AGENDA - ISO Ne



AGENDA

NEPOOL RELIABILITY COMMITTEE (RC) MEETING

JUNE 9, 2016

LOCATION: Doubletree Hotel – Westborough, MA

Call-in Number: 1-866-711-7475 / Access Code: 8562734

Item Description Time Allotted

1.0 CHAIRS REMARKS 9:30 – 9:35

2.0 MEETING MINUTES (66.6% VOTE) 9:35 – 9:45

Review and approve the following draft meeting minutes, as available.

• May 17, 2016

3.0 PROPOSED PLAN APPLICATIONS (PPAs) Level II/III 9:45 – 10:30

Present Proposed Plan Applications for committee action on advisory

recommendations for ISO approval.

3.1 GREATER BOSTON TRANSMISION PROJECT – LEVEL III (66.6% VOTE)

(NEP: Jack Martin)

ES-16-T05 – Transmission notification from Eversource Energy (ES) for the

installation of a new 25 mile long 345 kV overhead line from Eversource’s Scobie

Pond Substation, in Londonderry, NH to National Grid’s Tewksbury 22A Substation,

in Tewksbury, MA. The Eversource portion of the new line is 9.8 miles. A new

345 kV bay connected to the existing breaker-and-half bus arrangement will be

constructed at Scobie Pond Substation with a circuit breaker on either side of the new

circuit. Proposed in service date of the project is December 2017.

ES-16-T06 – Transmission notification from Eversource Energy (ES) for the

installation of a new 8 mile 345 kV underground cable circuit from Eversource’s

Woburn Substation, in Woburn, MA to National Grid’s Wakefield Junction Substation,

in Wakefield, MA with 160 MVAr variable shunt reactors at each terminal. Expand the

345 kV switchyard at Woburn Substation to be a breaker-and-a-half substation with

four bays. NEP-16-T02 covers the National Grid portion of the project. Proposed in

service date of the project is December 2018.

ES-16-T07 – Transmission notification from Eversource Energy (ES) for the

addition of a new 115 kV overhead line from Eversource’s Sudbury Substation

to Hudson Light & Power’s Forest Avenue Substation and adding one 115kV breaker

(#7) at Sudbury Substation. HLPD-16-T01 covers the Hudson Light & Power

Department portion of the project. Proposed in service date of the project is

December 2018.

ES-16-T08 – Transmission notification from Eversource Energy (ES) for the

addition of a new 345 kV shunt reactor and converting the existing straight-bus

to a ring-bus at Eversource’s K Street Substation in Boston, MA by adding

breakers #109, #110, and #111. Proposed in service date of the project is

December 2018.

ES-16-T09 – Transmission notification from Eversource Energy (ES) for the

construction of a new Eversource 115 kV switching station in Sharon, MA to

break up the existing West Walpole to Holbrook 115 kV circuits 447-508 and

447-509 and the new West Walpole to Holbrook circuit (partially the existing

447-502) into two circuits each. Proposed in service date of the project is

December 2018.

ES-16-T10 – Transmission notification from Eversource Energy (ES) for the

addition of a new Eversource 115 kV 14 mile overhead line from Eversource’s

Walpole Substation, through a new Sharon Switching Station, continuing to

Eversource’s Holbrook Substation. At Holbrook, a new 115 kV circuit breaker

will be added to accommodate this new circuit. Proposed in service date of the

project is December 2018.

ES-16-T11 – Transmission notification from Eversource Energy (ES) for the

addition of a new 115 kV 36.7 MVAr shunt capacitor bank at Eversource’s

Hartwell Ave Substation. Proposed in service date of the project is December 2018.

ES-16-T12 – Transmission notification from Eversource Energy (ES) for the

construction of a new Eversource 115 kV 4.7 mile (total) underground cable circuits

from Eversource’s Mystic Substation to Eversource’s Chelsea Substation (via

new East Eagle Substation). Proposed in service date of the project is December 2018.

ES-16-T13 – Transmission notification from Eversource Energy (ES) for the

construction of a new six-breaker, 115 kV ring bus substation (East Eagle

Substation) in East Boston, MA connecting both to Eversource’s Mystic Substation

and to Eversource’s Chelsea Substation via new 115 kV underground cable circuits.

The new substation includes two 115/14 kV distribution transformers. Proposed in

service date of the project is December 2018.

ES-16-T14 – Transmission notification from Eversource Energy (ES) for splitting

the overhead DCT for approx. 1.5 miles from Baker St substation to a point on the

ROW at existing common structure locations. Then a new underground cable section,

which will be part of the 110-522 line, will go from that point on the ROW for approx.

2.36 miles where it will terminate at the Needham Substation. Proposed in service date

of the project is December 2018.

ES-16-T15 – Transmission notification from Eversource Energy (ES) for the

retirement of the Mystic 9 SPS. Proposed in service date of the project is December 2018.

ES-16-T16 – Transmission notification from Eversource Energy (ES) for the retirement

of the Y-151 SPS, an NPCC Type III SPS, designed to trip breakers at Power Street

Substation to eliminate overloads on the Y-151 line between Power Street and Pelham

substations. This SPS is no longer needed and procedures for approval of its removal

will be initiated following PPA approval. Proposed in service date of the project

is December 2018.

ES-16-T17 – Transmission notification from Eversource Energy (ES) for the

reconductoring of the 3.7 mile overhead 115 kV Y-151 line from Power St

Substation to the border with National Grid. See NEP-16-T03 for reconductoring

the 115 kV Y-151 and Y-151S lines from the Eversource / National Grid border

to Pelham Substation and from Pelham Substation to Dracut Jct. Proposed in

service date of the project is December 2018.

ES-16-T18 – Transmission notification from Eversource Energy (ES) for the

installation of series breakers #29S and #103S and installing a bus tie breaker #33

at K Street. Additionally, existing circuit breakers #29 (to be #29P), and #103

(to be #103P) at K Street as well as circuit breaker #7 at Mystic will be changed

to be operated normally-closed as opposed to their current normally-open status.

Proposed in service date of the project is December 2018.

ES-16-T19 – Transmission notification from Eversource Energy (ES) for the

upgrade of the existing 7.96 mile 115 kV 211-514 underground circuit from

Eversource’s Woburn Substation, in Woburn, MA to Eversource’s Mystic

Substation, in Everett/Boston, MA by paralleling the existing 115 kV

underground cable with a new 115 kV underground cable and operating in a

bifurcated manner. A new 115kV series reactor will be installed with the new

cable. Proposed in service date of the project is December 2018.

ES-16-T20 – Transmission notification from Eversource Energy (ES) for the

installation of a second 345/115 kV autotransformer and a new 345 kV circuit

breaker at Eversource’s Mystic Substation in Charlestown/Everett, MA.

Proposed in service date of the project is December 2018.

ES-16-T21 – Transmission notification from Eversource Energy (ES) for the

replacement of existing Woburn Autotransformer with a new larger unit. The

Project also adds four new 345 kV circuit breakers and relocates the termination

for the 345 kV 338 line from Tewksbury – Woburn and the 345 kV 346 line from

North Cambridge to Woburn. Proposed in service date of the project is December

2018.

ES-16-T22 – Transmission notification from Eversource Energy (ES) for the

completion of upgrades at the Kingston Substation in Boston, MA to create a

second normally closed 115 kV bus tie and associated circuit breakers.

Additionally, reconfigure the 345 kV switchyard by opening 345 kV breakers

#101 and #103. Proposed in service date of the project is December 2018.

ES-16-T23 – Transmission notification from Eversource Energy (ES) for the

opening of the existing 329-510/511 lines at Somerville Substation in Somerville,

MA and the 250-516/517115 kV lines at Chatham St. Substation in Boston, MA,

including line switchers and associated equipment at both Somerville Substation

and Chatham St. Substation. Proposed in service date of the project is December 2018.

ES-16-T24 – Transmission notification from Eversource Energy (ES) for the

addition of a 36.7 MVAR capacitor bank at Sudbury Station. Proposed in service

date of the project is December 2018.

ES-16-T25 – Transmission notification from Eversource Energy (ES) for the

reconfiguration of the Waltham Substation, including relocating terminations for

phase shifters and the 282-507 line and adding three new circuit breakers. Proposed

in service date of the project is December 2018.

ES-16-T26 – Transmission notification from Eversource Energy (ES) for operating

the 115kV bus tie breaker #13 at Brighton Substation as normally closed. Proposed

in service date of the project is December 2018.

ES-16-T27 – Transmission notification from Eversource Energy (ES) for the

installation of a 115 kV, 54 Mvar shunt capacitor bank at Newton Highlands

Substation in Newton, MA. Proposed in service date of the project is December 2018.

NEP-16-T01 - Transmission notification from New England Power Company (NEP)

for the addition of a new 345kV line from the Eversource border in Hudson, NH to

the Tewksbury 22A Substation owned by NEP. Additionally, two new 345 kV circuit

breakers will be installed in an existing indoor GIS at Tewksbury 22A. Proposed in

service date of the project is December 2017.

NEP-16-T02 - Transmission notification from New England Power Company (NEP)

for the installation of two new 345 kV, 50 kA, 4000 A circuit breakers in an existing

GIS 3-bay breaker-and-third configuration at Wakefield Junction substation, 4000 A

terminal equipment for the new proposed 345 kV UG cable (from Wakefield Junction

substation to Woburn substation) and a new 345 kV, 160 MVAr variable shunt reactor

bank (70 MVAr fixed and 90 MVAr variable). Also, operate one of the existing

Wakefield Junction Autotransformers in a normally open configuration. Proposed in

service date of the project is December 2018.

NEP-16-T03 - Transmission notification from New England Power Company (NEP)

for the reconductoring of the 5.22 mile overhead Y-151N 115 kV Line from Pelham

Substation in Pelham, NH to the PSNH border in Hudson, NH and the 4.10 mile

overhead Y-151 115 kV Line from Pelham Substation in Pelham, NH to Dracut

Junction in Dracut, MA. Proposed in service date of the Y-151N Line is

April 2017 and the proposed in service date of the Y-151 Line is September 2017.

HLPD-16-T01 – Transmission notification from Hudson Light and Power Department

(HLPD) for the expansion of the existing Forest Avenue Substation into a 6 position

115 kV ring bus to allow for termination of the new Sudbury – Hudson 115 kV line to be

installed by Eversource Energy. Proposed in service date of the project is December 2018.

CMP-16-T01 – Transmission notification from Central Maine Power Company (CMP)

for the installation of a +/- 200 MVAr STATCOM at the 345 kV bus of the Coopers Mills

Substation in Windsor, ME. Proposed in service date of the project is December 2018.

(C. Benker and E. Leonard April 6, 2016, J. Martin March 9, 2016, B. Choquette

March 9, 2016, and J. DeMay March 9, 2016 Cover Letters, Transmission Notifications

and One Line Diagrams, Task Force Approval Letter, Presentation, “Greater Boston

Switching Transient Study, Greater Boston 345 kV Switching Transient Study, Greater

Boston 115 kV Switching Transient Study, Greater Boston Stability Study, Greater

Boston Steady State Study, Greater Boston Short Circuit Addendum”)

3.2 QP 400 DOWNEAST WIND GENERATION AND TRANSMISSION PROJECT

LEVEL III (66.6% VOTE) (Emera Maine: Jeff Fenn) ***CEII TOPIC***

EM-16-G01 – Generator application from Emera Maine (“EM”) on behalf of

Downeast Wind LLC for the installation of 30 3.0 MW (90 MW Net Output)

wind turbine generators in Washington County, ME and interconnecting to Emera

Maine Epping 115kV switching station by means of a new collector substation and

Generator Lead. Proposed in service date of the project is December 31, 2018.

EM-16-T01 – Transmission application from Emera Maine (“EM”) on behalf of

Downeast Wind LLC for the Epping switching station reconfiguration and breaker

addition for the project generator lead. Proposed in service date of the project is

December 31, 2018.

EM-16-T02 – Transmission application from Emera Maine (“EM”) on behalf of

Downeast Wind LLC for the collector substation 115/34.5kV new main power

transformer and associated breakers and protection associated with QP#400. Also

construct a new five mile 115kV generator lead from Epping switching station to

the project collector substation. Proposed in service date of the project is

December 31, 2018.

(J. Fenn May 19, 2016 Cover Letter, Generator and Transmission Notification and

One Line Diagrams, Task Force Approval Letter, “QP 400 Downeast Wind

Interconnection System Impact Study” dated May 4, 2016)

3.3 QP 525 TIVERTON POWER GENERATION UPRATE PROJECT - LEVEL III

(66.6% VOTE) (Emera Maine: Jeff Fenn) ***CEII TOPIC***

EE-16-G01 – Generator application from Emera Energy (“EE”) on behalf of Tiverton

Power LLC for the uprate of existing Tiverton Power combined cycle generation facility

to 292MW and 287.5MW at 50F (for a plant output increase of approximately 21.5MW).

Power System Stabilizers for the two machines will be set and enabled as part of this uprate

project. Proposed in service date of the project is September 30, 2016.

EE-16-X01 – Generator application from Emera Energy (“EE”) on behalf of Tiverton

Power LLC for the retirement of the Tiverton ZL14/M13 Type III SPS. National Grid

was able to determine that the L14/M13 tap lines can be operated at a higher temperature.

QP#525 SIS concluded that the tap lines had ratings adequate for the total project (including

the uprate) output and will not require the SPS to prevent thermal overloads. Proposed

in service date of the project is September 30, 2016.

(J. Fenn May 4, 2016 Cover Letter, Generator and Transmission Notification and

One Line Diagrams, Task Force Approval Letter, “System Impact Study (Stability)

Interconnection Proposal at Position No. 525 on the ISO New England Generator

Interconnection Queue” dated April 11, 2016 and “System Impact Study (Steady State)

Interconnection Proposal at Position No. 525 on the ISO New England Generator

Interconnection Queue” dated April 11, 2016)

3.4 ELECTRIC AVENUE SUBSTATION PROJECT - LEVEL III

(66.6% VOTE) (Eversource: Betty Leonard) ***CEII TOPIC***

ES-16-T41 – Transmission notification from Eversource Energy (“ES”) for the

construction of a new twelve-breaker, 115 kV substation (Electric Ave. Substation)

in Brighton, MA connecting both to Eversource’s Waltham Substation and to

Eversource’s Brighton Substation via the 282-520/521 115 kV underground cable

circuits. The new substation includes three 115/14 kV distribution transformers.

Proposed in service date of the project is December 2018.

(E. Leonard May 26, 2016 Cover Letter, Transmission Notification and One Line

Diagram, Task Force Approval Letter, “Electric Avenue Station #315 I.3.9 Proposed

Plan Application Study” dated May 2016)

4.0 PROPOSED PLAN NOTIFICATIONS (Level 0/I) 10:30 - 11:00

Present application and notifications, receive committee review and

concurrence that the Plan requires Level 0 or I treatment.

4.1 510 DEVELOPMENT HYDE PARK BOSTON SOLAR PROJECT –

LEVEL 0 (NOTIFICATION) (Eversource: Al Scarfone) ***CEII Topic***

ES-16-G07 - Generator notification from Eversource Energy (“ES”) on behalf of

510 Development for the installation of a 3.0 MW solar array located in Boston,

MA and interconnecting via the 13.8 kV, 496-H2 circuit off Hyde Park Station.

Proposed in service date of the project is November 30, 2016.

(L. Yang May 11, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.2 CEC OLD COUNTRY ROAD WESTPORT SOLAR PROJECT – LEVEL 0

(NOTIFICATION) (NEP: Al Scarfone) *** CEII Topic***

ES-16-G08 – Generator notification from Eversource Energy (“ES”) on behalf of

CEC Solar for the installation of a 2.55 MW solar array located in Westport, MA

and interconnecting via the 13.2 kV, 522 feeder at the Fisher Road Substation #657.

Proposed in service date of the project is August 1, 2016.

(K. Jones May 12, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.3 CORBIN RUSSWIN BERLIN SOLAR PROJECT – LEVEL 0

(NOTIFICATION) (Eversource: Al Scarfone) *** CEII Topic***

ES-16-G03 – Generator notification from Eversource Energy (“ES”) on behalf of

Sol Systems LLC for the installation of a 1.78 MW solar array located in Berlin, CT

and interconnecting via the 13.8 kV, circuit 6A6 at the Berlin 6A Substation.

Proposed in service date of the project is July 1, 2016.

(P. Sousa May 25, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.4 DOWNING PARKWAY PITTSFIELD SOLAR PROJECT – LEVEL 0

(NOTIFICATION) (Eversource: Al Scarfone) *** CEII Topic***

ES-16-G16 – Generator notification from Eversource Energy (“ES”) on behalf of

Downing Parkway Solar LLC for the installation of a 2.34 MW solar array located

in Pittsfield, MA and interconnecting via the 23 kV, circuit 19A3 at the Doreen 19A

Substation. Proposed in service date of the project is October 31, 2016.

(P. Sousa May 27, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.5 STAFFORD MIDDLE SCHOOL SOLAR PROJECT – LEVEL 0 (NOTIFICATION)

(Eversource: Al Scarfone) *** CEII Topic***

ES-16-G04 – Generator notification from Eversource Energy (“ES”) on behalf of

Town of Stafford for the installation of a 2.0 MW solar array located in Stafford, CT

and interconnecting via the 23 kV, Blair 15M2 fed from Rockville 14W. Proposed in

service date of the project is July 1, 2016.

(P. Sousa May 25, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.6 BORREGO MARIE’S WAY FREETOWN SOLAR PROJECT – LEVEL 0

(NOTIFICATION) (NEP: Al Scarfone) *** CEII Topic***

ES-16-G10 – Generator notification from Eversource Energy (“ES”) on behalf of

Borrego Solar for the installation of a 3.96 MW solar array located in Freetown, MA

and interconnecting via the 13.2 kV, 108 feeder at the Industrial Park Substation #636.

Proposed in service date of the project is September 8, 2016.

(K. Jones May 12, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.7 TYNGSBOROUGH SOLAR PROJECT – LEVEL 0 (NOTIFICATION)

(New England Power Company: Jack Martin) *** CEII Topic***

NEP-16-GNF13 – Generation notification from New England Power Company for

the installation of a 1.656 MW solar array located in Tyngsborough, MA and

interconnecting via the 13.2 kV, 210L1 feeder to the Dunstable 210 Substation.

Proposed in service date of the project is December 31, 2016.

(C. Sullivan June 1, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.8 NORTON LANDFILL SOLAR PROJECT – LEVEL 0 (NOTIFICATION)

(New England Power Company: Jack Martin) *** CEII Topic***

NEP-16-GNF14 – Generation notification from New England Power Company for

the installation of a 2.25 MW solar array located in Norton, MA and interconnecting

via the 13.2 kV, 4L1 feeder to the Norton 4 Substation. Proposed in service

date of the project is December 31, 2016.

(C. Sullivan June 1, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.9 ROGERS ROAD NORWICH SOLAR PROJECT – LEVEL 0

(NOTIFICATION) (CMEEC: Bruce McKinnon) *** CEII Topic***

CMEEC-16-G02 – Generator notification from Connecticut Municipal Electric

Energy Cooperative (“CMEEC”) on behalf of Solar City Corporation for the

installation of a 2.5 MW solar array located in Norwich, CT and interconnecting

via the 13.8 kV distribution system at the Bean Hill Substation. Proposed in service

date of the project is June 30, 2016.

(G. Stern May 27, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.10 SOLAR CITY STOTT AVENUE NORWICH SOLAR PROJECT – LEVEL 0

(NOTIFICATION) (CMEEC: Bruce McKinnon) *** CEII Topic***

CMEEC-16-G03 – Generator notification from Connecticut Municipal Electric

Energy Cooperative (“CMEEC”) on behalf of Solar City Corporation for the

installation of a 3.5 MW solar array located in Norwich, CT and interconnecting

via the 13.8 kV, 913 feeder at the Bean Hill Substation. Proposed in service

date of the project is June 30, 2016.

(G. Stern May 23, 2016 Cover Letter, Generator Notification and One Line Diagram)

4.11 WOODBRIDGE FUEL CELL PROJECT – LEVEL 0 (NOTIFICATION)

(United Illuminating: Alex Boutsioulis) *** CEII Topic***

UI-16-G01 – Generator notification from United Illuminating (“UI”) for the installation

of a 2.8 MW fuel cell located in Woodbridge, CT and interconnecting via the 13.8 kV,

feeder 1605 at the June Street Substation. Proposed in service date of the project is

December 1, 2016.

(A. Boutsioulis May 26, 2016 Cover Letter, Generator Notification and One Line Diagram)

5.0 PLANNING PROCEDURES 11:00 – 12:00

5.1 PP 5-6 – SCOPE OF INTERCONNECTION STUDIES FOR GENERATION

AND ETUs (60.0% VOTE) (ISO: Al McBride) 4th Meeting

Revisions related to the scope of interconnection Studies for generation and ETU’s.

(PP 5-6 Redline)

5.2 PP 10 – PLANNING PROCEDURE TO SUPPORT THE FORWARD CAPACITY

MARKET (FUTURE VOTE) (ISO: Mariah Winkler) 2nd Meeting

Document revisions related to the Resource Retirement Reform initiative and

administrative clean up.

(PP 10 Redline)

LUNCH 12:00 – 12:45

6.0 TRANSMISSION COST ALLOCATIONS 12:45 – 1:30

6.1 NORTHWEST CONNECTICUT AREA PROJECTS UPGRADES

PROJECT TCA – Part of GHCC Project (66.6% VOTE)

(Eversource: Al Scarfone) *** CEII Topic***

ES-16-TCA-14 - Transmission Cost Allocation from Eversource Energy (“ES”)

for the Northwest Connecticut Area Project Upgrades for the addition of a new

10.35 mile, 115 kV line from Frost Bridge to Campville and associated terminal

equipment. The separation of 115 kV DCT corresponding to the Frost Bridge to

Campville (1191) line and the Thomaston to Campville (1921) line and add a

115 kV breaker at Campville substation. Also upgrade the terminal equipment on

the 115 kV line between Chippen Hill to Lake Avenue Junction (1810-3) and

reconductor the 5.2 mile 115 kV line between Southington to Lake Avenue

Junction (1810-1). Pool Supported PTF costs are $63.135M (2015 Estimated Costs).

(A. Scarfone May 11, 2016 Cover Letter, TCA Application, Presentation)

6.2 W-175 LINE RECONDUCTORING PROJECT TCA (66.6% VOTE)

(NEP: Jack Martin) *** CEII Topic***

NEP-16-TCA-05 – Transmission Cost Allocation from New England Power

Company (“NEP”) for the reconductoring and refurbishment of the 16 mile

W-175 115 kV Line between West Charlton and Palmer. Pool Supported PTF

costs are $28.0M (2016 Estimated Costs)

(D. Latulipe May 27, 2016 Cover Letter, TCA Application, Presentation)

6.3 WEST HAMPDEN INTERCONNECTION PROJECT TCA(66.6% VOTE)

(Eversource: Al Scarfone) *** CEII Topic***

ES-15-TCA-10 - Transmission Cost Allocation from Eversource Energy (“ES”)

for the West Hampden Interconnection Project The 115-kV 1976 and 1205 line

work (formerly 1515 Line ) and related work (Ludlow Substation, MA and Scitico

Substation, CT), is to accommodate National Grid's new West Hampden Substation.

Pool Supported PTF costs are $3.226M (2014 Actual Costs).

(A. Scarfone May 28, 2015 Cover Letter, TCA Application, Presentation)

6.4 WEST HAMPDEN SUBSTATION PROJECT TCA(66.6% VOTE)

*** CEII Topic***

NEP-16-TCA-04 – Transmission Cost Allocation from New England Power

Company (“NEP”) for the conversion of the O-15S 69 kV line (10 mi) to 115 kV

between Palmer and new West Hampden substation. Installation of a new 115 kV

breaker at Palmer substation and reconductor of the 115 kV bus work and asset

condition upgrades. In addition, construction of a new 115/69 kV substation in

Hampden, MA (W Hampden substation). Pool Supported PTF costs are $36.75M

(2016 Actual Costs)

(D. Latulipe May 27, 2016 Cover Letter, TCA Application, Presentation)

7.0 GRIDEX III COMMUNICATION PROTOCOL – FOLLOW UP 1:30 – 2:00

Follow up to GridEx III Exercise results regarding possible improvements and

enhancements to communication protocols with LCC’s, Federal and State Agencies.

(ISO: John Norden)

8.0 DUAL FUEL AUDIT TARIFF REVISIONS (POSSIBLE VOTE) 2:00 – 2:15

(ISO: Ben Ewing)

Section III.1.5.2 Tariff revisions to fix an incorrect reference to Dual Fuel Generator

audit language.

(Tariff Redline)

9.0 FOLLOW UP ON DYNAMIC MODEL VALIDATION FOR MOD-032 2:15 – 2:30

(NOTIFICATION) (ISO: John Pearson)

Update on status of MOD-032 Dynamics Data Reviews. Includes MOD-032

requirements summary, DDMS Compliance Officer registration and status of

verifications for each Lead Market Participant.

(MOD-032 Presentation)

10.0 OPERATING PROCEDURES 2:30 – 3:00

10.1 OP 16 – TRANSMISSION SYSTEM DATA AND APPENDICES OP16A, OP16C,

OP16D, OP16G THROUGH OP 16K (FUTURE VOTE) (ISO: Jerry Elliott) 1st Meeting

Document revision as part of biennial review to add glossary of terms used in NERC

Reliability Standards, submission schedule and quick reference table changes,

submission of one line diagrams and web based method of submission. Also specification

of submittal requirements for generator Lead Market Participants and addition of BES

designated equipment to the one line requirement standard.

(OP 16, OP 16A, OP 16C, OP 16D, OP 16G through OP 16K Clean and Redline documents)

11.0 CLOSING REMARKS/ADJOURN 3:00

................
................