Project Management Plan - Chicago State University

Project Management Plan Grand Calumet Feasibility Study

U.S. Army Corps of Engineers Chicago District 111 North Canal Street Chicago, Illinois 60606 March 2003 Revised April/May 2003 Approved May 16, 2003

JCH00 All Other Real Estate Analyses/Documents

24

JD000 Environmental Studies/Reports/EIS

25

JDA00 Documentation of Scoping Meetings

25

JDB00 Environmental Impact Statement (EIS)

25

JDC00 Coordination Documents with Other Agencies

26

JDD00 Environmental Resource Inventory Report

26

JDE00 Mitigation Analysis Report

27

JDF00 Endangered Species Analysis

27

JDG00 Ecosystem Restoration Alternative Design

27

JDH00 Section 404(b)(1) Analysis Report

27

JDI00 Statement of Findings (SOF)

27

JDJ00 Other Environmental Documents

28

JE000 Fish and Wildlife Coordination Act Report

29

JEA00 Coordination District

29

JEB00 Preparation of Coordination Act Report

29

JF000 HTRW Studies

30

JFA00 HTRW Report

30

JFB00 HTRW Remedial Investigation (RI)

30

JFC00 All Other HTRW Documents

31

JG000 Cultural Resource Report

31

JGA00 Site Survey Field Report

31

JGB00 Data Collection and Analysis Report

31

JGC00 Mitigation Plan Report

31

JGD00 Memorandum of Agreement

32

JGE00 One Percent Waiver

32

JGF00 All Other Cultural Resources Studies/Reports

32

JH000 Cost Estimates

32

JHA00 Study Cost Estimate Updates

32

JHB00 PED Cost Estimate

33

JHC00 Project Cost Estimate

33

JHD00 OMRR&R Cost Estimate

34

JHE00 Baseline Fully Funded Cost Estimate (MCACES)

34

JHF00 All Other Cost Estimates

34

JHG00 Cost Engineering Appendix

34

JI000 Public Involvement Documents

34

JIA00 Public Meetings

35

JIB00 Minutes of Public Meeting(s)

36

JIC00 Public Comments Report

36

JID00 ? Newsletters

36

JIE00 All Other Public Involvement Documents

37

JJ000 Plan Formulation and Evaluation Report

38

JJA00 District Coordination Meeting

39

JJB00 Establish Without-Project Conditions

39

JJC00 Preliminary Formulation and Screening of Alternatives

39

JJD00 Alternative Formulation Briefing and Report

40

JJE00 Plan Formulation Management and Report

40

ii

JJF00 Plan Formulation Conference JJG00 LRD Approves Formulation Material JK000 Draft Report Documentation JKA00 Product Team (PT) Review JKB00 ? Independent Technical Review (ITR) JKC00 ? Feasibility Review Conference (FRC) Documents JKD00 Public Review Comments JKE00 Project Guidance Memorandum (PGM) JKF00 All Other Draft Feasibility Documents JL000 Final Report Documentation JLA00 Division Commander's Notice JLB00 ? All Other Final Feasibility Report Documents JM000 Washington Level Report Approval JMA00 Policy Review Approval JMB00 Chief's Report JMC00 OMB Report Approval JMD00 ASA (CW) Report Approval JN000 All Other Feasibility Studies/Investigations JO000 Management Documents JOA00 Project Management Plan (PMP) JOB00 Acquisition Plan JOC00 A/E Contract Documents JOD00 Coordination Documents JOE00 Study Funds Control Documents JOF00 Trip Reports JOG00 Minutes of Review Meetings JOH00 All Other Management Documents and Activities K0000 Project Agreements KA000 Preconstruction Engineering and Design (PED) Agreement KB000 Draft PCA KC000 Federal/Non-Federal Allocation of Funds Table C. REFERENCE TO STATUTES, REGULATIONS, AND GUIDANCE III. Work Breakdown Structure IV. Organization Breakdown Structure A. EXECUTIVE COMMITTEE B. PROJECT REVIEW BOARDS (PRB'S) C. PROJECT DELIVERY TEAM (PDT) Corps of Engineers, Chicago District Planning, Programs and Project Management Division (PM) Technical Services Division (TS) Office of Counsel (OC) Public Affairs Office Contracting Office Support Offices/Organizations Information Management Resource Management

41 42 42 42 42 43 43 43 43 43 44 44 44 44 44 44 45 45 45 45 45 45 45 46 46 46 46 47 47 47 47 48 52 54 54 55 56 57 57 57 58 58 58 58 58 58

iii

................
................

In order to avoid copyright disputes, this page is only a partial summary.

Google Online Preview   Download