MONTGOMERY COLLEGE Germantown Campus Utilities Master Plan Update Final ...

MONTGOMERY COLLEGE Germantown Campus

Utilities Master Plan Update Final Report

Wiley|Wilson Commission #211130.02 February 13, 2013

MONTGOMERY COLLEGE Germantown Campus

Utilities Master Plan Update Final Report

Wiley|Wilson Commission #211130.02 February 13, 2013

Contact: S. M. (Steve) Terry, P.E., LEED AP Project Manager 434.455.3206 .direct 434.947.1613 .fax sterry@

TABLE OF CONTENTS

Tab

EXECUTIVE SUMMARY ............................................................................................................1 DOMESTIC/FIRE WATER SYSTEM...........................................................................................2 SANITARY SEWER SYSTEM ....................................................................................................3 STORM DRAINAGE SYSTEM....................................................................................................4 MECHANICAL SYSTEMS...........................................................................................................5 ELECTRICAL SYSTEMS............................................................................................................6

APPENDIX

Utility Summary and Combined Utility Maps.............................................................. A

Table 1-1 Utility Summary - Existing Facilities Data Table 1-2 Utility Summary - Future Facilities Data List of Abbreviations C-1 Utilities Site Plan ? Existing Conditions

Domestic Water, Stormwater and Sanitary Sewer ..................................................... B

Table 2-1A Domestic Water ? Existing Conditions Table 2-1B Fire Water ? Existing Conditions Table 3-1 Sanitary Sewer ?Existing Conditions Table 2-2A Domestic Water ? Future Conditions Table 2-2B Fire Water ? Future Conditions Table 3-2 Sanitary Sewer ?Future Conditions

C-2 Water System Site Plan - Existing Conditions C-3 Water System Site Plan - Future Conditions C-4 Sanitary System Site Plan - Existing Conditions C-5 Sanitary System Site Plan - Future Conditions C-6 Storm System Site Plan - Existing Conditions C-7 Storm System Site Plan - Future Conditions

TOC-1

Montgomery College Germantown Campus Utilities Master Plan Update Comm. No. 211130.02

................
................