates a project's probable cost. Cost estimates are prepared at concept stage, refined throughout the project-preparation process, and updated during implementation (see Figure 1). The cost estimate should identify those principal cost
components needed to support effective project management (including monitoring of costs and physical progress during implementation). Cost estimates, for ADB purposes, should be prepared using a commercially available spreadsheet package.2
Figure 1. Evolution of Cost Estimates during the Project Life Cycle
Project Identification
Project Concept
Preparation/
Due Diligence
Detailed Design
Implementation
Completion
? Prepare "ballpark" estimate of costs and financing requirements
? Prepare initial cost estimate and financing requirements
? Prepare and review feasibility study
? Identify cost structure (outputs, components, categories)
? Develop procurement plan
? Estimate contingencies and financial charges during implementation
? Refine cost estimates and financing arrangements
? Update procurement plan
? Prepare bidding documents
? Further refine cost estimates
? Update procurement plan
? Monitor and report actual costs against estimates
? Update cost estimates and financing arrangements
? Assess actual costs against cost estimates (accuracy and efficiency)
1 ADB. 2013 Procurement Governance Review. Manila. 2 A group of institutions led by the African Development Bank is considering supporting the redevelopment or
replacement of the COSTAB cost estimation application, which was formerly used by ADB and World Bank.
2
B. Guiding Principles
3. Ownership. Project cost estimates should be prepared from the perspective of the project and therefore the borrower. Cost estimates should be sufficiently detailed and constructed to facilitate project financing and enable effective implementation.
4. Local currency basis. Detailed cost estimates should be prepared in local currency units.3 Borrowers normally have a better appreciation of costs expressed in their local currency and the budgetary implications of the project will be more relevant. Preparing cost estimates in local currency units will also facilitate project monitoring and supervision as project accounting systems and financial reports are likely to be maintained in local currency units. Expressing the costs in local currency is also required for the purposes of their incorporation into the economic analysis and project entity financial projections. Project costs are translated into USD equivalents, summarized, and presented in the report and recommendation of the President (RRP).4
5. Using government accounting systems. As much as possible, project expenditures should be categorized using the government's regular chart of accounts and accounting system. When determining how to structure and present project cost estimates, it is necessary to consider the structure and capabilities of the government's accounting system.
6. Foreign exchange and local currency cost. The underlying project cost estimates should differentiate between foreign exchange and local currency costs5 as: (i) component prices are likely to vary between local and international markets, taking into consideration, among other things, varying tax rates between import and local sales taxes, freight, customs, etc; (ii) computation of price contingencies may differ according to currency; (iii) having the detailed assumptions underlying the cost estimates will facilitate project management; and, (iv) this approach could highlight the extent to which the project could be susceptible to foreign exchange risks during implementation.
7. Timeliness. If the date of the cost estimates is:
(i) less than 6 months before the project is presented to ADB's Management or Board, the cost estimates are acceptable;
(ii) 6?12 months before presentation, the cost estimates should be revised by indexation6, unless the project team concludes that the base cost has not changed materially in the intervening period; or
3 However, the detailed cost estimates may be prepared in foreign currency units (e.g., USD) where (i) costs are expected to be predominantly in direct or indirect foreign exchange costs; (ii) there is no reliable and accurate reference domestic price (e.g., new technologies); (iii) market exchange rates are substantially different from official exchange rates; and/or (iv) domestic inflation rates are high, unstable, and unpredictable, and exchange rates are difficult to estimate with confidence. In such cases, guidance should be sought from ERD and/or OSFMD.
4 In this document, unless stated otherwise, "RRP" refers also to periodic financing requests and additional cofinancing papers.
5 This is a continuation of current practice. The underlying cost estimates model or spreadsheet should include a differentiation between foreign exchange and local currency costs, however this breakdown is not required to be presented in the RRP, but only in one PAM cost estimates table: Detailed Cost Estimates by Expenditure Category.
6 A simple escalation factor, reflecting actual price changes since the date of cost estimates, should be applied to the base cost estimates.
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- preparing and presenting cost estimates for projects and
- electric production cost modeling
- downtime cost and reduction analysis survey results
- the cost of digital printing in newspaper production
- introduction to cost modeling template overview for
- industrial hemp seed production costs and returns in
- sample costs to produce rice university of california davis
- teaching students the production cost report an
Related searches
- youtube woodworking projects and plans
- wood craft projects and ideas
- analysts estimates for ge stock
- preparing for colonoscopy and endoscopy
- direct and indirect cost analysis
- direct and indirect cost accounting
- direct and indirect cost examples
- preparing for test and exams
- grants for projects in africa
- food and beverage cost control 6th edition
- food and beverage cost control
- food and beverage cost formulas