Product Development Project Plan Template - Parcus Group
ID
Task Name
1
Phase 1
2
Scoping Workshop
3
Concept Development
4
Market Analysis
5
Idea Generation & Idea Screening
6
High Level Project Plan
7
Milestone 1
8
Phase 2 - Business Case
9
Develop business case
10
Approval for business case
11
Milestone 2
12
Phase 3 ? Product Requirements Document (PRD)
13
Project Planning & Project Management
14
Milestone 3.1
15
Product Requirements Document (PRD)
16
Purpose, scope & stakeholders
17
Project Overview
18
Product functional requirements
19
Ordering / provisioning
20
Change management
21
Support requirements
22
Billing model & process
23
Reporting
24
Legal & regulatory
25
Project Impacts
26
Product pricing & quoting model
27
Service Activation SLA
28
Service Assurance SLA
29
Training
30
Resource requirements
31
Milestone 3.2
32
Phase 4 - Solution Design & Planning
33
Technical & Network Systems Solution Definition & Design
34
Accreditation Phase
35
Product Engineering Research and Testing
36
Demo Order Equipment
37
Equipment arrive
38
Architecture Design
39
Detailed Design
40
Detailed network & solution design
41
Business systems design
42
Network/Systems Detailed Design
43
Milestone 4.1
44
Business Systems Solution Definition & Design
45
BSS Sales / Quoting
46
BSS Ordering
47
BSS Implementation / Activation
48
BSS Support / Assurance
49
BSS Billing
50
Milestone 4.2
51
Product description & feature matrix
52
Contextual product description
53
Product features matrix development
54
Milestone 4.3
Project: Tool 00X - Service Creation P Date: Mon 21/10/13
Task Split
Progress Milestone
Duration
11 days 2 days 2 days 2 days 2 days 2 days 1 day
15 days 5 days
10 days 1 day
111 days 110 days
1 day 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days
1 day 38 days 20 days 15 days 15 days
5 days 5 days 10 days 10 days 10 days 10 days 10 days 1 day 10 days 10 days 10 days 10 days 10 days 10 days 1 day 5 days 5 days 5 days 1 day
Start
Mon 28/10/13 Mon 28/10/13 Wed 30/10/13
Fri 1/11/13 Tue 5/11/13 Thu 7/11/13 Mon 11/11/13 Tue 12/11/13 Tue 12/11/13 Tue 19/11/13 Tue 19/11/13 Mon 11/11/13 Mon 11/11/13 Mon 14/04/14 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 20/11/13 Wed 27/11/13 Thu 28/11/13 Thu 28/11/13 Thu 28/11/13 Thu 28/11/13 Thu 28/11/13 Thu 28/11/13 Thu 28/11/13 Thu 12/12/13 Thu 12/12/13 Thu 12/12/13 Thu 12/12/13 Thu 26/12/13 Fri 27/12/13 Fri 27/12/13 Fri 27/12/13 Fri 27/12/13 Fri 27/12/13 Fri 27/12/13 Fri 10/01/14 Mon 13/01/14 Mon 13/01/14 Mon 13/01/14 Mon 20/01/14
Finish
% Complete Predecessors November 2013
December 2013
January 2014
February 2014
March 2014
April 2014
252831 3 6 9 1215 182124 2730 3 6 9 1215 182124 2730 2 5 8 1114172023 2629 1 4 7 10131619222528 3 6 9 1215 1821242730 2 5 8 1114 17
Mon 11/11/13
0%
Tue 29/10/13
0%
Thu 31/10/13
0% 2
Mon 4/11/13
0% 3
Wed 6/11/13
0% 4
Fri 8/11/13
0% 5
Mon 11/11/13
0% 6
Mon 2/12/13
0%
Mon 18/11/13
0% 7
Mon 2/12/13
0% 9
Tue 19/11/13
0% 9
Mon 14/04/14
0%
Fri 11/04/14
0% 6
Mon 14/04/14
0% 13
Tue 26/11/13
0%
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Tue 26/11/13
0% 11
Wed 27/11/13
0% 30
Mon 20/01/14
0%
Wed 25/12/13
0%
Wed 18/12/13
0%
Wed 18/12/13
0% 31
Wed 4/12/13
0% 31
Wed 4/12/13
0% 31
Wed 11/12/13
0% 31
Wed 25/12/13
0%
Wed 25/12/13
0% 38
Wed 25/12/13
0% 38
Wed 25/12/13
0% 38
Thu 26/12/13
0% 42
Thu 9/01/14
0%
Thu 9/01/14
0% 43
Thu 9/01/14
0% 43
Thu 9/01/14
0% 43
Thu 9/01/14
0% 43
Thu 9/01/14
0% 43
Fri 10/01/14
0% 49
Fri 17/01/14
0%
Fri 17/01/14
0% 50
Fri 17/01/14
0% 50
Mon 20/01/14
0% 53
Summary Project Summary
External Tasks External Milestone
Deadline
Page 1
ID
Task Name
55
Phase 5 - Development/Build & Operational Readiness
56
Technical Solution Build
57
System build & implementation
58
Equipment Installations
59
Systems and Portal connections
60
Technical Training
61
Systems Documentation
62
Technical & network processes for service activations incl portal setup
63
Technical & network processes for service support
64
Solution testing
65
Finalise Technical documentation
66
Operations Rollout
67
NOC Training doc & process
68
Review doumentation (multiple reviews)
69
NOC Training Sessions (multiple sessions)
70
Integration time & beta testing
71
Technical Test with a Customer
72
Commercial Solution Build
73
Final product description/definition
74
Product documentation - ALL
75
Process Solution Build
76
Finalised Business Process Solution
77
Sales / Quoting process
78
Service Activation / Implementation process incl Planning
79
Service Support / Assurance process
80
Billing & Collections process
81
Milestone 5.1 (PROVISIONAL BETA AVAIL DATE)
82
Operational Readiness Test Plan
83
Project planning for Ops Readiness
84
Develop technical readiness plan incl technical processes
85
Develop product/commercial readiness plan
86
Develop operations and business processes readiness plan
87
Operational Readiness Test Execution
88
Finalized product/marketing documents & sales training materials
89
Vendor support agreements/process finalised
90
Technical documents ready
91
Testing completed
92
Finalised training
93
Service activation ready incl. ordering process, planning & design
94
Service assurance ready incl. NOC support process
95
ORT Conducted & results noted
96
Sales & Market Readiness
97
Milestone 5.2
98
LAUNCH BUFFER TIME
99
Phase 6 - Launch
100
Commercial Launch
101
All product collateral published
102
Sales training
103
Pricing published
104
Milestone 3.2 - COMMERCIAL LAUNCH
105
Phase 7 - Project Review & Lessons Learned
106
Project Review & Lessons Learned
107
Milestone 3.2
Project: Tool 00X - Service Creation P Date: Mon 21/10/13
Task Split
Progress Milestone
Duration
58 days 43 days 27 days
2 days 5 days 3 days 5 days 5 days 5 days 5 days 5 days 16 days 3 days 3 days 3 days 5 days 5 days 10 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 1 day 3 days 3 days 3 days 3 days 3 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 1 day 5 days 13 days 13 days 5 days 10 days 2 days 1 day 2 days 1 day 1 day
Start
Tue 21/01/14 Tue 21/01/14 Tue 21/01/14 Tue 21/01/14 Thu 23/01/14 Wed 29/01/14 Thu 30/01/14
Thu 6/02/14 Thu 6/02/14 Thu 13/02/14 Thu 20/02/14 Thu 27/02/14 Thu 27/02/14 Tue 4/03/14 Tue 4/03/14
Fri 7/03/14 Fri 14/03/14 Fri 28/03/14 Fri 28/03/14
Fri 4/04/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14
Thu 6/03/14 Fri 7/03/14 Fri 7/03/14 Fri 7/03/14 Fri 7/03/14 Fri 7/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 12/03/14 Wed 19/03/14 Thu 20/03/14 Thu 20/03/14 Thu 20/03/14 Thu 20/03/14 Thu 20/03/14 Thu 3/04/14 Mon 7/04/14 Tue 8/04/14 Tue 8/04/14 Wed 9/04/14
Finish
% Complete Predecessors November 2013
December 2013
January 2014
February 2014
March 2014
April 2014
252831 3 6 9 1215 182124 2730 3 6 9 1215 182124 2730 2 5 8 1114172023 2629 1 4 7 10131619222528 3 6 9 1215 1821242730 2 5 8 1114 17
Thu 10/04/14
0%
Thu 20/03/14
0%
Wed 26/02/14
0%
Wed 22/01/14
0% 54
Wed 29/01/14
0% 58
Fri 31/01/14
0%
Wed 5/02/14
0% 59
Wed 12/02/14
0% 61
Wed 12/02/14
0% 61
Wed 19/02/14
0% 63
Wed 26/02/14
0% 64
Thu 20/03/14
0%
Mon 3/03/14
0% 65
Thu 6/03/14
0% 67
Thu 6/03/14
0% 67
Thu 13/03/14
0% 69
Thu 20/03/14
0% 70
Thu 10/04/14
0%
Thu 3/04/14
0% 71
Thu 10/04/14
0% 73
Wed 5/03/14
0%
Wed 5/03/14
0% 65
Wed 5/03/14
0% 65
Wed 5/03/14
0% 65
Wed 5/03/14
0% 65
Wed 5/03/14
0% 65
Thu 6/03/14
0% 80
Tue 11/03/14
0%
Tue 11/03/14
0% 81
Tue 11/03/14
0% 81
Tue 11/03/14
0% 81
Tue 11/03/14
0% 81
Tue 18/03/14
0%
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Tue 18/03/14
0% 86
Wed 19/03/14
0% 96
Wed 26/03/14
0% 97
Mon 7/04/14
0%
Mon 7/04/14
0%
Wed 26/03/14
0% 97
Wed 2/04/14
0% 97
Fri 4/04/14
0% 102
Mon 7/04/14
0% 103
Wed 9/04/14
0%
Tue 8/04/14
0% 104
Wed 9/04/14
0% 106
Summary Project Summary
External Tasks External Milestone Page 2
Deadline
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- assessing new product development practices and
- new product development pipeline management cepac
- guide to preparing a learning and development strategy final
- marketing strategy template
- a practical guide to supplier development process
- chapter 8 new product development
- strategies for new product development
- product development 01 new product development
- product development project plan template parcus group
- new product development proposal
Related searches
- software development project plan template
- software development project plan example
- free project plan template word
- basic project plan template excel
- free project plan template excel
- simple project plan template free
- product development project plan template
- new product development project plan
- free project plan template download
- simple project plan template word
- simple project plan template excel
- excel project plan template free