Contractor, subcontractor, or consultant, the specific
..
O
goggESPOI9
BEFORE THE UNITED STATES
D0LKETED usNRC
NUCLEAR REGULATORY COMMISSION
L
Before the Atomic Safety and Licens'8in7gJMB1oa-2rdP5 :33
In the Matter of TEXAS UTILITIES GENERATING COMPANY,
et al.
(Comanche Peak Steam Electric
Station, Unit 1)
.
CFF; '
s
)
r,C m p.;;7 ''
)
) Dkt. Nos. 50-445-CPA
)
)
)
)
MEDDIE GREGORY'S INTERROGATORIES AND REQUEST FOR PRODUCTION OF DOCUMENTS
(Set 5) ,
Please respond to,the following interrogatories and requests for production of documents within the time limits specified by the NRC regulations and pursuant to the requirements of those
regulations.
For purposes of this document, the following definitions and guidelines for clarifying answers are applicable:
a. " Applicants" refers to each owner of CPSES and to each
|
contractor, subcontractor, and consultant. Each answer
should indicate that the answer represents the information in the possession of each and every owner and that inquiry has been made to each contractor, subcontractor, and consultant, including those no longer employed at the site, and the responses received from them, if any. In addition, when information is
obtained from an owner other than TUEC or from any
contractor, subcontractor, or consultant, the specific information so obtained, particularly documents, chould
0701050433 861230
gDR ADOCK 05000 5
_ _ _ _ _ _ - _ _ _ _ _ _
J{f |
T
.
.
be identified by source whenever reasonably possible (i.e., from whom did TUEC obtain the information in
order to answer the question or request?).
b. " Documents" refers to everything ~ written or recorded in
any way, including draf ts and otherwise identical
copies of the same documents that contain substantive
additions or deletions.
c. All interrogatories and requests should be regarded as
separable and objections to portions of interrogatories
or requests do not relieve Applicants of the duty to
answer the remainder of the interrogatories or
requests. f
d. Where objections are interposed but answers given,
please indicate to what extent the answer is a complete
1
response and to what extent additional information is
being withheld because of the objection.
e. Identify all documents examined, used, and/or relied
upon in answering each interrogatory.
The foregoiny definitions and guidelines are incorporated by
reference into and are a part of each of the following
interrogatories and requects.
Interrogatories (Answers due in 15 days.) 1. When did Applicants first receive notice of the issues
identified by the NRC's TRT reports and SSERs, and in what form
did that notice come (i.e., NCR, IR, audit report, memorandum, consultant's report, e tc.) ?
2. For each item identified in Interrogatory 1, identify
-2-
,
. .
what response was taken to the problem and by whom.
3. If the answer to Interrogatory 2 is that no action was
taken, explain the reason that no action was taken. If that
reason is because Applicants relied on a "second opinion," identify the individuals or organizations who provided that
opinion.
4. Identify how each " finding" identified in Interrogatory 1 was integrated into consideration of the subsequent findings by
others. (For example, how were the findings by the NRC in 1978
and 1979 integrated into Applicants' response to the findings by
'
the Management Analysis Corporation (MAC) ?)
5. With referene"e to the ' attachment to the letter from
Robert A. Wooldridge to' Foster DeReitzes dated December 23, 1985, which attachment was the " work specification on the retrospective
audit," please answer the following questions:
a. What is the current status of that audit, and why is it
being conducted?
b. To what extent have the work specifications been
changed; what are the changes; who changed them; and why? c. When will the audit be completed?
d. Why was the completion of the audit originally tied to a
date shortly before anticipated fuel load of Unit 17
,
e. Is it still tied to a date shortly before fuel load of
Uni t 1, and, if so, why?
f. What types of documents have been generated in the
course of conducting the audit? Please include within your
answer handwritten notes, internal memos within the
!
,
-3-
I
_
,-
--
r , .
organization (s) conducting the audit, progress reports to Appticants on the audit, minutes of meetings and notes by participants in meetings among the auditor personnel or between the auditors and any other persons.
9 Has the audit or any of the audit personnel reached any tentative or final conclusions on any subjects? If so, what are those conclusions?
h. Who is conducting the audit, and who at TUEC is
supervising the conduct of the audit?
Request for Production of Documents
(Answers due in 36~~ days.)
1. With referencp to page 2 of Mr. Beck's letter to the
mnority owners dated July 31, 1985, please provide a copy of the
"Dreakdown of the 1978 MAC report findings to identify which items have been resolved by the project and which are being further addressed by the CPRT ef fort."
2. With reference to Interrogatory 5, please provide a copy
of all the documents the types of which are described in
i
Interrogatory 5.f.
3. With reference to Interrogatory 5, please provide a copy of all documents that define the nature of the audit and the relationship between TUEC and the auditors, including all
contracting documents. Portions of the documents that disclose the actual price of the work to be performed need not be
disclosed.
4. Produce the original or copies of all documents in
Applicants' custody, possession, or control that were examined,
used, and/or relied upon for answering Interrogatories 1 through
1
-4-
L
-
.
.
4
S above. If a document has already been supplied in this docket or in the OL docket, Applicants may identify with particularity the location of the document or answer by including the name of the document, page and line number, in which docket the document was produced, and the date it was produced. This does not apply if the answer previously provided was an objection. In that case, Applicants must reassert the obbjection to the extent
applicable to this proceeding.
m .
f
*
Dated: December 30, 1986
Respectfully submitted,
'-
~
/M
hg
ANTHONY Z. KIdpN
Trial Lawy fs for Public Justice
2000 P S eet, NW, #611
Washington, D.C. 20036
(202) 463-8600
Counsel for Meddie Gregory
-5-
|
1
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- understanding flow down clauses in subcontracts woolford law
- subcontractors faq irs tax forms
- welcome to the subcontractors academy austin texas
- contractor subcontractor or consultant the specific
- course 6 tutorial 4 using subcontractors and consultants to sbir
- contractor travel reimbursement guidelines january 2019
- subcontractor vs contractor vs consultant guidance
- subcontractor vs vendor contractor vs consultant umd
- subcontractor subawardee vs vendor northern arizona university
- distinguishing between subrecipient subawardee vendor and contractor
Related searches
- nonetheless or none the less
- a specific or an specific
- specific to or for
- nevertheless or never the less
- how to calculate the average specific heat
- calculate the specific heat capacity
- how to find the specific heat
- calculate the specific heat
- meanwhile or in the meanwhile
- in society or in the society
- contractor to subcontractor agreement
- general contractor to subcontractor agreement