SECTION 010000 - DP&R SPEC TEMPLATE - Denver



SECTION 01 42 10 REGULATORY REQUIREMENTS

GENERAL

1. RELATED DOCUMENTS

A. Contract Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

2. SUMMARY

A. This Section identifies primary compliance with the State, and City and County of Denver’s regulatory requirements including:

1. Colorado Department of Transportation (CDOT).

2. Denver Department of Public Works

a. The Division of Wastewater Services

b. Right of Way Services

c. Construction Engineering

d. Traffic Engineering

3. Applicable Utilities

4. Denver Department of Public Health and Environment ()

a. Regulated Asbestos Contaminated Soils Standard Operating Procedures (RACS SOP), Denver Department of Public Health and Environment (DDPHE) – Environmental Quality Division, May 2, 2019 (see Appendix).

b. City and County of Denver – Standard Materials Management Plan (MMP), Denver Department of Public Health and Environment (DDPHE) – Environmental Quality Division, November 13, 2019 (See Appendix).

c. City and County of Denver – Guidance for Reuse of Soil on City Projects, Denver Department of Public Health and Environment (DDPHE) – Environmental Quality Division, October 5, 2017 (See Appendix).

B. Construction shall be based on the latest edition of the referenced codes including additions and revisions thereto that are in effect at the time of project bidding.

3. BUILDING CODE

A. All construction work shall be governed by the Building Code for the City and County of Denver, latest edition. This is based upon the International Building Code of the International Code Council with Denver Amendments to this code.

4. DENVER BUILDING DEPARTMENT

A. For review and approval of all construction documents for compliance to the Denver Building Code:

City and County of Denver

Community Planning and Development

Building Inspection Division

201 West Colfax Avenue, Dept 205

Denver, Colorado 80202

Telephone 720-865-2720

Fax 720-865-2880

5. DENVER FIRE DEPARTMENT

A. For review and approval of plans for compliance with the Denver Fire Department’s requirements as they apply to projects for the Department of Public Works:

Denver Fire Department

745 W. Colfax Ave.

Denver, Colorado 80204

Telephone 720-865-2833

B. The Contractor is advised that the Denver Fire Department – Fire Prevention Bureau requires permitting for the following activities as they apply to the scope of work. The Contractor is responsible for obtaining the appropriate permits necessary to complete the work. All costs associated with this permitting and policy compliance shall be the responsibility of the Contractor. The policies all reference the International Fire Code (IFC).

1. Hot Work: “Hot work” shall be defined as the operation of any equipment or tool that creates sparks, hot slag, or radiant or convective heat as a result of the work. This includes, but is not limited to, welding, cutting, brazing, or soldering.

2. Use and storage of compressed gas for both temporary storage and permanent facility installation. This includes, but is not limited to, flammable gas (excluding propane-LPG), oxidizer (including oxygen), and inert and/or simple asphyxiates.

3. Tank installation, which includes above-ground storage tanks (AST) and underground storage tanks (UST) for both temporary tanks and permanent facility installations.

C. In addition to the above permits, the Denver Fire Department may require other permits that are associated with the specific work in the Contract Documents. Policies provided by the Denver Fire Department are meant to provide basic information for the most common conditions and situations. In any given occupancy, many other International Fire Code (IFC) requirements may be enforced. These should be addressed with the Denver Fire Department before construction begins and during construction with premise inspection(s). Any questions can be addressed to the Fire Prevention Bureau between 6:30 a.m. and 9:00 a.m. Monday-Friday at 720-913-8242 or 720-913-8237.

6. THE DENVER OFFICE OF DISABILITY (ADA) COMPLIANCE

A. Construction shall be based on the latest edition of the referenced codes including additions and revisions thereto that are in effect at the time of project bidding.

City and County of Denver

Human Rights and Community Partnerships

Office of Disability Rights

201 West Colfax Avenue, Dept 1102

Denver, CO. 80202

*Note: Currently the 2010 ADA standards for accessible design and the Transportation Standards and Details for the Engineering Division, Denver Public Works Department, 7.0-8.1 are being used as reference documents.

7. SUBSURFACE UTILITY ENGINEERING (SUE)

A. Colorado Senate Bill 18-167 (SB18-167) established additional requirements for Subsurface Utility Engineering Notification. Parks projects meeting the criteria of an SUE Required project shall comply. Refer to the 811 website for SUE Required Project criteria.



B. Per SB18-167 all new underground facilities must be electronically locatable when installed

C. As-Built drawings shall be provided for all SUE Required Projects.

PRODUCTS (Not Used)

EXECUTION

1. PERMITS AND CERTIFICATIONS

A. The Contractor shall acquire all applicable permits for the contracted scope of work. Refer to General Conditions 317 “Permits and Licenses.”

B. The Contractor shall maintain records on site of all permits acquired by federal, state, and local agencies. Posting of permits shall conform to requirements of the respective agencies.

C. At the completion of any inspection by other agencies, the Contractor shall forward copies of the status of the inspection and copies of any approved or “signed-off” inspections by the respective agencies to the Project Manager.

D. At the time of request for Substantial Completion, the Contractor shall forward to the Project Manager all permits approved by the respective agencies.

MEASUREMENT AND PAYMENT

1. MEASUREMENT

A. No separate measurement shall be made for work under this Section.

2. PAYMENT

A. No separate payment will be made for work under this Section. The cost of the work described in this Section shall be included in the Contract price.

END OF SECTION 01 42 10

................
................