Design Projects Documentation
Design Projects Documentation
|Title of the project: |Radio Controlled Cargo Aircraft |
|Project description: |Design and build an RC cargo Aircraft capable of lifting the payload for SAE |
| |sponsored competition. The design will be scored in three categories: design |
| |presentation, and accuracy of the predicted payload. The objective is to familiarize|
| |the design process from concept, to detail design and report presentation, to final |
| |hands-on manufacturing as “real time“design engineering. |
|Team members: |Daryl Johnson, Jeff Leeper |
|Sponsor Industry: |SAE |
|Project year: |1989 |
|Title of the project: |Pier Block Machine Redesign Progress Report |
|Project description: |Redesign a concrete form shaping machine owned by the Concrete Shop of Vancouver, |
| |Washington. The existing machine had been overused thus exposed safety hazards. It |
| |was also difficult to operate. The goal of the redesign is to improve the operation |
| |control, reduce the safety hazards, and increase reliability and durability of the |
| |machine. |
|Team members: |Mike Dockter, Tom Lonergan, Colin Wright |
|Sponsor Industry: |The Concrete Shop of Vancouver, Washington |
|Project year: |1990 |
|Title of the project: |Tank Farm |
|Project description: |Design a new tank farm for Imperial Paint for its paint storage facilities. The |
| |objective is to comply with the new environmental protection regulations governing |
| |all bulk storage facilities that would take effect in December 1998. The task also |
| |intends to maximize the efficiency of allocation of petroleum based material in the |
| |current storage. |
|Team members: |Sam Louie, Mike McConnel, Tony Yan |
|Sponsor Industry: |Imperial Paint |
|Project year: |1990 |
|Title of the project: |Redesigning The Tensioning System For An I.D. Silicon Wafering Saw |
|Project description: |Redesign a wafer I.D. saw to improve the slicing process in terms of throughput and |
| |wafer quality for Wacker Siltronic, Inc. The target is to develop a system that |
| |enables rapid blade changeover (5 to 10 minutes) while improving the wafer quality as|
| |less than 30 microns of run-out at 3 standard deviations. The project includes two |
| |separate phases, 1) a remote tensioning system, and 2) a device easy and efficient |
| |for mounting the pre-tensioned blade to the saw. |
|Team members: |Paul K. Durant, Chris Burkle, Brent Running |
|Sponsor Industry: |Wacker Siltronic Inc |
|Project year: |1995 |
|Title of the project: |Metal Building Assembly Fixture |
|Project description: |Redesign the current building assembly fixture to improve its performance and |
| |increase its usability. The fixture design will include 12 – 16 ft wide buildings, |
| |allow different framing member spacing between building sizes, and allow installation|
| |of doors and windows anywhere around the building perimeters. The redesigned fixture|
| |will be able to work on the same site where the job is. The fixture size will be |
| |adjusted to 8 ft long and 4 ft wide for transportation. |
|Team members: |Russel Reigel, Steve Rothe, Ali Kashi |
|Sponsor Industry: |Reigel Buildings, Inc |
|Project year: |1994 |
|Title of the project: |Design of a Ground Ambulance Gurney |
|Project description: |Design a Ground Ambulance Gurney (a medical emergency wheeled cot or stretcher) for |
| |Life Port to stay in competition on the gurney market. The design model NE-31 must |
| |meet the following constraints: |
| |18” (height) x 76” (length) x 22” (width). |
| |Able to carry 500lb patient with maximum deflection of 1”. |
| |The four wheel casters must be free to allow the gurney to maneuver around corners. |
| |Compatible with the existing attachment systems used in ambulances. |
|Team members: |Richard Berney, David Graham, Mike Rusch |
|Sponsor Industry: |Life Port, Inc |
|Project year: |1990 |
|Title of the project: |A Method to Rebuild Delaminated Color Printer Heads |
|Project description: |Designing a procedure to rebuild the delaminated color printer heads so that the |
| |returned defective heads can be reused. The rebuilt heads not only need to be |
| |functional, but also need to meet the following goals: |
| |The built head will have a service life of 7 years. |
| |The head rebuilding must use the existing equipment at Tektronix as much as possible.|
| |The process must complete by June 9, 1989. |
| |Four phases are developed for the rebuilding process: |
| |Disassembly and sorting. |
| |Surface preparation. |
| |Adhesive selection. |
| |Reassembly. |
|Team members: |Mark Erickson, Eric Muhvy |
|Sponsor Industry: |Tektronix |
|Project year: |1989 |
|Title of the project: |Unwind Stand for James River Corp |
|Project description: |Design an unwind stand for James River Corporation. The design focuses on areas of |
| |self loading, brake, and tension controls. The targets are to increase productivity,|
| |eliminate paper breakage, ensure the edge alignment, ensure self loading, and |
| |properly position the bulk rolls. Utilizing the latest technology in paper tension |
| |control and brake devices, the design also includes a scissor lift mechanism mounted |
| |in the floor, and a hydraulic actuator integrated with a photo-electronic senor for |
| |lateral adjustment. |
|Team members: |Peter Arola, Kevin O’Connell, Man Wah Poon, Arthur Miller |
|Sponsor Industry: |James River Corporation. |
|Project year: |1987 |
|Title of the project: |Warn Vacuum Locking Hub Group |
|Project description: |Design and prototype a remotely-actuated mechanisms which can engage and disengage |
| |the clutch ring with the inner drive gear for Warn Industries, Inc. The design |
| |objectives focus on the mechanism itself as follows, |
| |The remote actuation will be accomplished by way of vacuum or pressure delivered |
| |through the spindle. |
| |The design must allow the clutch ring to move to the locked and unlocked positions |
| |repetitively and reliably. |
| |It must survive the exposed location of a front wheel hub in a four-wheel drive |
| |vehicle. |
| |The mechanism must fit into approximately the same internal cavity of the hub as |
| |found on Warn’s current design. |
|Team members: |Brian Baker, Mike MacGregor, Ken Millard, Daniel Morrow |
|Sponsor Industry: |Warn Industries, Inc. |
|Project year: |1995 |
|Title of the project: |The Densification of Energy Wood Material for Economical Transpiration to Distant |
| |Energy Markets |
|Project description: |The objective of the design is to propose and evaluate a method to densify (bale) |
| |waste wood materials for convenient and economical long range transportation to |
| |distant energy markets. The design focuses on two areas of processes, the method of |
| |densifying waste wood and means of transportation for shipping waste wood. |
|Team members: |Richard Allen, Steve Ringous, Roger Doolin, Ali Khashab |
|Sponsor Industry: |USDA Forest Service Pacific Northwest Research Station. |
|Project year: |1995 |
|Title of the project: |Tillamook Cheese Project |
|Project description: |The objective is to design an automated cheese trimming system to replace manual |
| |operation that causes injuries due to repetitive motion. Eliminating manual |
| |operation in this trimming process reduces the medical cost due to the injuries. |
| |Along with the savings from medical costs and recycling the excessive cheese from |
| |oversized cheese block, this project would ultimately bring $80,000-$10,000/yr |
| |savings to Tillamook Cheese Corporation. The automated cheese trimming system would|
| |be integrated into the existing conveyor system at Tillamook Cheese Corporation. |
|Team members: |Jim Jackson, Fred Frey, Jerry Stole, Terry Daugherty |
|Sponsor Industry: |Tillamook Cheese Corporation. |
|Project year: |1992 |
|Title of the project: |Bonnelville Navigation Lock |
|Project description: |The design proposes a new navigation lock gate actuating mechanism. The existing |
| |navigation lock that has not been replaced in the last twenty years has a long |
| |downtime in the event of mechanical failure. The long downtime could be up to 3 |
| |weeks that disrupts the traffic on the entire Columbia River. The components of the|
| |existing lock were custom made that takes longer time and expensive to replace. The |
| |new navigation lock would be less expensive in maintenance and shorter downtime that |
| |would ease the bottleneck condition developed on the Columbia River. |
|Team members: |Jim Jackson, Fred Frey, Jerry Stole, Terry Daugherty |
|Sponsor Industry: |US Army Corps of Engineers, Mechanical Design Section, Portland Oregon. |
|Project year: |1986 |
|Title of the project: |Design of Condensate Return System |
|Project description: |This is a preliminary design and economic evaluation of a steam condensate recovery |
| |system that will serve Ballast Water Treatment Plant for Portland Ship Repair Yard. |
| |One of the Ship Yard services is the separation and treatment of a mixture of water |
| |and crude oil, known as ballast water. The separation process utilizes steam from a |
| |nearby boiler house to heat and separate the mixture. After repeated cycles, the oil|
| |will be skimmed and the water will reach its purity level accepted to return to |
| |sewage or the Willamette River. Before this project, none of the condensate |
| |generated in the whole process was recovered. The water and its remaining heat all |
| |lost along with the chemicals in the water to prevent the corrosion in the boiler. |
| |The design objective is to capture the maximum amount of steam condensate possible |
| |and return it to the boilers at the highest temperate possible with free maintenance |
| |and reasonable cost. |
|Team members: |Scott Hewitt, Bill McKay, Dan Watson |
|Sponsor Industry: |Portland Ship Repair Yard, Port of Portland, Swan Island |
|Project year: |1990 |
|Title of the project: |Pneumatic Switch |
|Project description: |Redesign a pneumatic switch, an HVAC valve used in a cab of a truck for Sprague |
| |Aristo-Aire to meet their customer needs. Driven by the cost (under $8.00), the |
| |redesign report discussed two alternatives, use of the spool valve operated by a cam,|
| |and an adaptor allowing the current product to fit an Eaton style rocker arm switch, |
| |and picked latter as its final decision. The report gathered information of existing|
| |valve mechanisms, and did analysis including valve body, cam piston, bulking, |
| |pressure vessels, heat transfer, and rocker plunger. The report presents |
| |discussions of quality, decision matrix, and drawings |
|Team members: |Michael Pepelaskov, Danny Yuwono, Scott Hartell, Tom Lee |
|Sponsor Industry: |Sprague Aristo-Aire |
|Project year: |Dec., 1995 |
|Title of the project: |Freightliner Twin Steer |
|Project description: |The Twin Steer system is used in heavy duty truck to increase the load carrying |
| |capacity. Freightliner’s Twin Steer system poses problems when navigating uneven |
| |byways and rugged terrain. Using QFD (Quality Function Deployment) techniques, the |
| |project focuses on the front suspension used universally on various models of |
| |Freightliner trucks that will distribute the loading evenly over both the front |
| |axles. The proposal for the new suspension offers improved steering geometry over |
| |the current design and free of interference of the tire and the steering linkage. |
| |The intent is to solve the problem of 1) possible overloading on one axle; 2) |
| |interference of the right tire with the steering linkage. The final design uses a |
| |mix of exiting Freightliner components and new parts manufactured in house from |
| |standard Freightliner materials. The redesign has achieved equalization, and has |
| |been recommended to be a standard option for Freightliner heavy duty truck. |
|Team members: |Doug Johnson, Eric Kominek, Chris Phimister, Dilan Silva |
|Sponsor Industry: |Freightliner Corporation. |
|Project year: |unknown |
|Title of the project: |Refrigeration Update Design |
|Project description: |The project presents the design and analysis of a retrofit kit for semi-trailer |
| |refrigeration unit to replace earlier style of Thermo King model SNWD units and |
| |subsequent reinstallation into the glider kit to produce a unit which is a comparable|
| |in design and performance to late model Thermo King SB style units. The |
| |accomplishment also includes the update that is less than half of the cost of a new |
| |refrigeration unit. The design features include a flush mount evaporator section, |
| |improved evaporator fan design, and the conversion from CFC based refrigerant to an |
| |EPA approved HFC based alternative. The project consists four major tasks, 1) frame |
| |design and analysis; 2) evaporator fan selection and analysis; 3) alternative |
| |refrigerant selection and analysis; and 4) construction of the prototype Glider kit. |
| |The project also covers cost analysis of building the prototype and recommended |
| |testing procedure for determining the refrigeration performance of the prototype |
| |under actual operation condition. |
|Team members: |Andrew Gorman, Dodd Juenemann, Scott Basom |
|Sponsor Industry: |Thermo King Corporation |
|Project year: |June, 1994 |
|Title of the project: |Final Report Prototype Air Burst Screen Cleaning System |
|Project description: |The objective of the project is to develop a functional prototype of an air burst |
| |system to remove debris from two selected dewatering screens, as means of studying an|
| |effective replacement to the mechanical systems at the new JBS (Juvenile Bypass |
| |System) at Bonneville Dam. The project is to meet the request from the National |
| |Marine Fisheries Service (NMFS) to improve the survival rate of the young salmon |
| |during downstream migration. |
|Team members: |Dwayne M. Weston, Jeff Howard, James N. Rawlinson |
|Sponsor Industry: |U.S. Army Coprs of Engineers, Portland District |
|Project year: |June 1997 |
|Title of the project: |Large Building Monitoring |
|Project description: |The project is about the development of an energy monitoring procedure for large |
| |commercial buildings. The project presents a method that substantiates and pinpoints|
| |the savings attained in monitoring the various energy loads from the retrofits. The |
| |project derived the answers about the reason of monitoring a particular load, the |
| |measurement precision, recording frequency, the duration of the monitored load, the |
| |method of gathering ambient weather information, power quality analysis versus |
| |monitoring accuracy, monitoring procedure versus multiple-load testing, data |
| |acquisition system being stationary versus portable, and compatibility between |
| |procedure and the retrofit system. |
|Team members: |Dryan D. Babcock, Kevin C. Fish |
|Sponsor Industry: |Microgrid Inc. |
|Project year: |June 1993 |
|Title of the project: |IDC Fab Chiller Project |
|Project description: |The project analyzes the alternative sources of energy for facility cooling. These |
| |alternative energy sources are the use of natural gas and absorption driven chillers |
| |instead of electricity driven to cool the incoming air or remove the water vapor. |
| |The project focuses on reducing electrical energy costs for a chiller plant by using |
| |heat recovering from gas-engine-driven (GED) chillers to power absorption chillers. |
| |The design requirements are 10000 ton maximum required cooling load, payback period |
| |of 1 ½ to 2 years, inside dry bulb temperature of 70 (F, inside relative humidity of |
| |42-45%, and use off-the-shelf components. Additional requirements are space |
| |constraints, use of heat recovery, chilled water temperature, system reliability, |
| |maintenance downtime, system life, system cost, and fab location and ambient |
| |conditions (Austin, Texas). |
|Team members: |David Bueffel, Doug Crombie, Tony Hunt, Danny Wilhelmi |
|Sponsor Industry: |Industrial Design Corporation (IDC) |
|Project year: |June 1997 |
|Title of the project: |Human Powered Hydrofoil Design Report |
|Project description: |The project investigates the propeller and foil theories, and presents programs to |
| |predict a ten foot diameter air propeller and a wing tapering from a 2” to a 4 “ |
| |chord length. The project studied ergonomics and evaluated the data from the riders |
| |who were tested for their horsepower output (0.9 to 1 horsepower output is expected |
| |for an athlete pedaling at 100 rpm. The project presents a drive train system design|
| |that supplies the power to propeller from the rider using standard bicycle |
| |components. Using FEA, the project presents the design of the hull and tubular |
| |structures to support the foils and propeller. |
|Team members: |Craig Ulrich, Robert Ray, James Oliver, Gerald Knrdonowy, Linda Jackson, Paul |
| |Giuffrida |
|Sponsor Industry: |The International Human Powered Vehicle Association, Inc |
|Project year: |June 1992 |
|Title of the project: |1996 SAE Mini Baja Final Report |
|Project description: |The project is of an SAE sponsored annual Mini Baja competition. The ultimate goal |
| |of the project is to design and build a prototype of an off road vehicle. The intent|
| |of the prototype was the acquisition of suspension and drive train loading data, as |
| |well as information leading to the improvement of the overall design. The maximum |
| |vehicle size is 60” wide x 96” long, 8hp, and 4 cycles Briggs and Stratton engine. |
| |The competition is intended to simulate an industrial engineering situation in the |
| |form of prototype development, and is limited to a maximum production cost of $2500 |
| |per vehicle in a 4000 vehicle run. In addition to the technical specifications, SAE |
| |sets strict safety regulations. Vehicles conforming to safety and technical |
| |regulations are subjectively judged by practicing engineers based on marketability, |
| |design innovation, aesthetics, and cost effectiveness. The cars then compete in |
| |dynamic events intended to evaluate their performance characteristics. Dynamic |
| |events consist of a maneuverability slalom course, a hill climb, a drag race, and a |
| |four hour endurance event. |
|Team members: |Chris Aspmo, Dave Hort, Bill Hayhurst |
|Sponsor Industry: |Society of Automotive Engineers |
|Project year: |June 1996 |
|Title of the project: |Water Heater Design Project: Out for the Long Run |
|Project description: |The project researches the causes of the tank failure of residential water heaters |
| |and presents a new design of hot water heater with longer life (35 years versus 5-12 |
| |years of conventional water heater lives). The result of the project is a design |
| |that employs an anodic protection system and a sediment removal system to protect the|
| |tank from failure and thus increase tank life to at least 35 years. Schematics of |
| |the design were created such that a prototype can be constructed. The prototype can |
| |then be used to test the concepts generated. |
|Team members: |Jake Abraham, Peter Villanueva, Samarith Loeung |
|Sponsor Industry: |American Water Heater Group |
|Project year: |Unknown |
|Title of the project: |Condensate Recovery System |
|Project description: |The project was to evaluate the economic feasibility of recovering lost energy and |
| |/or water from the Tall Oil area steam condensate. The team concluded that the Tall |
| |Oil area under utilized the heat value from condensate produced. The condensate |
| |collection tank was under sized and only returned a portion of the available |
| |condensate for boiler water preheat. The project proposed Liqui-Mover |
| |collection/pumping system that would have a larger capacity and return more |
| |condensate. A new plate and frame heat exchanger is presented to replace with the |
| |shell and tube heat exchanger thus the heat transfer would be more effective from |
| |returned condensate to the boiler feed water. The new heat exchanger combined with |
| |the Tall Oil return system would cost Hercules $27,600 and save $40,000, that yields |
| |103% return on cost (ROC). |
|Team members: |Art Utter, Fred Imayoshi, Randy Mathieu, Susan Grant |
|Sponsor Industry: |Hercules, Inc |
|Project year: |June, 1995 |
|Title of the project: |UHMW-PE Parts Welding |
|Project description: |The project involves the development and design of an improved process for joining |
| |ultra-high molecular weight polyethylene (UHMW-PE) hubs to sprockets. To spin-welded|
| |the hubs to the sprockets, Solidur used a lathe to spin the hub against the |
| |stationary sprocket, generating enough heat from friction to weld the parts. The |
| |complexity of the lathe requires skilled labor intensity from the machinists. The |
| |molten plastic being thrown from the parts also became safety concerns. The project |
| |recommends an improved form of spin-welding through the use of automation that would |
| |reduce the skill level required to run the lathe, and free the lathe for other uses. |
| |Based on the economic analysis of costs, the team determined the configuration of the|
| |spin-welding fixture from the two alternatives, a dual-spindle welder that could weld|
| |two hubs at once, and conversion of an out-of-tolerance milling machine, and decided |
| |to use the conversion of an out-of-tolerance milling machine. |
|Team members: |Brian Bonn, John Calderbank, Larry Coon, Rich Rampone |
|Sponsor Industry: |Solidur Pacific Co. |
|Project year: |June, 1993 |
|Title of the project: |Tri-County Metropolitan Transportation |
|Project description: |The project was to develop an alternative wheelchair restraint system for the |
| |physically challenged riders of the Tri-County Metropolitan Transportation District |
| |of Oregon (Tri-Met) that reduces the company’s liability for injuries sustained by |
| |the restrained passengers and the drivers that must insure the safety of the regarded|
| |passengers. Tri-Met had been able to accommodate the wheelchairs before the change |
| |of modern wheelchair styles such as varied sizes of tires between front and rear, and|
| |3 tires instead of 2. Tri-Met previous restraint system could not work as intended. |
| |The project provides the development of a universal wheelchair restraint system to be|
| |installed on the buses to replace the outdated system for all styles of wheelchairs |
| |to meet ADA (American with Disabilities Act) and FTA (Federal Transit Administration)|
| |requirements. |
|Team members: |Brad Grabo, Loren Morris, Kellie Reid, Eric Tubbin |
|Sponsor Industry: |Tri-Met. |
|Project year: |January, 1996 |
|Title of the project: |Step-Chair Project |
|Project description: |Initiated by the chair of Electrical Engineering Department of PSU, Dr. Scghaumann, |
| |the project was a joint development between both the electrical and mechanical |
| |engineering senior students. The objective was to build an electro-mechanical device|
| |that would attach to a wheelchair, regardless of configuration, providing a means of |
| |traversing a step or a curb. The project presents the design focusing on the |
| |constraints of weight, size, automation, safety, efficiency of power use, ease of |
| |retrofittability, and climb time. The final deliverable includes a proof-of-concept |
| |prototype and a written report containing a recommendation, conceptual CAD drawings, |
| |and FEM analysis. |
|Team members: |Joe Brackin Dale Campbell, Tim Culligan, Bob Essex, Erik Halverson, Dave Henkemeyer, |
| |Jesse Inkpen, Larry Montoya, Craig Sarkinen, Mike Willardson, Ken Wolf |
|Sponsor Industry: |Electrical and Mechanical Engineering Dep’t of PSU. |
|Project year: |June, 1996 |
|Title of the project: |Facility Plan |
|Project description: |The project was to redesign an existing factory layout at Sequent Computer Systems, |
| |Inc. Focused on the subset of the overall factory layout and closely followed |
| |established methodology used in facilities planning at Sequent, the project reaches |
| |viable solutions for two large problems related to Production Floor Layout and Job |
| |Shop Layout. The solution meets the customer requirements for the new manufacturing |
| |system production and product logistics. |
|Team members: |Christian Vega, John Peterkort, James Chen, Vinesh Lal |
|Sponsor Industry: |Sequent Computer Systems, Inc. |
|Project year: |June, 1993 |
|Title of the project: |Curb-Climbing Wheelchair Redesign |
|Project description: |The project is the continuation of a senior electrical-mechanical joint project that |
| |began in 1996. The design was never operational though the substantial progress was |
| |made in the basic concept of the chair. Based on the previous design, the project |
| |was to redesign and build a prototype curb-climbing wheelchair that is safe and |
| |functional to both ascends and descends curbs automatically. The project spotted the|
| |problems from the previous design thus, setup new requirements and constraints, and |
| |proposed solutions so that the new prototype would be operational. |
|Team members: |Robert Deline, Clint Hutzenbilier, H. Mac Kuokka, Kent Nielson, Valentine Powers |
|Sponsor Industry: |Electrical and Mechanical Engineering Dep’t of PSU. |
|Project year: |June, 1997 |
|Title of the project: |Curb-Climbing Wheelchair Redesign |
|Project description: |The project targeted the existing problems of Single Roll Tissue (SRT) O-thane Belt |
| |Transport System that introduces product defects and resulting downstream machinery |
| |malfunction issues in the tissue processing. The project was to design a new SRT |
| |Transport System that eliminates snagging of SRT tails while meeting the needs of the|
| |existing system. Using QFD (quality function deployment) techniques, the project |
| |achieved a Retracting Table Top Chain SRT Transport System Design leading to reducing|
| |associated costs thus increasing productivity. |
|Team members: |Jeanne Lewis, Kellie Reid |
|Sponsor Industry: |James River Corporation. |
|Project year: |June, 1997 |
|Title of the project: |Design Project – James River Corp. (JRC) Wauna Mill |
|Project description: |The project utilizes the design methodology so called “Five Diamond Methodology”, |
| |developed by Migliore and Goulding of Portland State University, a design development|
| |process from initial conception to final implementation. The report details the |
| |methodology as it was used to solve problem associated with the work order requested |
| |at James River Corporation. The work order selected was a request for a closed loop |
| |liquid/liquid heat exchanger to cool the air compressor. Under the constraints of no|
| |change to the compressor and compressor operation, less than $100,000 budget, and |
| |keeping the water process chemistry acceptable, the project provides alternative |
| |approaches that are more cost effective than the corrosion inhibitors previously used|
| |at JRC to dealing with the corrosion problem of the air compressor leading to |
| |premature failure. |
|Team members: |Bob DeWitt, Geoff Ford, Martin Mance, Allen Zandonatti. |
|Sponsor Industry: |Wauna Paper Mill, James River Corporation. |
|Project year: |June, 1995 |
|Title of the project: |Freightliner Hood Tilt Assist Project |
|Project description: |The project was to redesign the hood tilt assist mechanism for more ergonomic reasons|
| |for Freightliner’s commercial trucks. Requiring less effort to open and close, the |
| |new proposed design offered a new hood tilt assist concept as an improvement upon |
| |Freightliner’s existing design. The final design for the hood locking mechanism |
| |utilized a linkage that mounts to the side of the radiator and also behind the front |
| |grill location. The design main advantage is its automation, meaning the driver |
| |needs only to open the hood in the conventional manner, and the locking mechanism |
| |automatically engages. The final design met Freightliner’s requirements of reducing |
| |the opening and closing forces to 35 and 40 pounts. |
|Team members: |Jaswant Sandhu, Ken Tran, Todd Wurster. |
|Sponsor Industry: |Freightliner Corporation. |
|Project year: |June, 1996 |
|Title of the project: |Evaluation and Redesign of a Bone Mill |
|Project description: |The project was about an evaluation and redesign of the bone mill for Acumed, Inc. |
| |Using functional decomposition techniques, the team performed an in-depth analysis on|
| |the previous design. Based on the knowledge and information gained during the |
| |preliminary assessment, the redesign generated the concept and prototype. Through a |
| |method of one-to-one comparison and using the criteria developed during the initial |
| |research, the team evaluated the redesign concepts and presented the most successful |
| |options of the redesign to Acumed so that Acumed could make the final decision on |
| |which prototype to pursue. The project presented a refined final prototype, a |
| |stainless steel, vertical cast body with integrated receiver bowl and inverting |
| |capability including drawings for manufacturing. The report also introduced new |
| |manufacturing processes including recommendations for fabrication and finishing |
| |processes into the design. |
|Team members: |Connie Drake, Shawn Gibbs, G. Vicky Jerome, Bruce Kell. |
|Sponsor Industry: |Acumed, Inc. |
|Project year: |June, 1994 |
|Title of the project: |Vehicle Diagnostics |
|Project description: |The project presents a study of the feasibility of monitoring the battery system of a|
| |Freightliner truck, and intends to measure the capacity of the battery by utilizing |
| |the data collected by Data Link of the truck. The goal is to predict when the |
| |battery is near the end of its life to start the truck. The Data Link of the truck |
| |previously gathered information about the trucks performance such as oil pressure, |
| |oil temperature, coolant temperature, ambient air temperature, and etc at 1-10 |
| |seconds. The project presents a test with the installation of additional analog |
| |sensors that measures the battery voltage, the current of the starter, and the |
| |battery temperature much faster. From the test data, a measurement of the capacity |
| |of the battery is calculated. From the calculated value, the characteristics of the |
| |start cycle, an estimation of the state of the battery is made. The information |
| |along with the start test is compared with the reference data from the start cycles |
| |performed on a new battery charged to specified percentages of its rate capacity. |
| |From the data, trends that indicate low battery capacity are identified. |
|Team members: |Jeff Lusardi, Wenyu Lin |
|Sponsor Industry: |Diameter-Benz Research and Technology Center, North America, Inc |
|Project year: |January, 1998 |
|Title of the project: |Proposal for Automated Molten Metal Delivery at Consolidated Metco |
|Project description: |Due to the request by Oregon Plant of Consolidated Metco, Inc for automation of a |
| |molten metal transportation and distribution system to reduce the cost and improve |
| |the die cast system, the project proposed a design of a semi-automatic system capable|
| |of delivering aluminum to an operator designated holding furnace without further |
| |human intervention. The project utilized concurrent engineering methods to research,|
| |evaluate, select, and design the system. |
|Team members: |Alan Hatfield, Tim long, Behnam Karandish, Qui Luu, Chris Stone |
|Sponsor Industry: |The Clackamas, Oregon Plant of Consolidated Metco, Inc |
|Project year: |June, 1998 |
|Title of the project: |Columbia Machine Palletizer |
|Project description: |The project proposed a replacement of the previous hydraulic system in Columbia |
| |Machine palletizer model FL200 with an alternate that performs as well as or better |
| |than the previous system, while eliminating environmental concerns, reducing noise, |
| |and maintaining consistent and reliable operation in a variety of climates. The |
| |project follows the design constraints such as non-hydraulic, same or better speed |
| |and control, environmentally safe, safe and smooth and quieter operation, reliable 24|
| |hours / day operation, option of redesign the structure, and fall within budget. |
|Team members: |Antonio Edgar, Andrew McGuire, Robert Grossnickle, Jeff Wey |
|Sponsor Industry: |Columbia Machine, Inc. |
|Project year: |Jan, 1998 |
|Title of the project: |Warn Clutch System |
|Project description: |Requested by Warn Industries for their clutch system used in their 8-kip and 12-kip |
| |winches, the project presented a new design utilized a pull and twist motion to |
| |disengage the winch, and utilized a spring to allow the rotated lever to snap back to|
| |engage the winch. The new design offered the feature that when the motor is running,|
| |the operator cannot snap the lever into the engaged position. The project report |
| |identified and solved the problems of the previous clutch lever. The new design |
| |conforms Warn Industries constraints and the standards of SAE. |
|Team members: |James E. Smith, Bardia Razzaghi, Bill Sterling, Dan Seale |
|Sponsor Industry: |Warn Industries, Inc |
|Project year: |Jan, 1992 |
|Title of the project: |Strapbinder J-Series Hose Clamp Semi-automatic Hand Tool |
|Project description: |Requested by A.J. Gerrad LlC Company, the project was to design a hand held (less |
| |than 18 lbs) semi-automatic tool to install any J-series pre-formed hose clamps. |
| |Traditionally, the hose clamp installation tools were either manual versions or semi |
| |automatic bench mounted units. This portable tool would reduce the cost therefore |
| |reduce the price and gain the market. Powered by the compressed air (80 psi) and |
| |with less than 30 seconds, this installation tool tensions the clamp and reports the |
| |clamping force being applied to the hose, and then holds the tension force until the |
| |clamp is sealed and the excess banding material is cutoff. |
|Team members: |Michael V. Fenton, Dean C. Marleau |
|Sponsor Industry: |A. J. Gerrard LLC Company |
|Project year: |June, 1996 |
|Title of the project: |Weld improvement Project |
|Project description: |The paper dealt with the time required in the weld area when change their products at|
| |Custom Hoists department of Warn Industries. The project focused on the setup |
| |process and new fixturing that would allow faster change from product to product. |
| |The team analyzed and determined the problems, and provided solutions that would |
| |reduce the required time to change products for welding. |
|Team members: |Scott Lambing, Jon R. Stroud, Cory Williams |
|Sponsor Industry: |Warn Custom Hoists, Warn Industries, Inc |
|Project year: |January, 1995 |
|Title of the project: |Drum Weld Fixture |
|Project description: |The paper presented a welding fixture that deals with welds between flanges and |
| |tubing on the winch drum at Custom Hoists department of Warn Industries. The |
| |existing fixtures did not work well and took too much time to setup. The project |
| |presented modifications on the existing fixtures to solve the problems the existing |
| |fixtures have. As a redesign, the modifications focused on the fixture holding the |
| |spool flanges firmly against the headstock and tailstock while allowing the flanges |
| |of the spool to rotate, and expanding outward against the flanges when activated. |
|Team members: |Scott Lambing, Jon R. Stroud, Cory Williams |
|Sponsor Industry: |Warn Custom Hoists, Warn Industries, Inc |
|Project year: |June, 1995 |
|Title of the project: |Palletizer Push Bar Design Proposal |
|Project description: |This proposal outlines a strategy for increasing the speed of a palletizer HL90 |
| |manufactured by Columbia Machine. With minimal additional cost, the goal of the |
| |project is to increase the processing speed by eliminating a product backup at the |
| |pusher section of the palletizer. |
|Team members: |Marvin Joanis, Arnold Top, Ralf Busby, Scott Witt |
|Sponsor Industry: |Columbia Machine, Inc. |
|Project year: |January, 1994 |
|Title of the project: |Human Powered Vehicle |
|Project description: |The project was to design and build a high performance vehicle to compete in the 1996|
| |ASME sponsored human-powered vehicle competition. The PSU human-powered vehicle is a|
| |semi-recumbent bicycle fully enclosed in a carbon fiber/Kevlar faring. Continued |
| |from the last year’s competition, this project focused on the fairing and additional |
| |seat design offered the improvements that allow a greater degree of reliability and |
| |rider comfort. |
|Team members: |Basem Abdallah, Shawn Murphy, Jason Wilson |
|Sponsor Industry: |ASME |
|Project year: |June, 1996 |
|Title of the project: |Veterinary Hospital Animal Cage Heater |
|Project description: |This report presents the design of a simple device that provides uniform heat to all |
| |parts of the animal, allows for bodily fluid drainage, easy to clean, and operates |
| |quietly without hazardous to animals during and after the animal surgery. The device|
| |does not interfere with the cage door motion and veterinarian’s view of the animal |
| |inside the cage. The design utilized a combination of existing devices which added |
| |to its flexibility. The device consists of a lightweight plastic slab that fits |
| |inside of a medium sized animal cage and two fans that attached to the slab allowing |
| |heated air to flow under the animal and out of the cage. |
|Team members: |Martia Jenkins, Hung Dang, Patrick Sandow, Jamie White |
|Sponsor Industry: |East Mill Plain Animal Hospital |
|Project year: |June, 1995 |
|Title of the project: |Electrical Resistance Space Heater |
|Project description: |The design presented a quiet, compact, smoothly warm, and inexpensive space heater |
| |that would compensate heat due to the heat loss varied from ventilation performance, |
| |and satisfy 10% occupants who always feel cold on their feet in the heating climate |
| |of the building. Cadet Manufacturing made heaters but not satisfactory to the 10% |
| |unsatisfied building occupants. The design offered features of the heater capable of|
| |floor, wall, or desk knee-hole mounting, one hour running and automatically shutoff, |
| |hand, or toe, or knee activation with push button, maximum 500W power, and noise |
| |level is below 40 dBA. |
|Team members: |Wayde Hager, David L. Hall, Steve Waitman |
|Sponsor Industry: |Cadet Manufacturing, Vancouver, Washington |
|Project year: |June, 1992 |
|Title of the project: |Precision Chain Grinder |
|Project description: |This project concerns the design of a precision saw chain grinder to be used in the |
| |test laboratory of Oregon Cutting Systems Division (O.C.S.D). The task of the |
| |project was to design a fully adjustable, partially automated, precision saw chain |
| |grinder that would be able to meet the requirements such as sharpening a standard 20 |
| |in loop of saw chain in 20 min. or less, sustaining cutter to cutter repeatability of|
| |+/- 2 degrees of accuracy for all three angles of concern, allowing fabrication of |
| |the design at the O.C.S.D to use existing components, and keeping the total cost of |
| |the design below $15,000. |
|Team members: |Tim Vonderohe, Kelly Jackman, Taylan Caglar, Vince Tejeda |
|Sponsor Industry: |Oregon Cutting Systems Division (O.C.S.D) |
|Project year: |June, 1991 |
|Title of the project: |Mining Vehicle Tilt Table Design |
|Project description: |The project was to design a 15x 40 ft tilt table that tips in one plane along 40 ft |
| |edge using a two-way hydraulic cylinder and journal bearings. Using structured |
| |design methodology, the team evaluated the concepts, and selected the concept. The |
| |team completed a detailed analysis of the hinge and pin connections and has provided |
| |detailed drawings for the components. Using FEA and maximum deflection technique, |
| |the project presented the platform design, calculated the required section |
| |properties, and determined the configuration of the structural members. |
|Team members: |Robert W. Cowling, Casey Dotson, Minh Nguyen, Hai Vu |
|Sponsor Industry: |Atlas Copco Wagner |
|Project year: |June, 1996 |
|Title of the project: |Design of A Telephone Answering Machine |
|Project description: |The project was to design a telephone answering machine for those individuals who are|
| |intimidated by electronic devices. The project was requested for the senior people, |
| |in age from 50 to 75, who are not yet familiar with using answering machine. The |
| |project examined the design of a telephone answering machine from lust to dust. The |
| |fact that many people dislike missing phone calls was a major factor in the project |
| |selection. Therefore, a design methodology was formulated to attack the problem. |
| |The project included problem recognition and definition, defining customer |
| |restraints, gathering and analysis of information, generating alternative solutions, |
| |and evaluating and implementing solutions. The end result is a design that is |
| |compact and user friendly. |
|Team members: |Kellie Reid |
|Sponsor Industry: |Unknown |
|Project year: |March, 1996 |
|Title of the project: |Prime Mover, Human Powered Vehicle |
|Project description: |The report is a one man project in addition to Portland State University’s 1996 HPV |
| |entry. The author designed and built his own fairing using his connections with the |
| |experts in composites and laying up fiberglass and carbon cloth. Continued from |
| |1995’s work that provided the frame design and prototype, the project focused on the |
| |fairing design report, prototype, and the testing that was required. |
|Team members: |Trent Warwick |
|Sponsor Industry: |ASME |
|Project year: |June, 1996 |
|Title of the project: |Prime Mover, Human Powered Vehicle |
|Project description: |The report is a one man project in addition to Portland State University’s 1996 HPV |
| |entry. The author designed and built his own fairing using his connections with the |
| |experts in composites and laying up fiberglass and carbon cloth. Continued from |
| |1995’s work that provided the frame design and prototype, the project focused on the |
| |fairing design report, prototype, and the testing that was required. |
|Team members: |Trent Warwick |
|Sponsor Industry: |ASME |
|Project year: |June, 1996 |
|Title of the project: |Design Submittal for Energy Resource Center for HVAC Laboratory |
|Project description: |The project proposed to build a HVAC laboratory that is not available in Portland |
| |area for educational and research purpose by students, professionals, and others who |
| |with an interest in HVAC. Used a cause and effect and affinity diagrams, the project|
| |conducted a survey of the potential customers, and compiled their needs. Using |
| |Quality Function Development (QFD) procedure, the project ranked the needs of the |
| |potential customers, and developed measurable engineering goals for the design. |
| |Using Paul’s decision matrix, the project developed concepts based on the needs of |
| |the potential customers. The final design incorporated a Variable Air Volume (VAV) |
| |Air Handler Unit (AHU) supplying a test chamber and an additional HVAC zone equipped |
| |with false heating and cooling loads. An extensive and comprehensive array of |
| |instrumentation and controls is included for analysis of psychometric relationships |
| |and energy usage. |
|Team members: |Roger Sorrentino, Dennis Conser, Dennis Vega |
|Sponsor Industry: |The Energy Resource Center (ERC) |
|Project year: |June, 1996 |
|Title of the project: |Log Boss Group |
|Project description: |The Project report describes the conceptual development of an active-sensor bandmill |
| |strain system. The system has two objectives: first, to reduce the response time of |
| |the strain system, and second, to maintain a dynamically controlled strain on the |
| |bandsaw blade during operation. The project includes study of the straining process|
| |development and evaluation of possible strain configurations, ANSYS analysis of |
| |response time, and recommendation of a strain system with integration into a |
| |commercial bandmill. The project predicted future work that would entail the |
| |building of a bandmill prototype using an active-sensor straining system, testing and|
| |performance evaluation, further modification if necessary, and finally, production of|
| |a commercial bandmill. |
|Team members: |Tim Golik, James Knope, Dan Smith, Allen Williams |
|Sponsor Industry: |Log Boss, Inc |
|Project year: |June, 1998 |
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related searches
- history and physical documentation guide
- medical student documentation and cms
- documentation guidelines for medical students
- history and physical documentation guid
- completed assessment documentation examples
- cms medical student documentation 2018
- medical student documentation guidelines 2019
- student documentation in medical records
- cms student documentation requirements
- free printable homeschool documentation forms
- employee conversation documentation template
- cms surgery documentation guidelines