OPERATION SHEET - Directory
OPERATION SHEET
|Operation Number: |O-7 |Product: |Scotch Yoke |
|Operation Name: |Plane to finish width |Worked on by: |Student name |
|Previous Station: |0-6 |Next Station: |I-2 |
|Part Name: | Base |Drawing of Major Details of Operation: |
| | |[pic] |
|Part Number: |1 | |
|Quantity: |50 | |
|Material or Stock: |¾” X 3-1/2” X 12” hard maple, | |
| |FAS, S2S1E, KD | |
|Tools/Equipment: |Planer | |
|Fixtures/Gauges: |Fixture O-7 | |
|Supplies: |Fixture | |
|Step | |Fixtures |Materials | |Tools and |
|No. |Description of Step |or Gauges |or Stock |Supplies |Equipment |
|1 |Put on safety glasses and make sure all loose| | |Safety glasses |Planer |
| |clothing and long hair is secured. | | | | |
|2 |Inspect machine for wear or visible defects. | | | | |
| |Report any problems to the instructor. | | | | |
|3 |Secure Fixture O-7 from storage. |Fixture O-7 | | | |
|4 |Secure stock from operation O-6 | |See above | | |
|5 |Place one base in the fixture with the | | | | |
| |jointed edge down and the grain going up | | | | |
| |toward the back of the fixture, use boards | | | | |
| |and the wedges to secure part firmly. | | | | |
|6 |Adjust the infeed table so the fixture and | | | | |
| |the sample base will slide through the | | | | |
| |planer. | | | | |
|7 |Open the dust vent. | | | | |
|8 |Turn on the planer let it reach maximum RPM. | | | | |
|9 |Place the fixture with the bottom resting on | | | | |
| |the infeed table near the throat opening of | | | | |
| |the planer. | | | | |
|10 |Slowly slide the fixture forward until the | | | | |
| |planer grabs the stock and feeds it through. | | | | |
| |Note: do not get fingers under the fixture or| | | | |
| |within 4” of the throat opening. | | | | |
|11 |Walk to the output table. | | | | |
|12 |Catch the fixture after it leaves the planer.| | | | |
| |Do not pull the fixture out. Remove the base | | | | |
| |from the fixture. | | | | |
|13 |Use gauge I-2 to check the width of the base.|Gauge I-2 | | | |
|14 |If needed adjust for the correct height of | | | | |
| |the planer table. | | | | |
|15 |Pick up bases at O-6 as needed. | | | | |
|16 |Place six bases in the fixture with the | | | | |
| |jointed edge down and the grain going up | | | | |
| |toward the back of the fixture. | | | | |
|17 |Place the wedges in the fixture making the | | | | |
| |bases tight in the fixture. | | | | |
|18 |Place the fixture with the bottom resting on | | | | |
| |the infeed table near the throat opening of | | | | |
| |the planer. | | | | |
|19 |Slowly slide the fixture forward until the | | | | |
| |planer grabs the stock and feeds it through. | | | | |
| |Note: do not get fingers under the fixture or| | | | |
| |within 4” of the throat opening. | | | | |
|20 |Walk to the output table. | | | | |
|21 |Catch the fixture after it leaves the planer.| | | | |
| |Do not pull the fixture out. Remove the bases| | | | |
| |from the fixture. | | | | |
|22 |Record number of parts completed on tally | | |Tally sheet, pencil| |
| |sheet | | | | |
|23 |Place the bases in a box for I-2. | | |Storage box | |
|24 |Repeat steps 15-23 until all parts are | | | | |
| |finished. | | | | |
|25 |Turn off the planer. | | | | |
|26 |Close the dust vent. | | | | |
|27 |Brush off all wood shaving from the planer. | | |Bench brush | |
|28 |Sweep and dust mop the floor. | | |Broom, dust mop | |
|29 |Inspect machine for wear or visible defects. | | | | |
| |Report any problems to the instructor. | | | | |
|30 |Return Fixture O-7 to storage | | | | |
-----------------------
Grain Direction
Throat opening
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- business analysis document home samhsa hrsa
- sample control plan methodology delta elevator
- sample procedure iso quality manual
- operation sheet directory
- practice problems chapter 4 forecasting
- team feasibility commitment
- chapter 7 joint product and by product costing
- comparison of major contract types under secretary of
- 5s manual lean manufacturing
Related searches
- back operation procedures
- installation and operation qualification
- operation qualification definition
- operation prevention parent toolkit
- order of operation in mathematics
- surgical operation vs surgical procedure
- operation qualification template
- operation functions of organizations
- most common operation in usa
- cow calf operation business plan
- cattle operation business plan
- vaginal operation video