Radioactive Air Emission Approval to Construct
Application Phase
Applicant Start
Applicant reviews activities
requiring an Air Emission Approval
A
to Construct
Applicant determines if project is exempt under WAC 246-247-020
Exempt
Not Exempt
No action required
Applicant determines if exemption request Requirements are met under WAC 246-247-
020(b) or (c)
Applicant
applies for an Exemption
B
Met
Not Met
Applicant submits a Notice of Construct application to the DOH in accordance with WAC
246-247-110
Radioactive Air Emission Approval to Construct
Department of Health (DOH)
Public or other interested party
No License Required
30 days
Review and Issuance Phase
DOH reviews the application for completeness
Incomplete
Complete
DOH requests additional information
DOH reviews application and issues determination
Deny
Approve
30 days
Applicant reviews conditions of the Approval to Construct
Accepts
Objects
Issues Denial Letter with Request for Adjudicative Proceedings (RAP) form
DOH sends applicant letter with
draft Approval to Construct
Within 30 days of receiving the draft Approval
Applicant sends written acceptance to DOH
Licensee can start construction. Once construction is complete, applicant notifies DOH to issue
License to Operate.
C
Issues Final Approval to Construct
Applicant cannot work. Application may be revised and resubmitted to DOH
headquarters. Appeal is processed according WAC 246-10, RCW 34.05,
and RCW 43.70.115
Within 28 days of decision
Issues Denial Letter with Request for Adjudicative Proceedings (RAP) form
Legend: A =Hyperlink
=Progression
=Revision
=Optional
For more information on this or any permitting process visit or call the Governor's Office for Regulatory Innovation and Assistance at (800) 917-0043
Rev. 2015 08 18
Appeal Phase
Application Phase
Applicant Start
Applicant reviews activities exempt under WAC 246-247-020
A
Not Exempt
Exempt
Approval to Construct and License to Operate
B may be required
Applicant submits New Exemption Application to the Washington
State Department of Health (DOH) headquarters
Radioactive Air Emission Exemption from Approval to Construct and License to Operate
Department of Health (DOH)
Public or other interested party
30 days
DOH reviews application for completeness
Incomplete
Complete
DOH requests additional information
30 days
DOH reviews application to determine if project meets
exemption criteria
Exemption Denied
Exemption Granted
Review and Issuance Phase
Appeal Phase
Applicant cannot proceed with project
Applicant may revise exemption application and resubmit
DOH issues exemption denial letter
with the Request for Adjudicative
Proceedings (RAP) form
Applicant submits the RAP to DOH headquarters. The
appeal is processed according to WAC 246-10,
RCW 34.05, and RCW 43.70.115
Applicant submits a Notice of Construction Application
Applicant can start work
Within 20 days of decision
DOH issues exemption letter with
RAP form
Legend: A =Hyperlink
=Progression
=Revision
=Optional
For more information on this or any permitting process visit or call the Governor's Office for Regulatory Innovation and Assistance at (800) 917-0043
Rev. 2015 08 18
Application Phase
Radioactive Air Emission License to Operate New Facility or Modification of an Existing Source (New Construction or Abatement)
Applicant
Start
Applicant reviews activities requiring an Air Emission Approval
to Construct
A
Department of Health (DOH)
Public or other interested party
Applicant reviews conditions and submits comments to DOH
Objects
Accepts
Applicant sends RAP
form
Applicant sends written acceptance
to DOH
Applicant can start work. For facilities subject to an Air
Operating Permit (AOP), submit required AOP change document
20 days
Within 30 days of receiving application
Within 28 days
DOH drafts License to Operate. Developed with the Licensee
DOH sends License to Operate Conditions and Limitations (C/L)
with Request for Adjudicative Proceedings (RAP) for applicant
DOH Review and Resolve
Yes
No
DOH issues final License to Operate letter
Send notice per RCW 70.98.080(2) to local jurisdiction
DOH issues denial letter with Request for Adjudicative Proceedings (RAP) form
Notice per RCW 70.98.080(2)
Opportunity to comment
Comment
No Comment
Submit per RCW 70.98.080(2)
Hold formal hearing per RCW 70.98.080(2)
Resolved
Yes
No
Review and Issuance Phase
Appeal Phase
Within 28 days of decision
Applicant submits RAP to DOH headquarters or revises application and resubmits. Appeal is processed
according to WAC 246-10, RCW 34.05, and RCW 43.70.115
Legend: A =Hyperlink
=Progression
=Revision
=Optional
For more information on this or any permitting process visit or call the Governor's Office for Regulatory Innovation and Assistance at (800) 917-0043
Rev. 2015 08 18
Radioactive Air Emission License to Operate New Facility or Modification of an Existing Source (New Construction or Abatement)
Link A
Correspondence can be mailed to:
Department of Health Office of Radiation Protection Radioactive Air Emissions Section 309 Bradley Boulevard, Suite 201 Richland, WA 99352 Email: AIRRichland@doh. Fax: (509) 946-0876
Back to Schematic
For more information on this or any permitting process visit or call the Governor's Office for Regulatory Innovation and Assistance at (800) 917-0043
Rev. 2015 08 18
Application Phase
Applicant Start
Radioactive Air Emission Modification/ Revision Approval to Construct
(New Construction or Abatement Controls)
Department of Health (DOH)
Public or other interested party
Applicant submits a Modification/ Revision Approval in accordance with WAC 246-247-110
A
30 days
DOH reviews the application for completeness
Incomplete
Complete
DOH requests additional information
DOH reviews application and issues determination
Deny
Approve
Issues Denial Letter with Request for Adjudicative
Proceedings (RAP) form
30 days
Applicant reviews conditions of the Approval to Construct
Objects
Accepts
DOH sends applicant a letter with a draft Approval to Construct
Review and Issuance Phase
Within 30 days of receiving the draft Approval
Applicant sends written acceptance to DOH
Licensee can start construction. Once construction is complete, applicant notifies DOH to issue
License to Operate.
B
Issues Final Approval to Construct
Letter
Within 28 days of the decision
Applicant cannot work and they may revise and resubmit application. The RAP will be submitted to
DOH headquarters. Appeal is processed
according to WAC 246-10, RCW 34.05
and RCW 43.70.115
Issues Denial Letter with Request for Adjudicative
Proceedings (RAP) form
Legend: A =Hyperlink
=Progression
=Revision
=Optional
For more information on this or any permitting process visit or call the Governor's Office for Regulatory Innovation and Assistance at (800) 917-0043
Rev. 2015 08 18
Appeal Phase
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- instruction manual manual de instructiones
- operator s manual sears parts direct
- radioactive air emission approval to construct
- last digit of model number varies
- prosecuting criminal conspiracies
- the formal incompleteness of object languages of
- errata federal communications commission
- teaching introductory statistics with activities and data
- working document toward a preliminary new report itu r m
- criminal procedure outline nyu law
Related searches
- radioactive iodine dangers to family
- radioactive pill to kill thyroid side effects
- radioactive pill to kill thyroid
- how to construct a frequency distribution
- air lb hr to scfm
- modal acoustic emission testing
- how to construct a truth table
- air force enlisted to commissioning programs
- air force enlisted to officer
- air force enlisted to officer process
- how to construct an intro paragraph
- air canada flights to toronto