| |1. |A landscape area measures 120’x 240’. How many square feet are in the area? |

| | |200 |

| | |28,800 |

| | |4,320 |

| | |24,400 |

| | | |

| |2. |The plans call for a concrete walk to be installed. The walk is 4’ wide and 75’ long. If the concrete is poured 4” deep, how many cubic |

| | |yards of concrete is needed? |

| | | |

| | |3.7 |

| | |27 |

| | |99.9 |

| | |300 |

| | | |

| |3. |A lawn measures 85’x 150’. If you were seeding this lawn at the rate of 4 pounds of seed per 1,000 sq. ft., how many pounds of seed would |

| | |be needed? |

| | | |

| | |12.5 |

| | |40 |

| | |3.2 |

| | |51 |

| | | |

| |4. |If a soil test report recommends one pound of nitrogen per 1,000 sq. ft., how many pounds of 6-12-18 are needed for a 5,000 sq. ft. area? |

| | | |

| | |30 |

| | |3.5 |

| | |41.6 |

| | |27.7 |

| | | |

| |5. |Two customers are shopping for one cubic yard of pine bark nuggets. Pine bark is sold at the rate of $20 per cubic yard (bulk rate), or |

| | |$3.00 per bag of pine bark nuggets (3 cu. ft.) How much cheaper is it to buy the nuggets by the bulk? |

| | | |

| | | |

| | |$20.00 |

| | |$9.00 |

| | |$7.00 |

| | |$27.00 |

| | | |

| |6. |How many ounces of Roundup do you mix in a 4 gallon solo backpack sprayer, if the rate is a 2% solution? |

| | | |

| | |5.12 |

| | |7.45 |

| | |8.48 |

| | |10.24 |

| | | |

| |7. |If a bale of pine straw will mulch an area of 50 sq. ft., how many bales are required to mulch a project that has 3,000 sq. ft. of bed |

| | |space? |

| | | |

| | |20 |

| | |40 |

| | |60 |

| | |80 |

| | | |

| |8. |The Materials and Labor Costs for a landscape project is $2,500. In addition, the landscaper will add a 10% Overhead Costs and a 25% Profit|

| | |Allowance to the cost of the project. What would be the total contract price for the landscape project? |

| | | |

| | | |

| | |$2,750 |

| | |$3,125 |

| | |$3,150 |

| | |$3,375 |

| | | |

| |9. |If two levels are 48 inches apart and 6-inch riser is desired, how many steps would be required to connect the two levels? |

| | | |

| | |6 |

| | |8 |

| | |10 |

| | |12 |

| | | |

| |10. |How many feet of plastic edging will you need to edge three shrub beds that are 10 feet x 40 feet? |

| | | |

| | |100 |

| | |200 |

| | |300 |

| | |400 |

| | | |

2009 STATE FFA NURSERY LANDSCAPE

PROBLEM SOLVING TEST

ANSWER SHEET

|# |Answer |

|1. |B |

|2. |A |

|3. |D |

|4. |B |

|5. |C |

|6. |D |

|7. |C |

|8. |D |

|9. |B |

|10. |C |

2009 STATE FFA NURSERY LANDSCAPE

PROBLEM SOLVING TEST

CALCULATIONS

1. 120’ x 240’ = 28,800 sq. ft.

2. 4’ x 75’ = 300 sq. ft. of surface area

300 sq. ft. @ 4” deep

1. Convert 4” to .33’ (inches to feet)

2. Multiply 300 sq. ft. x .33’ = 99.9 cubic feet

3. There are 27 cubic feet per cubic yard.

4. 99.9 cu. ft.

27 cu. ft. = 3.7 cubic yards needed for the sidewalk.

3. 85’ x 150’ = 12,750 sq. ft. = 12.75 x 4 = 51 pounds of seed needed

1000

4. Want = 1 lb. N = 16.7 lbs 16.7 lbs. x 5 = 83.5 lbs of 6-12-18 needed

Got 6-12-18 1,000 sq. ft.

5. 1 yard3 = 27 cu. ft. 27 = 9 bags @ $3.00 = $27.00 to purchase by the bag.

3

Bulk is $20 cubic yard. $27.00 - $20.00 = $7.00 cheaper by the bulk.

6. 128 oz / gallon 128 x 4 = 512 ounces x 2% solution

512 x .02 = 10.24 ounces Roundup / 4 gallons

7. 3000 = 60 bales of pine straw

50

8. $2.500 x .10 = $250 Overhead Costs

$2,500 x .25 = $625 Profit Allowance

$250 + $625 addition to $2,500 original cost

$2,500 + $875 = $3,375 Total Contract Price OR $2,500 x 1.25 = $3,375 Total Contract Price

9. Elevation (48”) = 48” = 8 steps are needed

Riser Dimension (6”) 6”

10. 10 + 40 + 10 + 40 = 100’ x 3 = 300’

................
................