Earned Value Cheatsheet - P6 Consulting
EARNED VALUE CHEAT SHEET
ABB. PV
(BCWS) EV
(BCWP) AC
(ACWP) BAC
TERM Planned Value (Budgeted Cost of Work Scheduled) Earned Value (Budgeted Cost of Work Performed)
Actual Cost (Actual Cost of Work Performed)
Budget at Completion
EAC
Estimate at Completion
ETC
Estimate to Complete
*ETC is set at the WBS Level, Earned Value tab.
GENERAL TERMS
CALCULATION
DEFINITION
Planned % Complete * Budget at Completion What is the planned value of the work scheduled to be
completed at this point in time?
Actual % Complete * Budget at Completion What is the value of the work completed at this point in
time?
Actual Labor Cost + Actual Nonlabor Cost + What is the cost of the work completed at this point in time?
Actual Expense Cost
Planned Labor Cost + Planned Nonlabor
What is the overall total budgeted cost of the project?
Cost + Planned Expense Cost
Actual Cost + Estimate to Complete
What do we expect the overall total cost of the project be to
completion?
Performance Factor * (Budget at Completion How much more will the project take to complete the
? Earned Value)
project?
P6 COLUMN NAME Planned Value Cost Planned Value ? Labor Units Earned Value Cost Earned Value ? Labor Units Actual Cost
Budget at Completion Budget at Completion ? Labor Units Estimate at Completion Cost Estimate at Completion ? Labor Units Estimate to Complete Estimate to Complete ? Labor Units
ABB. AV CV
SV VAC
TERM Accounting Variance
Cost Variance Schedule Variance Variance at Completion
CALCULATION Planned Value ?
Actual Cost Earned Value ?
Actual Cost Earned Value ? Planned Value Budget at Completion ? Estimate at Completion
VARIANCES
DEFINITION
INDICATION
How much more/less did you actually spend than Positive number indicates spending under budget
was budgeted?
Negative number indicates spending over budget
How much more/less did you spend to complete Positive number indicates spending under budget
work than was budgeted?
Negative number indicates spending over budget
How much more/less of the scheduled work has Positive number indicates ahead of scheduled work
been finished than was planned?
Negative number indicates behind scheduled work
How much more/less should we expect to add to Positive number indicates project is under budget
the total project to complete the project? How
Negative number indicates project is over budget
much under/over budget will the project be at
completion?
P6 COLUMN NAME Accounting Variance Accounting Variance ? Labor Units Cost Variance Cost Variance ? Labor Units Schedule Variance Schedule Variance ? Labor Units Variance at Completion Variance at Completion ? Labor Units
ABB. CPI
CVI SPI
SVI
TCPI
TERM Cost Performance
Index
CALCULATION Earned Value / Actual Cost
Cost Variance Index
Schedule Performance Index
Cost Variance / Earned Value Earned Value / Planned Value
Schedule Variance Schedule Variance / Planned Value Index
To Complete Performance Index
(BAC)
(Budget at Completion ? Earned Value) / (Estimate at Completion ? Actual Cost)
INDICES
DEFINITION Is the work being completed costing more/less than what was planned?
Is the work being earned costing more/less than what was planned? Is the work being completed more/less than what was scheduled?
Is the work being earned more/less than what was scheduled?
What cost performance must be achieved for the project to meet the estimated cost to completion (EAC)?
INDICATION < 1 indicates you spent more than planned > 1 indicates you spent less than planned
< 0 indicates you spent more than completed > 0 indicates you spent less than completed < 1 indicates that less work was performed > 1 indicates that more work was performed
< 0 indicates you earned less than scheduled > 0 indicates you earned more than schedued
< 1 indicates that you will require lower performance to meet EAC > 1 indicates you will require higher performance to meet EAC
P6 COLUMN NAME Cost Performance Index Cost Performance Index ? Labor Units Cost Variance Index Cost Variance Index ? Labor Units Schedule Performance Index Schedule Performance Index ? Labor Units Scheduled Variance Index Schedule Variance Index ? Labor Units To Complete Performance Index
?2016 CPM Solutions Ltd. Collaborative Project Management | cpmsolutions.ca
1|Page
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- calculating business value scrum inc
- calculating earned business value for an agile project
- brief introduction to earned value management evm
- wp1081 earned value mosaic projects
- earned value management handbook earne vaman
- earned value analysis exercise
- earned value management tutorial module 1
- earned value cheatsheet p6 consulting
- earned value management tutorial module 6
- cost management plan
Related searches
- examples of earned value analysis
- earned value analysis calculation examples
- earned value analysis software
- earned value analysis table
- earned value calculation examples
- earned value analysis template excel
- earned value management chart
- earned value project
- earned value spreadsheet excel
- earned value management in excel
- earned value table in excel
- earned value management template excel