Lecture 04: Design Structure Matrix (DSM) - MIT OpenCourseWare
ESD.36J System & Project Management
Lecture 4
+
- Design Structure Matrix
Instructor(s)
Prof. Olivier de Weck
+
Reminder
-
Term Project Proposals are due today !
- ESD.36 SPM
2
+
Today's Topic
-
DSM Introduction Project Graphs --> Task-based DSMs DSM Operations
sequencing partitioning Tearing
DSM Example
Humanitarian Logistics Project
DSM Tools and References
- ESD.36 SPM
3
+
- Lessons Learned from CPM
+
Focuses attention on a subset of critical tasks Determine effect of shortening/lengthening tasks Links task durations to schedule
-
Doesn't capture task iterations, in fact ... Prohibits iterations = called "cycle error"
However, iterations are one of the essential features of design and development projects
- ESD.36 SPM
4
+
PERT and CPM Charts
-
4
2
8
Start
3
4
Finish
Simple network diagrams are easy to understand.
We cannot represent the coupled/iterative task relationships.
- ESD.36 SPM
6
5
prohibited
days activity and duration activity precedence critical path
5
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- morphological chart cornell university
- organization management in workday datasheet
- information management according to bs en iso 19650 uk bim framework
- compensation discussion and analysis template deloitte
- job family matrix harvard university
- communications management plan template university of wisconsin
- project complexity matrix
- typ e s o f o rg a n i z a t i o n a l s t ru c t u re s
- design your governance model to make the matrix work kates kesler
- lecture 04 design structure matrix dsm mit opencourseware