Documents & Reports - All Documents | The World Bank



KADUNA STATE MINISTRY OF

WORKS AND TRANSPORT

RURAL ACCESS AND MOBILITY PROJECT

FINAL REPORT

ENVIRONMENTAL MANAGEMENT PLAN FOR THE CONSTRUCTION OF BRIDGES, CULVERTS AND OTHER RIVER CROSSING IN

KADUNA STATE.

1. PREPARED BY;

DR. BABA AUSTIN HYUWA

NO. L16, LINK ROAD, UNGWAN TELEVISION,

OPP. VINE FILLING STATION,

KADUNA.

P. O. BOX 9622,

TEL: 08035896968; 08022322291

Email: midlandsconsult@

TABLE OF CONTENTS

Tables of Contents --- --- --- --- --- --- --- --- --- (ii-v)

List of Tables --- --- --- --- --- --- --- --- --- --- (vi)

Abbreviations --- --- --- --- --- --- --- --- --- --- (vii)

Executive Summary --- --- --- --- --- --- --- --- --- (viii-xvi)

SECTION ONE

1.0 Introduction --- --- --- --- --- --- --- --- --- 1

1.1 Context --- --- --- --- --- --- --- --- --- --- 2

1.2 Environmental Requirement and Legal Frameworks --- --- --- --- 2

1.3 Goals and Objectives of EIA --- --- --- --- --- --- --- 2-3

1.4 Terms of Reference and Scope --- --- --- --- --- --- --- 3-4

1.5 Purpose of this Report --- --- --- --- --- --- --- --- 4

1.6 Methodology for the Preparation of this Report --- --- --- --- --- 4-5

1.7 Organization of this Report --- --- --- --- --- --- --- 6

SECTION TWO

2.0 Existing Legal and Administrative Frameworks--- --- --- --- --- 7

2.1 National Legal and Administrative Instruments--- --- --- --- --- 7

2.1.1 Federal Ministry of Environment --- --- --- --- --- --- 7-11

2.1.2 Forestry Law Cap 55, 1994 --- --- --- --- --- --- --- 12

2.1.3 Land Use Act 1978 --- --- --- --- --- --- --- --- 12

2.2 State Ministries/Environmental Protection Agencies --- --- --- --- 12-13

2.3 International Legal and Administrative Instruments --- --- --- --- 13

2.3.1 The Bank’s Safeguard Policies --- --- --- --- --- --- --- 13-115

2.4 National and State Legislative Framework for Transport --- --- --- --- 15-17

SECTION THREE

3.0 Introduction --- --- --- --- --- --- --- --- --- 18

3.1 The Project --- --- --- --- --- --- --- --- --- 18

3.2 Nature and Distribution --- --- --- --- --- --- --- --- 18-22

3.3 The Need and Importance of the Project --- --- --- --- --- --- 23

3.4 Project Operation, Maintenance and Sustainability --- --- --- --- 23

SECTION FOUR

4.0 Description of Baseline Environment Condition --- --- --- --- 24

4.1 Locations of Proposed Project--- --- --- --- --- --- --- 24-26

SECTION FIVE

5.0 Introduction --- --- --- --- --- --- --- --- --- 27

5.1 Overview of Project Impacts--- --- --- --- --- --- --- 27-35

5.3 Environmental and Social Mitigation – Principles and Clauses --- --- 36

SECTION SIX

6.0 Environmental Monitoring Plan --- --- --- --- --- --- 37

6.1 Introduction --- --- --- --- --- --- --- --- --- 37

6.2 Monitoring Procedure --- --- --- --- --- --- --- --- 37-50

6.4 Site Environmental Audit--- --- --- --- --- --- --- --- 51

6.5 EMP Organization --- --- --- --- --- --- --- --- 52-56

6.6 Capacity Development and Training- --- --- --- --- --- --- 56

6.7 Non Compliance of the EMP --- --- --- --- --- --- --- 56-58

6.8 Environmental Emergency Procedures --- --- --- --- --- 57-58

6.9 Environmental Complaints --- --- --- --- --- --- --- 58

APPENDIX

REFERENCE --- ---- ---- ---- --- --- --- --- --- --- 108

LIST OF TABLES

1. Table 3.1 – Distribution of Crossing Structures by Local Government Areas 19

2. Table 3.2 – Ecological Distribution of the 20 LGAs and Project Sites in the State 20-22

2. Table 5.1 – List of Identified Impacts with Corresponding Mitigation Measures

for the Project 28-34

3. Table 5.2 – River Crossing with Special Problems 35

4. Table 6.1 – Summary of Implementation of Phase Mitigation Measures –

Design & Construction 38-44

5. Table 6.2 – Project Site Activity Monitoring and Frequency during Construction 45-48

6. Table 6.3 – Environmental Monitoring Criteria 49-50

APPENDIX 1.1

List of Prioritized River Crossings – Structures Sizes and Contract Lots--- --- --- 59-66

APPENDIX 2.1

Category I Project --- --- --- --- --- --- --- --- --- 67-68

APPENDIX 5.1

Environmental and Social Clauses --- --- --- --- --- --- --- 69-80

APPENDIX 5.2

Contractor’s Checklist on Environmental and Social Issues- --- --- --- --- 81-88

APPENDIX 6 A

Environmental Complaint Log --- --- --- --- --- --- --- --- 89-90

APPENDIX 6 B

Environmental Complaint Record Form --- --- --- --- --- --- --- 91-92

APPENDIX 6 C

Compliant Response Procedures --- --- --- --- --- --- --- 93-94

APPENDIX 6 D

Field Data Record Sheet for TSP Monitoring -- --- --- --- --- --- 95-96

APPENDIX 6 E

Field Data Record Sheet for Water Quality Monitoring --- --- --- --- 97-98

APPENDIX 6 F

Field Data Record Sheet for Noise Monitoring --- --- --- --- --- --- 99-100

APPENDIX 6 G

Corrective and Preventive Action Request Form --- --- --- --- --- 101-102

APPENDIX 6 H

Environmental Site Inspection Report --- --- --- --- --- --- 103-105

APPENDIX 6 I

Interim Notification of Environmental Quality Limit Exceedances Report Sheet --- 106-107

REFERENCE --- ---- ---- ---- --- --- --- --- --- --- 108

ABBREVIATIONS

RAMP - Rural Accessibility and Mobility Project

SPIU - State Project Implementation Unit

PC - Project Coordinator

EMP - Environmental Management Plan

CCEMP - Crossings Construction Environmental Management Plan

EIA - Environmental Impact Assessment

EA - Environmental Assessment

EPB - Environmental Project Brief

NPS - National Park Service

WB - World Bank

NESREA - National Environmental Standard and Regulation Enforcement Agency

NOSDRA - National Oil Spill Detection and Remediation Agency

EIS - Environment Impact Statement

EMS - Environmental Management Systems

FEPA - Federal Environmental Protection Authority

FMEnv - Federal Ministry of Environment

KEPA - Kaduna State Environmental Protection Authority

MENR - Ministry of Environment and Natural Resource

BDC - Baseline Data Collection

NPE - National Policy on the Environment

EXECUTIVE SUMMARY

Introduction

Kaduna State is one of the beneficiaries of the World Bank Assisted Rural Access and Mobility Project (RAMP). The project coordination, in the State, is by the State Project Coordinating Unit (SPIU) which is under the State Ministry of Works and Transport. The aim of this project is to improve accessibility and enhance mobility in a sustainable manner in the rural areas of the State with a view to, improving the quality of life of the rural population. In the effort to achieve the main objectives of this project, the SPIU has undertaken techno-economic studies for the detailed designs for the rehabilitation, construction and maintenance of 132 drainage crossing structures namely, bridges, culverts and other crossings, in the State.

Existing Policy, Legal and Administrative Frameworks

Environmental Impact Assessment Act No. 86 of 1992 gives specific powers to the Federal Ministry of Environment to mandate an EIA on development projects of this nature, whether private or public sector.

The World Bank’s Operational Policies (OP) includes guidance on Environmental Assessment requirements. The Bank’s Safeguard Policies, ten of them, is meant to ensure that operations of the Bank and her borrowers do not lead to adverse impacts or cause any harm.

These were considered in the development of the EMP

The Project

The project involves the identification of river crossings for reinstatement, construction, repairs of damaged, washed away, and or missing river crossings in rural areas of Kaduna State. The emphasis is on the provision of river crossings along rural roads in the State.

The construction of these structures is expected to bring about the solution to the problem of rural inaccessibility in the State, on the one hand. On the other hand, in the course of construction, especially and operation some negative environmental (adverse) impacts could result.

It is in the light of this that Environmental Management Plan was designed by the SPIU for the proposed project. This Environmental management plan (EMP) consists of the set of mitigation, monitoring, and institutional measures to be taken during construction of the river crossings and operation with a view to eliminating any adverse environmental and social impacts, offset them, or reduce them to acceptable levels. The plan also includes the actions needed to implement these measures.

Potential Impacts and Mitigation

Table A below outlines the potential impacts identified and the corresponding mitigation measures that should reduce potentially significant adverse environmental impacts to acceptable levels.  

|Table A: List of identified impacts with corresponding mitigation measures for the project |

|No |Activity |Potential Negative Impacts |Mitigation Measures |

|A. MOBILISATION |

|1 |Movement of goods, |Reduction in air quality due to |Employ fuel efficient and well maintained haulage trucks with proper exhaust system to minimize emissions. |

| |equipment, etc, to site |vehicular emissions |All parked vehicles on the site shall have their engines turned off; |

| | | |Service vehicles as at when due and stick to manufacturers’ specifications in use |

| | | |Develop and follow a controlled fueling, maintenance and servicing protocol |

| | |Increase in noise nuisance |Raise community awareness of unusual activity |

| | | |Plan activities such that Regulatory limits are not exceeded |

| | |Movement of heavy equipment to |Avoid hauling of materials particularly on market days of the project communities |

| | |worksite which may pose danger to|Place visible warning signs on roads and vehicles |

| | |public/wildlife |Driving course for the drivers shall be ensured. |

| | | |Large and slow moving vehicles shall be scheduled during off-peak periods |

| | | |Raise community awareness of unusual activity |

| | | |Schedule compulsory medical fitness test for all drivers. |

| | | |Ensure construction vehicles enter and leave the site at controlled points only |

| | | |Use workers to direct vehicles and pedestrians to prevent accidents while vehicles are moving in and out of the site. |

| | |Vibration from plant/equipment |As necessary, construction barriers shall be erected for safety and to direct pedestrian traffic safely around the construction |

| | | |site. |

| | | |Fix noise abating gear mufflers to plant/equipment. |

|B. SITE PREPARATION |

|1. |Site Clearing and |Loss of Vegetation Wildlife |Minimize the extent and intensity of destruction. |

| |preparation |habitat, Flora and Fauna |Change the alignment of the proposed crossings where necessary. |

| | | |Avoid and protect destruction of exortic plants and wildlife where the exist. |

| | | |Avoid cultural sites and shines where they exist. |

|2. | |Dust emission |Enclose all material stock piles. |

| | | |Use water spray to dampen the dust. |

| | | |Use dust extractors such as in concrete plants. |

| | | |Covering of trucks and other vehicles where transporting laterite, spoil materials or any other material that generate dust on |

| | | |transits. |

| | | |Regular spraying of construction site and loading/off loading any loose materials that generate dust. |

| | |Emissions from operating plants |Engage well maintained and efficient fuel leakage trucks in line with recommended standards by manufactures. |

| | |and vehicular exhausts |Develop and follow a controlled and fueling, maintenance and servicing protocol. |

| | | |Service vehicles as and when due as stipulated by the manufactures. |

| | | |Turn off vehicles while parked. |

| | |Water contamination from site |Maintain proper housekeeping. |

| | |cleaning materials, oils and soil|Site storage tanks for fuels and oils on in previous bases with bund walls. |

| | |spoils |Place pumps on drip trays. |

| | | |Adequate sanitary facilities for employees. |

| | | |Careful plant maintenance to avoid spillages and blow outs. |

| | | |Make adequate provision for proper drainage system within the site. |

| | | |Minimize built up of silt, and spoils in river water course. |

| | | |Vehicle washing at locations and in manner that surface water is not contaminated. |

| | |Destruction of visual scenery |Screen off site during site clearing. |

| | | |Careful design and placement of ground level components. |

| | | |Screening by vegetation planting. |

| | |Accidents involving people and |Provide proper warning signs for people and animals. |

| | |animals |Remove all likely obstructions to traffic flow. |

| | | |Remove objects that may obstruct view. |

|C. CONSTRUCTION PHASE: |

|1 |Vegetation clearance |Enhance soil erosion and |Revegetate surroundings after construction. |

| | |topographic changes. |Protect exotic plants and animals where they exist. |

| | | |Protect slopes against erosion. |

|2 |Noise/ |noise level increases during |Raise community awareness of unusual activity. |

| |Vibration |construction operation |Plan activities such that Regulatory limits are not be exceeded. |

| | |ground vibration due to |Ensure powered mechanical equipment and machinery filtered with noise abating gear such as mufflers for effective sound reducing, in|

| | |construction operations |compliance with the national regulations. |

| | | |As far as possible, the operation of heavy equipment shall be conducted in day light hour. |

| | | |Construction equipment which generates excessive noise/vibration shall be isolated. |

| | | |Well maintained haulage trunks will be used with speed control. |

|3 |Air Quality and Dust |Air borne emission released to |Plant and equipment using fuel that may produce high levels of air pollutants shall be avoided; |

| | |the atmosphere due to |Fuel efficient and well maintained haulage trucks with proper exhaust baffles shall be employed to minimize exhaust emissions. |

| | |Construction-related air |Stockpiled soil and sand shall be slightly wetted before loading, particularly in windy dry conditions. |

| | |pollution |Stockpiles of sand and aggregate greater than 20 m3 in volume shall be enclosed in walls extending above the pile and beyond its |

| | |Plant operations, Material dump |front face. |

| | |sites , Vehicular emissions and |Weigh hoppers shall be vented to a suitable filter. |

| | |Haulage of materials |All vehicles, while parked on the site shall have their engines turned off. |

| | | |Using efficient equipment, machinery and vehicles with regular checking to effect necessary corrections or repairs to ensure |

| | | |compliance with safety and air pollution requirements. |

| | | |Soil, sand and other construction materials in storage and in transit shall be covered. |

| | | |Effective water sprays shall be used during the delivery and handling of all sand and aggregate and other similar material when dust|

| | | |is likely to be created and to dampen them during dry, windy weather. |

| | | |Spraying of bore areas and roads used for haulage of material with water. |

| | | |Washing of tires and lower body of vehicles when moving out from the construction site. |

| | | |Selection of sites for material extraction away from residential areas to reduce impact of dust. |

| | |Emission from plants/equipment |Vehicles/plans should be properly serviced periodically, to minimize emission of gaseous contaminants. |

| | |exhaust pipes | |

|4 |Surface Erosion/Surface |Run-off during construction |Design temporary and permanent drainage systems to minimize soil erosion. |

| |run-off |operations; |Develop and implement storm water control measures during construction. |

| | |Carry over of eroded soil |Implement an erosion and sediment control plan as part of the construction project. |

| | |particles by surface run-off |Back-fill shall be compacted properly in accordance with design standards. |

| | | |Install temporary or permanent drainage works to protect all areas susceptible to erosion, flood damage and silt |

| | | |transport/sedimentation. |

| | | |Measures shall be taken to prevent ponding of surface water and scouring of slopes. |

| | | |Newly eroded channels shall be backfilled and restores to natural contours. |

| | | |Deploy silt fences to avoid/reduce soil erosion and run-off. |

|5 |Water Quality |Water quality caused by |Divert the water and waste products arising from the site via a suitably designed temporary drainage system in a manner that will |

| |Deterioration / |construction activities affects |not cause pollution problems or other nuisance. |

| |Water Resource |the streams/rivers. |Proper disposal of solid waste from construction activities and labour camps. |

| |Protection | |Ensure storage of lubricants, fuels and other hydrocarbons in self contained enclosures. |

| | | |Vehicles and equipment shall be maintained in good condition, ensuring no leakage of oil or fuel. |

| | | |Servicing of vehicles, machinery and equipment at properly managed and equipped workshops where waste oil is collected and disposed |

| | | |off at approved locations. |

| | | |Providing sanitation arrangements at work sites and temporary accommodation facilities to avoid release of waste water and sewage to|

| | | |the environment. |

| | | |Protect groundwater by use of grouts and diaphragm walls where necessary. |

|6 |Handling and Storage of |Contamination of the immediate |Safe ventilation for storage of volatile chemicals shall be provided. |

| |Hazardous Materials |surroundings. |Access to areas containing hazardous substances shall be restricted and controlled. |

| | | |Hydrocarbon and hazardous materials shall be stored on impervious ground under cover; the area shall be constructed as spill tray to|

| | | |avoid spread of accidental spills. |

| | | |All hot mix plant, crushing plant, workshops, depots and temporary workers accommodation facilities shall be sited in approved |

| | | |locations. |

|7 |General Waste |Generation of spoil and |All other wastes generated including environmentally deleterious materials generated by construction activities will be disposed |

| | |construction waste; |offsite in an appropriate, legal, and safe manner. |

| | |Unsafe and improper disposal of |The overall goal will be to minimize as much as practical the generation of all wastes |

| | |spoil and construction waste. |Unsuitable excavated materials shall be systematically carried out away from areas prone to erosion. |

| | |Soil contamination |Reuse waste materials wherever possible and use designated disposal sites. |

| | |Water contamination |Used oil and lubricants shall be recovered and reused or removed from the site in full compliance with the FMEnv and KEPA |

| | |Injury to personnel |regulations. |

| | | |Oil wastes, debris and/or other waste materials must not be burned. |

| | | |Optimize the reuse of spoil and construction waste. |

| | | |All the construction camps and facilities shall be dismantled and removed from the site, unless otherwise desired by the local |

| | | |community. |

| | | |Restore the site to a condition in no way inferior to the condition prior to the commencement of work. |

| | | |Cover soak pits and septic tanks and effectively seal them off. |

| | | |Follow safety measures while disposing wastes. |

| | | |Avoid introduction of foreign soil and synthetic materials. |

|8 |Plants and animal life |Disturbance of plants and animal |Change alignment of crossings where necessary to minimize extent and intensity of disturbance/destruction especially of endemic |

| | |community habitats |Wildlife and Exotic plants where they exist. |

|9 |Land degradation |Creation of Excavation sites and |Rehabilitate Excavation sites by filling. |

| | |triggering erosion |Plant trees, and shrubs to check erosion. |

| | | |Develop embankment on steep slopes to protect them from erosion. |

| | | |Stone pitch to protect slopes where necessary |

|10 |New Settlements |Attraction of new settlers near |Discourage new settlements close to the stream (river crossing). |

| |Development |the crossing which will lead to |Create forest/bush reserves around the crossing area to preserve fauna and flora. |

| | |destruction of vegetation | |

| | |wildlife and increased traffic | |

|11 |Visual Impact |Destruction of visual scenery |As much as possible keep plants and equipment off the crossing and its immediate vicinity. |

| | | |Areas opened up by clearing vegetation to pave way for the crossing construction should be replanted after construction. |

| | | |Ugly scars left around the crossing site through clearance for construction should be leveled and landscaped. |

| | | |New structures such as signboards, bill boards for the project should be removed after construction. Those required such as |

| | | |direction or warning signs should be properly placed. |

|12 |Accessibility |Risk of accidents |Ensure the traffic (vehicular) does not exceed the capacity of the river crossing by placing restrictions on type/weight of |

| | | |vehicles. |

| | | |Place signs and speed limits or zebra crossing/bumps. |

|13 |Influx or new settlers, |Risk of spread of diseases |Create public enlightenment and awareness on crime and STDs such as HIV/AIDs. |

| |workers, and traders | |Contractors staff. |

| | | |Provision of health care facilities. |

|14 | |Land take |Minimize land take through realignment or relocation of affected crossing. |

| | | |Engage land swaps. |

| | | |Improve access to alternative land. |

| | | |Choosing route locations away from built-up areas and restricting the extent of road works to avoid interference with existing |

| | | |activities. |

| | | |Adoption of a reduced speed design, reduced right-of-way land requirements, or design changes (underground drainage, for instance) |

| | | |to reduce impacts on properties and acitivites. |

| | | |Alternative considerations in route selection. |

| | | |Integration of mitigation measures in road designs, where appropriate. |

| | | |Compensation rates for owners of the land, properties, etc that reflect current market realities. |

|D. PROJECT OPERATION |

|1. |Vehicular movement |Air contamination from vehicular |Speed limits to be imposed. |

| | |exhausts. |Road worthiness and traffic control regulations to be enforced. |

| | |Dust arising vehicle tyre/road |Proper warning signs to be properly placed. |

| | |surface contact. | |

| | |Risk of accidents | |

| | |(human/animals). | |

|2. |Improved accessibility |Immigration towards project site |Provide for influx of people. |

| | |and risk of conflict. |Increase communities facilities to accommodate new comers. |

| | | |Encourage community integration. |

Monitoring

In this Section of the EMP, specific description, and technical details, of monitoring measures, including the parameters to be measured, methods to be used, etc are given as shown in Tables B and C.

Table B: Project Site Activity Monitoring and Frequency during Construction

|Activity |Mitigation Measure Implementation |Monitoring Activity |Frequency |Monitoring Responsibility |Budget |

| | | | | |(N) |

|Obtain required Govt. |Submit EIA/ EMP to FMEnv/KEPA |Retain copy of approval |Once |Contractor/ER |N500,000.00 |

|Approvals | | | | | |

|Erection of contractor |Contractor to identify suitable camp site |Retain a record of discussions |After each discussion |Contractor/ER/ET |N150,000/monitoring site visit|

|construction camp |in consultation with local | | | | |

| |community/local government |Retain a record of approval | | | |

| |Contractor obtain approval for camp site | |Once | | |

| |from KASUPDA/Local government | | | | |

|Community consultation |Continue to undertake community |Retain copies of minutes of discussions |After each discussion |Contractor/ER/ET |N150,000.00/visit site |

| |consultation | | | | |

|Materials testing |to include requirement for independent |Retain copy of contracting documents with the |Once |Contractor/ER/ET |N300,000.00/sample |

| |materials testing in contracting documents|requirement |Weekly when materials are | | |

| |to ensure that Contractor complies with |Check record of materials testing |delivered | | |

| |requirements | | | | |

|Operation of Contractor |Inclusion of requirement for regular |Retain copy of contracting documents with the |Once |Contractor/ER |N150,000.00/monitoring site |

|construction camp |watering of camp site and construction |requirement | | |visit |

| |sites in contracting documents | | | | |

| |Contractor to implement approved |Maintain record of implementation activities | | | |

| |Contractor work plan |Daily monitoring |Daily during dry weather | | |

| |submit monthly reports on Contractor |Ensure all complaints are recorded in the |condition | | |

| |implementation of approved work plan and |register | | | |

| |mitigation measures |Maintain a record of working hours |Daily | | |

| |Establish and maintain public complaints |Maintain a record of discussions with local | | | |

| |register |community in relation to requests for | | | |

| |Include the following requirements for |extension of working hours |As required | | |

| |worker facilities in contracting documents|Maintain a record of any agreements for | | | |

| |Adequate numbers of functional bathrooms |extension of working hour | | | |

| |and latrines |Retain copies of contracting documents with |As required | | |

| |Covered rubbish bins for scraps |requirement | | | |

| |Adequately stocked first aid medical kits |Retain copies of contracting documents with |As required |Contractor/ER | |

| |Trained person to provide first aid |requirement | | | |

| |assistance if required |Retain copies of waste disposal dockets | | | |

| |include requirement in contracting |Maintain a photographic record of disposal | | | |

| |documents for Contractor to provide |activities | | | |

| |facilities for disposal of solid and | | | | |

| |liquid wastes |Maintain documentary record of monitoring | | | |

| |Contractor to undertake regular disposal |activities | | | |

| |of solid and liquid wastes | | | | |

| |undertake frequent regular monitoring to | | | | |

| |ensure compliance with requirements | | | | |

|Heavy machinery operation |Ensure contracting documents include |Retain copy of contracting documents on |Once | |N141,375.13/hr |

| |specifications relating to type, weight |project files | | | |

| |and operation of heavy machinery |Include reference in acceptance advice | | | |

| |ensure that acceptance of CCMP includes |Maintain record of inspections and public |Once | | |

| |consideration of heavy machinery operation|complaints | | | |

| |Contractor to operate machinery in | |Weekly | | |

| |accordance with accepted CCMP | | | | |

|Excavation generally |Include requirement in contracting |Maintain photographic and documentary record |Daily | |N150,000/monitoring |

| |document for Contractor to remove and |of Contractor material disposal activities | | |site visit |

| |dispose of surplus material at approved |Retain copy of approved list on project files | | | |

| |sites |Retain copy of contracting documents on | | | |

| |Include the following requirements for |project files | | | |

| |Contractors in the contracting documents: |Retain copy of contracting documents on | | | |

| |Provide temporary services acceptable |project files | | | |

| |standard where required |Maintain duplicate copies record of Contractor| | | |

| |Undertake permanent repair works for |performance | | | |

| |disrupted services within specified times |Maintain photographic and documentary record |Once | | |

| |Provide warning and safety signs in local |of Contractor performance | | | |

| |language at excavation sites | | | | |

| |Provide PPE for site workers | | | | |

| | | | | | |

| | | | | | |

|Management of spills and |Ensure that requirements relating to spill|Retain copy of contracting documents on |Once | |N50,000/truck Load |

|construction debris |management and debris are included in |project files | | | |

| |contracting documents |Maintain photographic and documentary record | | | |

| |Ensure that Contractor addresses spill |of Contractor performance |Daily | |N50,000/landfill fee/truck |

| |management and debris removal as criteria | | | |load |

| |for acceptable Contractor work plan | | | | |

| |Ensure that Contractor to promptly attend | | | | |

| |to any spills | | | | |

| |Ensure that Contractor collects and | | | | |

| |disposes of construction debris in | | | | |

| |designated locations | | | | |

| |Monitor Contractor performance in | | | | |

| |accordance with QA requirements | | | | |

Table C: Environmental Monitoring Plan

|Component |Parameters |Method |Frequency |Responsible |Remarks |Budget (N) |

|Air quality |Dust |Visual Observation |Everyday during construction |Contractor | | |

| | | | | | | |

| | | | | | | |

| | | | | |FMEnv. limits | |

| |PM, TOC, HCl, HF, SO2, CO, NOX |Ambient air monitoring using standard |Annually or where visual observations| | | |

| |, Hg, Cd, Tl, Sb, As, Pb, Cr, |method of sampling and analysis around|indicate unpleasant scenario | | |N150,000/air sample |

| |Co, Cu, Mn, Ni and V, PCDD/F |the premises | | | |analysis |

|Noise |75dB – Day time |Disturbance/pinch |Everyday during construction |Contractor | | |

| |65dB – Evening | | | |FMEnv. limits |N75,000/monitoring |

| |35dB - Night | | | | |sample |

| |Level |Sensor measurement around the premises|annually | | | |

|Erosion |Top soil movement/ground |Visual assessment |Routinely during construction |Contractor |- | |

| |cutting | | | | | |

|Water Quality |pH, TSS, Cd, Cr, Pb, Hg, |Standard method of sampling and |Where it is established that |Contractor/ Consultant | | |

| |Chlorine, total residual, |analyses |construction caused impact |Regulator | | |

| |Phenols, Total coliform | |Annually | |FMEnv. limits |N150,000/water sample |

| |bacteria, | | | | |analysis (all relevant |

| |Temp, turbidity | | | | |parameters) |

|General Waste |Reduction, |Visual Assessment, General Aesthetics,|Routinely, Daily |Contractor/HSE Officer | | |

|Management |Segregation protocols, |hazard free environment | | | |N50,000/ |

| |proper handling, storage, | | | | |truck load |

| |treatment, and transportation | | | | |N50,000/landfill |

| | | | | | |fee/truck load |

|HSE |Public and Workers Health, |Hazard and risk assessment |Annually | |Maintain records of |N100,000/worker/month |

| | | | | |occupational accidents| |

| | | | | |and diseases and | |

| | | | | |dangerous occurrences | |

| | | | | |and | |

| | | | | |accidents | |

|Health & Safety |Public health & Safety |Hazard assessment |Before Start of work and routinely | |- |N25,000/worker/month |

| |Occupational Health of workers,|Hazard Assessment |Before Start of work and routinely | |- |N50,000/worker |

| | | | | | |month |

Capacity Development and Training

To enhance the respective roles and collaboration of the relevant stakeholders, the following broad areas for capacity building have been identified as deserving of attention for effective implementation of the EMP:

1. Improving River Crossings and Environmental implications

2. Project screening techniques, screening tools and the applicable legislations and procedures;

3. General project planning and management inter-faced with environmental and social assessment and management;

4. Occupational Health and Safety

5. Environmental Impact Assessment (EIA);

6. Understanding Environmental Management Plan

7. Environmental Management Planning;

8. Monitoring and Environmental Audit;

9. Annual Environmental Report preparation and other reporting requirements;

10. Public participation techniques Public Hearing Procedure;

11. Public awareness creation / educational techniques (on environmental, social and health issues).

Implementation Schedule and Cost Estimates

For mitigation, monitoring, and capacity development, an implementation schedule for measures that must be carried out as part of the project, showing phasing and coordination with overall project implementation plans as well as the capital and recurrent cost estimates are outlined for implementing the EMP, as shown in Table D..  

 Table D: EMP Implementation Schedule

|S/N |Activity Description |Responsible |Pre-Construction |Construction |Post Construction |Estimated Cost (N) |

|1 |

The Federal Ministry of Environment EIA procedures are illustrated in Fig. 2.1

Procedurally, in Nigeria, it is worthy to note that before commencement of an EIA, the FMENV issues a letter of intent on notification by the proponent, approve the terms of reference, ensure public participation, review and mediate. However, the categorisation of the project into I, II and III determines the level of this latter part. The ministry’s project-categorization is shown in Fig. 2.2.

The possible technical activities expected for a proposed project include screening, full or partial EIA Study, Review, Decision-making, Monitoring Auditing and Decommissioning/Remediation post-closure

[pic]

Fig. 2.1: FMENV EIA Procedure

FIGURE 2i: CHECKLIST FOR THE CATEGORISATION OF EIA PROJECTS

Category I

2.1.2 Forestry Law Cap 55, 1994

The Forestry Act 1958 which was amended as the Forestry Law CAP 55 (1994) prohibits any act that may lead to the destruction of or cause injury to any forest produce, forest growth or forestry property in Nigeria. The law prescribes the administrative framework for the management, utilization and protection of forestry resources in Nigeria.

2.1.3 Land Use Act of 1978

The land-use Act of 1978 states that it is “in the public interest that the rights of all Nigerians to use and enjoy land in Nigeria in sufficient quality… to enable them to provide for the sustenance of themselves and their families” through assured, protected and preserved environmental amenities.

2.2 State Ministries/Environmental Protection Agency

In Part III of the FEPA ACT, the State Governments in Nigeria are encouraged to set up “their own Environmental Protection Bodies for the purpose of maintaining good environmental quality in the areas under their control.”

In consonance with this and the need to protect public health and safety, restore and enhance environmental quality, and sustain economic vitality through effective and efficient implementation of environmental programmes in the various States, the Kaduna State Government established the Ministry of Environment and its Parastatals, Kaduna State Environmental Protection Authority.

Inter alia, the Ministries are empowered to give direction to all issues concerning the environment, monitor and control pollution and the disposal of solid, gaseous and liquid wastes generated by various facilities in the states.

Some of the functions of the State Ministry of Environment include:

i) Liaising with the Federal Ministry of Environment, FMENV to achieve a healthy or better management of the environment via development of National Policy on Environment

ii) Co-operating with FMENV and other National Directorates/Agencies in the performance of environmental functions including environmental education/awareness to the citizenry

iii) Responsibility for monitoring waste management standards,

iv) Responsibility for general environmental matters in the State, and

v) Monitoring the implementation of EIA studies and other environmental studies for all development projects in the State.

2.3 International Legal And Administrative Instruments

Nigeria subscribes to a number of International Regulations and Conventions relating to Environmental Protection. International Development Partners/Agencies such as World Bank and other financial organizations interested in development projects have sets of environmental categorizations, assessments and management standards, which must be complied with by project proponents before these institutions invest in them.

Thus, since the RIVER CROSSING PROJECT is co-sponsored by the World Bank, it is of paramount importance to consider the World Bank Requirements on Environmental and Social issues relating to it.

2.3.1 The Bank’s Safeguard Policies

The World Bank’s Operational Policies (OP) includes guidance on Environmental Assessment requirements. The Bank’s Safeguard Policies, ten of them, is meant to ensure that operations of the Bank do not lead to adverse impacts or cause any harm.

The Safeguard Policies are lumped into Environment, Rural Development, Social Development and International Law.

The following four out of the ten whose main elements are summarized in Box 1 are relevant for considerations. These include:

• Environmental Assessment (OP 4.01);

• Involuntary Resettlement (OP/BP 4.12);

• Forestry (OP/BP 4.36); and

• Management of Cultural Property (OPN 11.03).

Environmental Assessment (OP 4.01)

The OP 4.01 requires among others that screening for potential impacts is carried out early, in order to determine the level of EA to assess and mitigate potential adverse impacts. The Bank’s project screening criteria group projects into three categories:

• Category A – Detailed Environmental Assessment;

• Category B - Initial Environmental Examination and

• Category C – Environmentally friendly

The EA ensures that appropriate levels of environmental and social assessment are carried out as part of project design, including public consultation process, especially for Category A and B projects. The OP 4.01 is applicable to all components of Bank financed projects, even for co-financed components.

Involuntary Resettlement (OP/BP 4.12)

The Policy on Involuntary Resettlement is intended to assist displaced people arising from development projects, in order not to impoverish any affected people within the area of influence of projects. An action plan that at least restores the standard of living must be instituted, in cases where resettlement is inevitable or loss of assets and impacts on livelihood occurs. Public consultation of “re-settlers” as well as the host communities is significant for the successful resettlement process and implementation of the action plan, in order to incorporate appropriate choices.

Forestry (OP/BP 4.36)

The OP/BP 4.36 aims at enhancing the environmental and social contribution of forested areas, and the need to reduce deforestation. The protection of forests through the control of forest-related impact of all investment operations is a concern of the policy. It promotes the restriction of operations affecting critical forest and conservation areas, while requiring that the sector and other relevant stakeholders should be consulted as appropriate.

Management of Cultural Property (OPN 11.03)

The policy is premised on the need to investigate and take inventory of cultural resources likely to be affected. Mitigations are provided for in cases of adverse impacts on physical cultural resources. Mitigation measures should be undertaken in conjunction with the appropriate authorities, organizations and institutions that are also required to be consulted and involved in the management of cultural property.

Bank’s Policy on Disclosure

The Bank’s policy on disclosure currently under review requires that all the people residing in the given areas of a project have the right to be informed of the proposed development project in their respective areas. Prior to project appraisal therefore, the summary of the study of the development action along with other relevant information should be disclosed to or at the level of the Bank and the project area.

The World Bank and Nigeria’s EA requirements and operational procedures were harmonised as far as possible, which makes this EMP responsive to the objectives of good practice, in the following respects:

• Early consideration of environmental and social issues;

• Identification and early consultation with stakeholders;

• Prevention of adverse impacts through the consideration of feasible alternatives; and

• Incorporation of mitigation measures into planning and (engineering) design.

The main levels of EA following screening (i.e. screening outcomes) under the Nigerian Regulations are that:

• No further EA required;

• Partial/Preliminary Environmental Assessment required;

• Environmental Impact Assessment (EIA) required;

This corresponds in principle with the Bank’s EA requirements of:

• Category C;

• Category B;

• Category A;

2.4 National and State Legislative Framework for Transport

Under the 1999 Constitution of Nigeria, there exists the Federal Government of Nigeria. The State Governments including the Federal Capital Territory and the Local Governments. Legislative functions for all levels of government are clearly spelt out in the 1999 Nigerian Constitution. Thus, the Federal Government has exclusive jurisdiction to legislate on matters set out in the Exclusive Legislative List as set out in Part 1 of the Second Schedule to the Constitution.

Matters such as Railways, Construction, alteration and maintenance of roads that are declared by the National Assembly to be Federal Trunk Roads, and Maritime shipping and navigation including shipping and navigation on tidal waters are within the exclusive preserve of the Federal Government to legislate, control and generally deal with. Therefore the State Government cannot for instance, pass any laws or legislate on matters within the Exclusive Legislate List.

|Box 2: Some Relevant World Bank's Safeguard Policies |

|Policy |Focus |

|OP 4.01 Environmental |The core requirement of this Policy is that screening should be done as early as possible for potential impacts |

|Assessment |and selection of an appropriate instrument to assess, minimize and mitigate potentially adverse impacts. |

| |Environmental Assessment (EA) ensures that appropriate levels of environmental and social assessment are carried |

| |out as part of project design. It also deals with the public consultation process, and ensures that the views of |

| |PAPs and local NGOs are incorporated as early as possible for Category A and B projects. |

| |It is worth noting that OP 4.01 applies to all components of a project with financing from the World Bank, |

| |including co-financed components by the Borrower or by other funding agencies. |

|OP/BP 4.12 Involuntary |This Policy is based on assisting the displaced persons in their efforts to improve or at least restore their |

|Resettlement |standards of living. |

| |The impetus of this Policy is that development undertakings should not cause the impoverishment of the people who|

| |are within the area of influence of the undertakings. In cases where resettlement of people is inevitable, or in |

| |cases where loss of assets and impacts on the livelihood of the PAPs is experienced, a proper action plan should |

| |be undertaken to at least restore, as stated above, their standard of life prior to the undertakings. |

| |Concerning public consultation, resettlers as well as the host communities should be consulted for the successful|

| |implementation of the resettlement process. The views of the consulted resettlers and the host communities should|

| |be incorporated into the resettlement action plan (RAP) including the list of their choices. |

|OP/BP 4.36 Forestry |The Policy envisages the protection of forests through consideration of forest-related impact of all investment |

| |operations, ensuring restrictions for operations affecting critical forest conservation areas, and improving |

| |commercial forest practice through the use of modern certification systems. |

| |In the process of forest conservation interventions, especially the local people, the private sector and other |

| |pertinent stakeholders should be consulted. |

| |In general, the Policy aims at reducing deforestation and enhancing the environmental and social contribution of |

| |forested areas. Experience with the Bank reveals that the Bank does not support commercial logging in primary |

| |tropical moist forest. |

|OPN 11.03 Management of |The Policy bases itself on investigating and inventorying cultural resources potentially affected. It includes |

|Cultural Property |mitigation measures when there are adverse impacts on physical cultural resources. |

| |The management of cultural property should be undertaken in conjunction with consulting the appropriate agencies |

| |including NGOs and academic institutions. |

| |The Bank avoids undertakings that will significantly damage non-replicable cultural property, and will assist |

| |only those undertakings that are sited or designed so as to prevent such damage. |

|The Bank’s Policy on |It is the belief of the Bank that the peoples residing in the project areas have the right to be informed of the |

|Disclosure |proposed development project(s) in their respective areas. Therefore, prior to project appraisal, the summary of |

| |the study of undertakings along with other relevant information should be disclosed at the Bank’s as well as the |

| |project area’s (local) level. |

| |The World Bank policy on disclosure is currently under review, but the present proposals state that Category B |

| |Environmental Assessment reports should be self-standing documents, and thus disclosure is a pre-requisite for |

| |appraisal of the project. |

On the other hand, where any matter is listed on the Concurrent List, both the Federal and the State Governments have the power to legislate on such issues. (See Section 4 (4) of the 1999 Constitution) where there is a conflict between a Federal Law and a State Law, the Federal Law shall prevail and the State Law shall to the extent of the inconsistency be void (see Section 4(5) of the 1999 Constitution). Apart from the matters set out in the Concurrent List, the State Government under Section 4(7) (c) is also empowered to make laws in respect of any other matters to which it is empowered to make laws in accordance with the provisions of the Constitution.

Thus, on environmental issues, the Federal Government established the FMENV, hitherto, FEPA. Section 24 of the FEPA Act encouraged the establishment of State and Local Government Environmental Protection bodies. Past Constitutions did not address environmental issues until the present 1999 Constitution which, under Section 20, sets out the protection and improvements of the environment as the Environmental Objectives for the State, thus safeguarding water, air, land, Forest and wildlife of Nigeria. It is pursuance of Section 24 of the Constitution that the Kaduna State Environmental Protection Authority (KEPA) was created vide Edict No. 1 of 1994 by the Kaduna State Government. The Kaduna State Ministry of Environment also exist which serves as the main Ministry to the Kaduna State Environmental Protection Authority.

Local Governments constitute the third tier of Government and their functions are clearly spelt out in the 4th Schedule of the Constitution. Thus, for instance, they are also responsible for the construction and maintenance of roads, streets, drains and public highways, as may be prescribed by the House of Assembly of a State.

The level at which government legislation is formulated and implemented, depends on which level of government is involved. For instance, if the issue at hand is Road Construction and Maintenance and a road is designated as Federal road, only the Federal Government has the right to construct and maintain that road under the Constitution. Where a road is designated as 8a State road, then only the State Government has the right to maintain or construct it. Local Government has powers to construct or maintain only those roads that are under its jurisdiction. The resultant effect is that there could be some Federal Roads within a State which may be in need of repairs, but may not receive the attention needed early enough, and consequently, the road continues to deteriorate. Thus for a State Government to repair such a road in order to facilitate easy movement for the citizens of the State, an agreement needs to be struck with the Federal Government.

SECTION 3: PROJECT DESCRIPTION

3.0 Introduction

In this Section, a summary of the proposed development is given

3.1 The Project

The project involves the identification of river crossings for reinstatement, construction, repairs of damaged, washed away, and or missing river crossings in rural areas of Kaduna State. The emphasis is on the provision of river crossings along rural roads in the State. Most of the activities in the provision of these river crossing structures will involve the following:

(i) Procurement of materials including stone chippings of various grades, cement, fabricated materials, motorized equipment, deployment of both skilled and unskilled labour and execution of both concrete and earth works for the structures.

(ii) Some of the materials such as sand and stone chippings may be sourced locally and, especially stone chippings, will involve blasting of granite rocks that are common sights in Kaduna State.

(iii) The types of equipment and machineries that will be brought to the site will include but not be limited to bulldozers, graders, pay loaders, excavators, dump trucks, concrete mixers etc.

The sourcing of the above listed materials and the use of machineries and equipment as shown above, will result in some environmental adverse impacts of various types as indicated in the relevant sections below.

3.2 Nature and Distribution

The structures to be constructed include bridges, culverts (box and pipe), drift, bailey bridge repairs as well as other repairs. The proposal contains Nine (9) bridges, Eighty-Five (85) box culverts, Sixteen (16) pipe culverts, Nine (9) drifts, Five (5) bailey bridge repairs and Eight (8) other structures.

The proposed project in spatial distribution covers 20 of the 23 Local Government Areas in the State. The urban Local Government Areas of Kaduna North, Kaduna South and Sabon-Gari have been excluded from the project because they have no rural communities. The distribution of these structures among the Local Government Areas is shown on Table 3.1. Also, their distribution among the Local Government Areas between the North and South is shown in Table 3.2.

Table 3.1: Distribution Of Crossing Structures By Local Government Areas

|S/No. |LGA |

| |U/Tata /Makoyi | |Kuyit |

|KUDAN |Nasarawan Kudan / Randa |KAURA |Mikunat Sabon Gari – Zakan * |

| |Zabi / Kudan | |Bailey Fadan Daji - Chenchichuong |

| |Garu / Lafia | |Dusaigada |

| |U/Tata / Makoyi | |Swanta - Kongu |

| |U/Samaila / Doka | |Bailey Fadan Daji – Chenchichuong * |

| |K/Wali South / Taba | |Bailey Fadan Daji - Chenchichuong |

| |Gidan Sharu / Mayere * | |Koko – Kussom – Mada |

|MAKARFI |Mayere / Ang. Lili |JAMA’A |Ungwa Gwandara Jagindi |

| |Abamalam / Nasarawa Doya | |Godogodo - Nindem |

| |Gangarau / Makaurata | |U Pa – Bakin Kogi - Kaninkon |

| |Feleke / Dan Ayamaka | |Ungwa Fari – Rafindadi * |

| |Feleke / Dan Ayamaka * | |Gidan Waya – Hayin Gada |

| |Maitukurwa Bridge Mayere – Ang. Karoti | | |

| |Malikanchi / Hayin Turawa | |Antor – Gwanigu Road |

|IKARA |Gimbawa / Asakale |SANGA |Agom Road |

| |Kurmin Kogi / Dallawal * | |Mayir – Tari-Ninche |

| |Kargo Bridge | |Mayir – Tari-Ninche |

| |Saulawa / Janmaramara | |Antor – Gwanigu Road |

| |Janmaramara / Saulawa | |Abu - Kanri |

| |Kapo Pala / Gidan Guza - Garki | |Mayir – Tari-Ninche |

| |T/Kaya – Madarzai-Sabongari – Turawa | |Udawa – Rimi |

|SOBA |Lungu – Takalafia – Rahama |CHIKUN |Udawa - Rimi |

| |Kinkiba-Zanko Tamba | |Udawa - Rimi |

| | | |Udawa - Rimi |

| | | |Udawa - Rimi |

| | | |Udawa – Rimi |

Source: Environmental Screening Report (2008) : * Selected Sites visited

Table 3.1: Ecological Distribution of The 20 LGAs and Project Sites In The State, cont’d

|Northern Local Government Areas |Southern Local Government Areas |

| |Tashan Adamu – Gedege | |Maraba Iri-Iri Station Maro |

| |Pambegwa – Dan Maliki | |Danbagudu - Afago |

| |Anhau – Haskiya – Ung Gata | |Fadama Kororo-Kutura-Maro |

|KUBAU |Kanar Mai Molo – Banki |KAJURU |U. Rana Kufana – Rafin Kunu * |

| |Mah-Nasarawa Mah | |Maraban Kajuru - Tantatu |

| |Kanar mai Molo-Leren Dutse | |Maraban Kachia – Aduma |

| |Kanar mai Molo-Leren Dutse | | |

| |Ang Bagwai / Alh. Babandi | |Kwalakwangi |

| |Ang. Lelle Doka / Dan Magaji | |Kwalakwangi |

|GIWA |Matsiyach Raf / Ganuwa |BIRNIN GWARI |Kwalakwangi |

| |Nasara / Balabus | |Kwalakwangi |

| |Gangara / Dundubus | |Kwalakwangi |

| |Sabon Fili / Bula | |Rafin Gungume |

| |Sabon Fili / Bula | | |

| |Hayin Danmani – Gadan Toro Toro | |Kwassam - Kibangari |

| |Rigachukun – V/Tatau - Zaure | |Kamaru – Kiza Koro |

| |Rigachukun – V/Tatau - Zaure | |Pari - Rahama |

|IGABI |Tsohon Telwa – Farin Ruwa |KAURU |Kaura Dawa - Ibada |

| |Farin Ruwa - Kuzizigi | |Kaura Dawa - Ibada |

| |Kemfa – A/Dano – Baku – Sayawa Wadaza | |Sabon Gari – Kauru – Makau Saleh |

| |Birnin Yero – Kwarau - Tami | |Sabon Gari – Kauru – Makau Saleh |

| |Baban Abu-R/Gora | |Maraba Warsa - Piti |

| |Dakace –R/Gura * | |Gure Rewa |

| |Dambo – Rafin Giwa | |Garu – Baban Fadama Road |

|ZARIA |K/Doka – Magume |LERE |Mararaba – Arande – Warsa Piti |

| |Rafin Albasa – Gwargwaje | |Kayarda – Goron Dutse |

| |Zura – Dorayi | |Maigamo – Jankasa |

| |Zura – Dorayi | |Kayarda – Goron Dutse |

Table 3.1: Ecological Distribution of The 20 LGAs and Project Sites In The State, cont’d

|Northern Local Government Areas |Southern Local Government Areas |

| | | |Zonkwa – Wadon |

| | | |Kamantan - Ashafa |

| | | |Kabam – Gidan Maga |

| | |ZANGO KATAF |Zaman Dabo – Doka 2 |

| | | |Zaman Dabo – Doka |

| | | |Kamantan – Ashafa Road * |

| | | |Zonkwa – Ramai Road |

| | | | |

| | | |Nasarawa - Adege |

| | | |K/Mazuga - Nasarawa |

| | | |Doka - Akilibu |

| | |KACHIA |Mai Ido |

| | | |Yarbung - Magajiram |

| | | |Dangalmi |

| | | |Insane – Itah |

| | | |Gidan Kundi- Shadalafiya - Inkojo |

| | | |Gidan Kundi- Shadalafiya - Inkojo |

| | | |Kubacha – Kushe Fada |

| | |KAGARKO |Kubacha – Kushe Fada |

| | | |Kubacha – Kushe Fada |

| | | |Kushe Fada Kafarma - Kasabere Gidan Kundi |

| | | |Shadalafiya Inkojo |

| | | |Sambam – Ungwa Zuma - Chori |

| | | |Chori Makama – K. Musa |

| | | |Sambam – Ungwa Zuma - Chori |

| | |JABA |Daddu – Kurmi Zomo - Kyari |

| | | |Daddu – Tsakiya Road |

| | | |Keffi - Kaf |

| | | |Sambam – Ungwa Zuma - Chori |

Source: Environmental Screening Report (2008) : * Selected Sites visited

3.3 The Need and Importance of the Project

The project concerns the provision of rural crossings on rural roads. The main aim of the project is to improve accessibility and mobility among the rural communities in Kaduna State.

Poor rural accessibility has partly been responsible for the continued poverty in the rural areas in the State. It is believed that if this infrastructure can be improved upon, by providing adequate crossings on the rural roads, the rural communities will find access to both rural and urban markets for their farm produce. This will enable them obtain the proper market pricing and value for their goods as they would have removed the middlemen in the process and getting the right price commensurate with their labour and other farm inputs. This will also increase the earning capacity of these rural farmers and in the process will reduce poverty level among them in the State.

3.4 Project Operation, Maintenance and Sustainability.

The project is being undertaken by the Kaduna State Project Coordinating Unit (SPIU). The Unit will initially be responsible for the operation of the project but there is a long term plan to transfer such operation to the local host communities. In the long run, it is believed or hoped that the host communities will take over the maintenance of the project. The SPIU will organize training programmes for the local communities on skills development for the project maintenance. The intention here is to give the local communities the ownership of the project. It is therefore, important that they are given the right skills that will enable them discharge such responsibilities most effectively.

SECTION 4: DESCRIPTION OF BASELINE ENVIRONMENTAL CONDITIONS

4.1 Locations of Propose Project

The 132 projects are spread over twenty (20) Local Government areas in the State. The State lies between lat. 9002′N – 110, 32′N and long. 60 15’E – 80 50′E.

Kaduna State is largely an undulating landscape with a lot of rock outcrops which vary in height up to 1370m above see level. It is dissected by a dense network of drainages with Rivers Kaduna and Gurara being the two main river systems that drain the north and the south respectively.

The northern part is an area that is threatened by desert encroachment, so that it has very thin vegetation cover, with extensive bare land. The South on the other hand, is forested, so that a project such as the one made under consideration here must involve the removal of vegetation. Also, the rainfall ranges between 700mm and 900mm in the North, while in the South, some areas receive rainfall of 2000mm a year. These climatic conditions make the soils in the two parts respond differently to the various aspects of erosion. While, wind erosion is normally severe in the North during the dry season, gully erosion is predominantly in the South. However, it is believed that the sites selected are true representatives of the remaining ones in the North and South, respectively.

The State experiences distinct wet and dry seasons. The wet season normally starts in the months of April/May and finishes in the months of October/November. The dry season on the other hand lasts between November and March. The annual rainfall is about 900mm in the north and rises up to 2000mm in the south. Minimum Temperatures are between 90C and 180C while the maximum Temperatures are between 300C and 420C.

The vegetation is the southern to northern Sudan Savanna type. The vegetation is green and covers up to 85% in the wet season, but in the dry season it dries up and vegetation coverage can be as low as 3% particularly in the North, and in areas that have been consumed by bush fire.

Soils, Water, air and noise quality test were conducted at two sites, Kurmin Kogi/Danlawal in Ikara which is in the north and Ungwan Fari – Rafindadi in Jema’a Local Government Area in the south. The parameters of all the samples were found to be within the Federal Ministry of Environment Limits. These results form the basis for monitoring of these environmental components when the project is commissioned.

It was observed during the site inspection that, these sites had problems which should need special attention. These are Fadan Kamanto- Ashafa bailey bridge - Zagon-kataf Local Government Area; Feleke- Dan-Ayamaka crossing – Makarfi Local Government Area, and Fadan Dayi –chenchechions bailey bridge, Kaura Local Government Area. D

One of the Consultants discussing with Community Members around Ungwan Fari – Rafin Dadi River Crossing, Jema’a Local Government Area.

Rural Communities in Kaduna State are largely engaged in agricultural activities which include farming and the rearing of animals, although hunting is also an important economic activity in the rural areas.

However, as majority of the people at the project site are farmers, therefore land is a critical matter to them. Generally, land-take usually constitutes one of the major issues of linear infrastructural development, like the crossings under consideration here. Therefore, compulsory land acquisition (expropriation of property for public projects) or demolishing of structures such as buildings, shops associated with linear developments can result in displacement of communities, affected individuals, families, or communities. Although almost all the people interviewed indicated their willingness to relinquish their land to the project, without compensation, such claims have no legal basis and can easily be challenged even after the project has been commissioned. Therefore, even if the land is not compensated for, there is the need to consider the crops, which may be on the land during the construction period of the crossings.

Infrastructural services such as road, electricity potable water supply and telecommunication are not readily available in the rural areas of Kaduna State.

SECTION 5: POTENTIAL IMPACTS AND MITIGATION MEASURES

5.0 Introduction

Outlined in this Section are a summary of the impacts that are likely to result from the project as a result of the interaction between the project components and the environmental elements.

5.1 Overview of Project Impacts

The project is envisaged to have a range of positive environmental and social impacts. Some of these are a function of the objectives of the project, while others are a function of the way in which the project is designed to meet its objectives.

The proposed project however is also expected to have some negative impact on both the surrounding land use and the local environment. These impacts include the short-term construction related impacts and long-term operation unavoidable impacts. The short-term construction impacts include the following:

In Table 5.1, a summary of the identified impacts are listed with their corresponding mitigation measures for the project while in Table 5.2, sites the shall require special attention are identified with their concerns and mitigation measures.

Table 5.1

|Table 5.1: List of identified impacts with corresponding mitigation measures for the project |

|No |Activity |Potential Negative Impacts |Mitigation Measures |

|A. MOBILISATION |

|1 |Movement of goods, |Reduction in air quality due to |Employ fuel efficient and well maintained haulage trucks with proper exhaust system to minimize emissions. |

| |equipment, etc, to site |vehicular emissions |All parked vehicles on the site shall have their engines turned off; |

| | | |Service vehicles as at when due and stick to manufacturers’ specifications in use |

| | | |Develop and follow a controlled fueling, maintenance and servicing protocol |

| | |Increase in noise nuisance |Raise community awareness of unusual activity |

| | | |Plan activities such that Regulatory limits are not exceeded |

| | |Movement of heavy equipment to |Avoid hauling of materials particularly on market days of the project communities |

| | |worksite which may pose danger to|Place visible warning signs on roads and vehicles |

| | |public/wildlife |Driving course for the drivers shall be ensured. |

| | | |Large and slow moving vehicles shall be scheduled during off-peak periods |

| | | |Raise community awareness of unusual activity |

| | | |Schedule compulsory medical fitness test for all drivers. |

| | | |Ensure construction vehicles enter and leave the site at controlled points only |

| | | |Use workers to direct vehicles and pedestrians to prevent accidents while vehicles are moving in and out of the site. |

| | |Vibration from plant/equipment |As necessary, construction barriers shall be erected for safety and to direct pedestrian traffic safely around the construction |

| | | |site. |

| | | |Fix noise abating gear mufflers to plant/equipment. |

|B. SITE PREPARATION |

|1. |Site Clearing and |Loss of Vegetation Wildlife |Minimize the extent and intensity of destruction. |

| |preparation |habitat, Flora and Fauna |Change the alignment of the proposed crossings where necessary. |

| | | |Avoid and protect destruction of exortic plants and wildlife where the exist. |

| | | |Avoid cultural sites and shines where they exist. |

|2. | |Dust emission |Enclose all material stock piles. |

| | | |Use water spray to dampen the dust. |

| | | |Use dust extractors such as in concrete plants. |

| | | |Covering of trucks and other vehicles where transporting laterite, spoil materials or any other material that generate dust on |

| | | |transits. |

| | | |Regular spraying of construction site and loading/off loading any loose materials that generate dust. |

| | |Emissions from operating plants |Engage well maintained and efficient fuel leakage trucks in line with recommended standards by manufactures. |

| | |and vehicular exhausts |Develop and follow a controlled and fueling, maintenance and servicing protocol. |

| | | |Service vehicles as and when due as stipulated by the manufactures. |

| | | |Turn off vehicles while parked. |

| | |Water contamination from site |Maintain proper housekeeping. |

| | |cleaning materials, oils and soil|Site storage tanks for fuels and oils on in previous bases with bund walls. |

| | |spoils |Place pumps on drip trays. |

| | | |Adequate sanitary facilities for employees. |

| | | |Careful plant maintenance to avoid spillages and blow outs. |

| | | |Make adequate provision for proper drainage system within the site. |

| | | |Minimize built up of silt, and spoils in river water course. |

| | | |Vehicle washing at locations and in manner that surface water is not contaminated. |

| | |Destruction of visual scenery |Screen off site during site clearing. |

| | | |Careful design and placement of ground level components. |

| | | |Screening by vegetation planting. |

| | |Accidents involving people and |Provide proper warning signs for people and animals. |

| | |animals |Remove all likely obstructions to traffic flow. |

| | | |Remove objects that may obstruct view. |

|C. CONSTRUCTION PHASE: |

|1 |Vegetation clearance |Enhance soil erosion and |Revegetate surroundings after construction. |

| | |topographic changes. |Protect exotic plants and animals where they exist. |

| | | |Protect slopes against erosion. |

|2 |Noise/ |noise level increases during |Raise community awareness of unusual activity. |

| |Vibration |construction operation |Plan activities such that Regulatory limits are not be exceeded. |

| | |ground vibration due to |Ensure powered mechanical equipment and machinery filtered with noise abating gear such as mufflers for effective sound reducing, in|

| | |construction operations |compliance with the national regulations. |

| | | |As far as possible, the operation of heavy equipment shall be conducted in day light hour. |

| | | |Construction equipment which generates excessive noise/vibration shall be isolated. |

| | | |Well maintained haulage trunks will be used with speed control. |

|3 |Air Quality and Dust |Air borne emission released to |Plant and equipment using fuel that may produce high levels of air pollutants shall be avoided; |

| | |the atmosphere due to |Fuel efficient and well maintained haulage trucks with proper exhaust baffles shall be employed to minimize exhaust emissions. |

| | |Construction-related air |Stockpiled soil and sand shall be slightly wetted before loading, particularly in windy dry conditions. |

| | |pollution |Stockpiles of sand and aggregate greater than 20 m3 in volume shall be enclosed in walls extending above the pile and beyond its |

| | |Plant operations, Material dump |front face. |

| | |sites , Vehicular emissions and |Weigh hoppers shall be vented to a suitable filter. |

| | |Haulage of materials |All vehicles, while parked on the site shall have their engines turned off. |

| | | |Using efficient equipment, machinery and vehicles with regular checking to effect necessary corrections or repairs to ensure |

| | | |compliance with safety and air pollution requirements. |

| | | |Soil, sand and other construction materials in storage and in transit shall be covered. |

| | | |Effective water sprays shall be used during the delivery and handling of all sand and aggregate and other similar material when dust|

| | | |is likely to be created and to dampen them during dry, windy weather. |

| | | |Spraying of bore areas and roads used for haulage of material with water. |

| | | |Washing of tires and lower body of vehicles when moving out from the construction site. |

| | | |Selection of sites for material extraction away from residential areas to reduce impact of dust. |

| | |Emission from plants/equipment |Vehicles/plans should be properly serviced periodically, to minimize emission of gaseous contaminants. |

| | |exhaust pipes | |

|4 |Surface Erosion/Surface |Run-off during construction |Design temporary and permanent drainage systems to minimize soil erosion. |

| |run-off |operations; |Develop and implement storm water control measures during construction. |

| | |Carry over of eroded soil |Implement an erosion and sediment control plan as part of the construction project. |

| | |particles by surface run-off |Back-fill shall be compacted properly in accordance with design standards. |

| | | |Install temporary or permanent drainage works to protect all areas susceptible to erosion, flood damage and silt |

| | | |transport/sedimentation. |

| | | |Measures shall be taken to prevent ponding of surface water and scouring of slopes. |

| | | |Newly eroded channels shall be backfilled and restores to natural contours. |

| | | |Deploy silt fences to avoid/reduce soil erosion and run-off. |

|5 |Water Quality |Water quality caused by |Divert the water and waste products arising from the site via a suitably designed temporary drainage system in a manner that will |

| |Deterioration / |construction activities affects |not cause pollution problems or other nuisance. |

| |Water Resource |the streams/rivers. |Proper disposal of solid waste from construction activities and labour camps. |

| |Protection | |Ensure storage of lubricants, fuels and other hydrocarbons in self contained enclosures. |

| | | |Vehicles and equipment shall be maintained in good condition, ensuring no leakage of oil or fuel. |

| | | |Servicing of vehicles, machinery and equipment at properly managed and equipped workshops where waste oil is collected and disposed |

| | | |off at approved locations. |

| | | |Providing sanitation arrangements at work sites and temporary accommodation facilities to avoid release of waste water and sewage to|

| | | |the environment. |

| | | |Protect groundwater by use of grouts and diaphragm walls where necessary. |

|6 |Handling and Storage of |Contamination of the immediate |Safe ventilation for storage of volatile chemicals shall be provided. |

| |Hazardous Materials |surroundings. |Access to areas containing hazardous substances shall be restricted and controlled. |

| | | |Hydrocarbon and hazardous materials shall be stored on impervious ground under cover; the area shall be constructed as spill tray to|

| | | |avoid spread of accidental spills. |

| | | |All hot mix plant, crushing plant, workshops, depots and temporary workers accommodation facilities shall be sited in approved |

| | | |locations. |

|7 |General Waste |Generation of spoil and |All other wastes generated including environmentally deleterious materials generated by construction activities will be disposed |

| | |construction waste; |offsite in an appropriate, legal, and safe manner. |

| | |Unsafe and improper disposal of |The overall goal will be to minimize as much as practical the generation of all wastes |

| | |spoil and construction waste. |Unsuitable excavated materials shall be systematically carried out away from areas prone to erosion. |

| | |Soil contamination |Reuse waste materials wherever possible and use designated disposal sites. |

| | |Water contamination |Used oil and lubricants shall be recovered and reused or removed from the site in full compliance with the FMEnv and KEPA |

| | |Injury to personnel |regulations. |

| | | |Oil wastes, debris and/or other waste materials must not be burned. |

| | | |Optimize the reuse of spoil and construction waste. |

| | | |All the construction camps and facilities shall be dismantled and removed from the site, unless otherwise desired by the local |

| | | |community. |

| | | |Restore the site to a condition in no way inferior to the condition prior to the commencement of work. |

| | | |Cover soak pits and septic tanks and effectively seal them off. |

| | | |Follow safety measures while disposing wastes. |

| | | |Avoid introduction of foreign soil and synthetic materials. |

|8 |Plants and animal life |Disturbance of plants and animal |Change alignment of crossings where necessary to minimize extent and intensity of disturbance/destruction especially of endemic |

| | |community habitats |Wildlife and Exotic plants where they exist. |

|9 |Land degradation |Creation of Excavation sites and |Rehabilitate Excavation sites by filling. |

| | |triggering erosion |Plant trees, and shrubs to check erosion. |

| | | |Develop embankment on steep slopes to protect them from erosion. |

| | | |Stone pitch to protect slopes where necessary |

|10 |New Settlements |Attraction of new settlers near |Discourage new settlements close to the stream (river crossing). |

| |Development |the crossing which will lead to |Create forest/bush reserves around the crossing area to preserve fauna and flora. |

| | |destruction of vegetation | |

| | |wildlife and increased traffic | |

|11 |Visual Impact |Destruction of visual scenery |As much as possible keep plants and equipment off the crossing and its immediate vicinity. |

| | | |Areas opened up by clearing vegetation to pave way for the crossing construction should be replanted after construction. |

| | | |Ugly scars left around the crossing site through clearance for construction should be leveled and landscaped. |

| | | |New structures such as signboards, bill boards for the project should be removed after construction. Those required such as |

| | | |direction or warning signs should be properly placed. |

|12 |Accessibility |Risk of accidents |Ensure the traffic (vehicular) does not exceed the capacity of the river crossing by placing restrictions on type/weight of |

| | | |vehicles. |

| | | |Place signs and speed limits or zebra crossing/bumps. |

|13 |Influx or new settlers, |Risk of spread of diseases |Create public enlightenment and awareness on crime and STDs such as HIV/AIDs. |

| |workers, and traders | |Contractors staff. |

| | | |Provision of health care facilities. |

|14 | |Land take |Minimize land take through realignment or relocation of affected crossing. |

| | | |Engage land swaps. |

| | | |Improve access to alternative land. |

| | | |Choosing route locations away from built-up areas and restricting the extent of road works to avoid interference with existing |

| | | |activities. |

| | | |Adoption of a reduced speed design, reduced right-of-way land requirements, or design changes (underground drainage, for instance) |

| | | |to reduce impacts on properties and acitivites. |

| | | |Alternative considerations in route selection. |

| | | |Integration of mitigation measures in road designs, where appropriate. |

| | | |Compensation rates for owners of the land, properties, etc that reflect current market realities. |

|D. PROJECT OPERATION |

|1. |Vehicular movement |Air contamination from vehicular |Speed limits to be imposed. |

| | |exhausts. |Road worthiness and traffic control regulations to be enforced. |

| | |Dust arising vehicle tyre/road |Proper warning signs to be properly placed. |

| | |surface contact. | |

| | |Risk of accidents | |

| | |(human/animals). | |

|2. |Improved accessibility |Immigration towards project site |Provide for influx of people. |

| | |and risk of conflict. |Increase communities facilities to accommodate new comers. |

| | | |Encourage community integration. |

Table 5.2: RIVER CROSSINGS WITH SPECIAL PROBLEMS

|S/No |Crossing/Location |Problems |Solution |

|1. |Fadan Kamantan to Ashafa Bailey |Approaches to crossing are steep and subject to |Reduce the steep slopes by filling the |

| |bridge in Zangon Kataf Local |erosion. Crossing gets flooded during the peak of|approaches; |

| |Government Area. |the rainy season. |The bridge sides should be embanked to |

| | | |prevent erosion. |

|2. |Feleke – Dan Ayamaka crossing in |Approaches to the culvert crossing have been |Fill up the cut off areas and embank or stone|

| |Makarfi Local Government Area. |eroded, cutting off the northern portion of the |– pitch to control erosion; |

| | |road completely from the culvert. |Raise level of crossing above the stream to |

| | |The crossing is also very liable to flooding |control the flood. |

| | |which leads to destruction of farmlands. | |

|3. |Fadan Dayi – Chenchechiong Bailey |The Bailey bridge is located some 80m – 100m from|Install noise and vibration reducing measures|

| |Bridge in Kagoro, Kaura Local |houses to the south east. During construction, |in plants and equipment; |

| |Government Area. |the residents will be affected by vibration, |Check/control air pollution by sprinkling |

| | |noise, air pollution, water pollution of their |water during construction; |

| | |river which is their source of drinking water. |Temporary divert water course to avoid |

| | | |pollution from construction material; |

| | | |Vegetation after construction. |

TABLE 5.3: Potential Adverse Impacts, Mitigating Measures, Monitoring and Cost Estimates

|S/N |Potential Adverse Impact |Mitigation Action/Activity |Monitoring and Evaluation Responsibility |Cost (Naira) |

|1. |MOBILISATION | | | |

| |Reduction in air quality due to vehicular |Employ fuel efficient and well maintained |Contractor/State Project Implementation |N150,000/air sample analysis |

| |emissions |vehicles and equipment; |Unit (SPIU) /Kaduna Environmental | |

| | |Service vehicles regularly according to |Protection Authority (KEPA) | |

| | |specifications. | | |

| |Increase in noise nuisance due to: | | | |

|2. |Movement of heavy equipment to worksite |Maintain noise levels at 75dB – during the day|Contractor/SPIU/KEPA |N150,000/air sample analysis |

| |which may pose danger to public/wildlife |65dB – evening 45dB – night. | | |

| |Vibration from plant/equipment | | | |

| |SITE PREPARATION | | | |

|3. |Loss of Vegetation Wildlife habitat, Flora |Vegetation clearing to be restricted to area |Contractor/SPIU/KEPA |N150,000/monitoring site visit |

| |and Fauna |required for safe operation; | | |

| | |Discourage hunting, fishing, collection of | | |

| | |forest products; | | |

| | |Avoid unnecessary damage to valuable trees, | | |

| | |crops, wildlife and areas of environmental | | |

| | |interest. | | |

|4. |Dust emission |Sprinkle water to reduce dust |Contractor/SPIU/KEPA |N150,000/air sample analysis |

|5. |Emissions from operating plants and |Employ fuel efficient and well maintained |Contractor/SPIU/KEPA |N150,000/air sample analysis |

| |vehicular exhausts |vehicles; | | |

| | |Service vehicles according to specifications. | | |

|6. |Water contamination from site cleaning |Maintain water flow as required in rivers, |Contractor/SPIU/KEPA |N200,000/water sample monitoring analysis |

| |materials, oils and soil spoils |streams and other natural channels and | | |

| | |re-establish them if disrupted; | | |

| | |Avoid releasing oils, lubricants and waste | | |

| | |water into streams, rivers, irrigation | | |

| | |channels and other water bodies. | | |

|7. |Destruction of visual scenery |Screen off site. | |N150,000/site visit |

|8. |Accidents involving people and animals |Provide adequate warning signs; |Contractor/SPIU/KEPA |N150,000/monitoring site visit |

| | |Remove all likely obstructions to traffic; | | |

| | |Remove objects that may obstruct view. | | |

|9. |Enhance soil erosion and topographic |Re-vegetate site surroundings after | |N150,000/monitoring site visit |

| |changes. |construction; | | |

| | |Protect exotic plants; | | |

| | |Protect slopes against erosion. | | |

|10. |Noise level increases during construction |Raise community awareness; |Contractor/SPIU/KEPA |N150,000/noise level samplings analysis/site |

| |operation |Conduct construction activities during the | | |

| |Ground vibration due to construction |day; | | |

| |operations |Use noise abating gear such as mufflers to | | |

| | |reduce nuisance; | | |

| | |Service and maintain haulage trucks according | | |

| | |to specification. | | |

|11. |Air borne emission released to the |Stock piled soil and sand shall be slightly |Contractor/SPIU/EC/KEPA |N300,000/monitoring visit and air sample analysis |

| |atmosphere due to Construction-related air |wetted before loading and shall be located | | |

| |pollution |where trees act as butters to reduce dust | | |

| |Plant operations, Material dump sites , |pollution; | | |

| |Vehicular emissions and Haulage of |Excess materials to be deposited in areas | | |

| |materials |approved by KEPA; | | |

| | |Hazardous liquid and solid materials shall be | | |

| | |deposited at sites approved by the ER and | | |

| | |KEPA. | | |

|12. |Run-off during construction operations; |Avoid run-off containing spoils site effluent,|Contractor/SPIU/KEPA |N150,000/monitoring site visit |

| |Carryover of eroded soil particles by |such as cement and, oils into natural | | |

| |surface run-off |drainage; | | |

| | |No waste from washing into water courses | | |

| | |without treatment; | | |

| | |Site spoils and temporary stockpiles to be | | |

| | |located away from drainage systems. | | |

|13. |Water quality caused by construction |Water quality parameters to be maintained in |Contractor/EC/KEPA |N200,000/water sample analysis |

| |activities affects the streams/rivers. |accordance with the Federal Ministry of | | |

| | |Environment limits. | | |

|14. |Contamination of the immediate |Safe storage area; |Contractor/EC/KEPA |N150,000/site monitoring visit |

| |surroundings. |Only authorized and competent person to handle| | |

| | |hazardous storage materials; | | |

| | |Prefer bulk storage with mechanized handling | | |

| | |than small drums to avoid spillage; | | |

| | |Label storage tanks/drums; | | |

| | |Vehicle carrying inflammable liquid to be put | | |

| | |off before loading/unloading; | | |

| | |Maintain fire extinguishers; | | |

| | |Display adequate warning signs. | | |

|15. |Generation of spoil and construction waste;|Reuse waste material whenever possible; |Contractor/EC/KEPA |N150,000/site visit |

| |Unsafe and improper disposal of spoil and |Rehabilitate site so that rate of | | |

| |construction waste. |rehabilitaties is similar to the rate of | | |

| |Soil contamination |construction; | | |

| | |Top soil not to be stored in large heaps; | | |

| | |Locate stokepiles where they are not disturbed| | |

| | |by construction activities; | | |

| | |Soils shall not be stripped when they are wet | | |

| | |to avoid soil compaction and loss of | | |

| | |structure; | | |

| | |Keep toxic materials well protected until | | |

| | |proper disposal. | | |

|16. |Creation of Excavation sites and triggering|Obtain permit/license from KEPA, Federal |Contractor/EC/KEPA |N150,000/monitoring site visit |

| |erosion |Ministry of Solid Minerals, Local Government, | | |

| | |Traditional rules; | | |

| | |Locate excavation sites away from settlements,| | |

| | |forest reserves, archaeological sites or other| | |

| | |areas of restructions; | | |

| | |Demarcate and mark bounding of site. | | |

|17. |Risk of accidents |Provide adequate warning signs; |Contractor |N150,000/monitoring visit/site |

| | |Speed limit to be maintained; | | |

| | |Access roads to be done in consultation with | | |

| | |local communities. | | |

|18. |Risk of spread of diseases |Mount awareness and hygiene campaign; |Contractor |N1,500,000/year |

| | |Sensitise workers and local residents on | | |

| | |health risks particularly HIV/AIDS. | | |

|19. |Land take |Minimize land take by re-alignment; |Contractor /Kaduna State Ministry of |N350,000 for valuation |

| | |Pay compensation if necessary. |Lands and surveys | |

| | | | | |

|20. |Conflict with realities on the site due to |Ensure that there is proper site analysis to |Contractor/SPIU/KEPA |N150,000/monitoring site visit |

| |inadequate site analysis |provide adequate site information; | | |

| | |Provide adequate site information. | | |

|21. |Community agitation |Ensure contractor provides acceptable work |Contractor/SPIU |N150,000/site monitoring visit |

| |Delays in project; |plan | | |

| |commencement because contractor has not |Ensure plan addresses requirements of EMP | | |

| |submitted acceptable work plan |Apply QA principles to work plan acceptance. | | |

|22. |Social conflict, (Community agitation); |Discuss contractor’s proposals with community;|Contractor/SPIU/KEPA |N150,000/site monitoring visit |

| |Reduction in community and government |Contractor to comply with applicable laws, | | |

| |support; |guidelines and regulation in force in Kaduna | | |

| |Increased risk of work force injury; |State; | | |

| |Increased risk of damage to built |Entry of run-off to the site shall be | | |

| |environment; |restricted. | | |

| |Delays in project commencement | | | |

|23. |Inconvenience to the community |Identify suitable camp site; |Contractor/SPIU/KEPA |N150,000/site inspection visit |

| |Noise and vibration generation from camp |Obtain relevant approvals for camp location; | | |

| |site; |Construction waste shall not be left in | | |

| |Over stretching of community infrastructure|stokepiles; | | |

| |due to unsuitable site location |Wastes shall be deposed on KEPA approved | | |

| | |landfills; | | |

| | |Waste materials must not be allowed to be | | |

| | |washed into water channels; | | |

| | |Provide proper sanitary facilities in camp; | | |

| | |Provide fencing round site to be well drained | | |

| | |for storm water. | | |

|24. |Loss of government support; |Ensure that required applications for approval|Contractor |N1,000,000 for relevant approvals |

| |Delays & cost increases due to absent of |are lodged with KEPA and KASUPDA. | | |

| |relevant approvals | | | |

|25. |Low quality/unacceptable work; |Train staff accordingly; |Contractor/SPIU |N150,000/site visit |

| |Delays and cost increases due to lack of |Give priority to indigenes in employment; | | |

| |evidence of contractor’s key |Include requirements for key staff | | |

| |staff qualifications |qualifications in contracting documents; | | |

| | |Non-acceptance contractor work plan until | | |

| | |evidence is provided. | | |

|26. |Failure to meet QA and QC requirement; |Include requirement for independent materials |Contractor |N300,000/sample |

| |Material quality unsuitable for the task; |testing in contracting documents; | | |

| |Delays and cost increases due to failure to|Ensure Contractor complies with all | | |

| |undertake required materials testing |specifications including those in QA and QC | | |

| | |manuals. | | |

|27. |Environmental degradation due to failure to|Conducting special briefing and/or onsite |Contractor |N150,000/monitoring visit |

| |provide adequate training and awareness on |trainings for the contractor’s personnel on | | |

| |environmental and requirements |the environmental requirement of the project; | | |

| | |Provide specific procedures training for those| | |

| | |employees that have peculiar responsibilities | | |

| | |associated with the project. | | |

| | |Training to includes: | | |

| | |EHS general (working procedures) | | |

| | |Emergency procedures; | | |

| | |Social and cultural aspects (awareness | | |

| | |creation) | | |

|28. |Increased levels of dust in the project |Undertake watering of camp site |Contractor/SPIU/KEPA |N150,000/air sample analysis |

| |site |Implement approved work plan | | |

| |Loss of community support; |Restrict vehicle movements | | |

| |Community inconvenience |Submit regular monitoring reports | | |

| |Contamination of soil, surface and |Include requirement for implementation of | | |

| |groundwater; |mitigation measures in the contracting | | |

| |From: |documents; | | |

| |Pollution and nuisance to the community |Provide workers with appropriate sanitation | | |

| |from lack of latrines, bathrooms, potable |facilities; | | |

| |water, uncontrolled dust generated |Undertake regular monitoring; | | |

| | |Implement QA requirements | | |

|29. |Increased dust pollution from material |Obtain license for the excavation of borrow |Contractor |N150,000/site visit |

| |stockpiles (dry season); |pits and quarries from Federal Ministry of | | |

| |Delays and cost increases; |Solid Mineral and Steel/KEPA; | | |

| |Accidents & injuries to workers & residents|Avoid areas of minimal vegetation; | | |

| |disposal of the excavated materials and |Deposit any excess materials in accordance | | |

| |during excavation. |with principles of the general conditions of | | |

| | |the EMP; | | |

| | |Undertake permanent repair works for disrupted| | |

| | |services/facilities; | | |

| | |Provision of warning and safety signs in Hausa| | |

| | |and English at excavation sites; | | |

| | |Provision of PPE for workers. | | |

|30. |Loss of community and government support; |Include requirements relating to spill |Contractor/SPIU/KEPA |N150,000/monitoring visit. |

| |Contamination of soil, surface water and |management and debris removal in contracting | |N50,000/truck load of debris for disposal. |

| |groundwater; |documents; | |N50,000 landfill disposal fee per truck load. |

| |Increased risk of injury due to failure to |Include spill and debris removal on Contractor| | |

| |promptly attend to spills. Failure to |work plan; | | |

| |appropriately dispose of construction |Promptly attend to oil spill; | | |

| |debris |Collect and dispose of construction debris in | | |

| | |designated locations; | | |

| | |Monitor performance in accordance with QA | | |

| | |provisions | | |

|31. |Impact on water quality due to failure to |Contractor shall avoid pollution of water |Contractor/SPIU/KEPA |N150,000/water sample analysis (all relevant |

| |consider importance of water quality |bodies caused by the operation of construction| |parameters) |

| | |machinery and equipment; | | |

| | |Proper disposal of water and wastewater | | |

| | |generated by construction activities; | | |

| | |Vehicles and equipment shall be maintained in | | |

| | |good operational condition, ensuring no | | |

| | |leakage of oil or fuel | | |

|32. |Impacts on air quality/dust due to failure |All heavy equipment and machineries shall be |Contractor/SPIU/KEPA |N150,000/air sample analysis |

| |to consider/count air quality/dust |in full compliance with national regulations | | |

| | |for emissions | | |

| | |Stockpiled sand and aggregate shall be | | |

| | |slightly wetted before loading, particularly | | |

| | |in dry windy conditions; | | |

| | |Spraying of water during delivery and handling| | |

| | |of dust generating materials; | | |

| | |Covering of materials during transportation. | | |

|33. |Land degradation from failure to ensure | Compacted backfill properly in accordance |Contractor/SPIU/KEPA |N150,000/site monitoring visit |

| |good engineering practices. |with design standards; | | |

| | |In the short-term, either temporary or | | |

| | |permanent drainage works shall protect all | | |

| | |areas susceptible to erosion, flood damage and| | |

| | |silt transport/sedimentation; | | |

| | |Measures shall be taken to prevent ponding of | | |

| | |surface water and scouring of slopes; | | |

| | |Newly eroded channels shall be backfilled and | | |

| | |restored to natural contours; | | |

| | |Use of silt traps where earthworks are carried| | |

| | |out adjacent to water bodies; | | |

| | |Remove and retain top soil for subsequent | | |

| | |rehabilitation; | | |

| | |Topsoil shall be stored in low moulds not | | |

| | |exceeding 1 – 2m high; | | |

| | |Revegetate stokepile with recommended grass | | |

| | |species to avoid erosion; | | |

| | |Identify toxic overburden and screen with | | |

| | |suitable material to prevent mobilization of | | |

| | |toxins. | | |

|34. |Increases risk of injuries for the project |Providing adequate warnings signs; |Contractor/SPIU/KEPA |N150,000/site monitoring visit |

| |labors; |Providing workers with skull guard or hard hat| | |

| |Increase public risk due to failure to |and other safety devices; | | |

| |conduct adequate safety and precaution for |Arrange for regular safety checks of vehicles | | |

| |the workers |and materials, and allocation of | | |

| | |responsibility for checking; | | |

| | |Ensuring that materials extractions are | | |

| | |supervised and carried out by trained and | | |

| | |experienced staff. | | |

|35. |Conflicts with local community; |Conflicts with local community shall be |Contractor/SPIU/Social Welfare |N150,000/site monitoring visit |

| |Nuisance to the community due to failure to|avoided; | | |

| |count/consider community health |Potential for spread of vector borne and | | |

| | |communicable diseases from labor camps shall | | |

| | |be avoided; | | |

| | |Competition with locals for resources will be | | |

| | |avoided; | | |

| | |Work to be carried out within working hours; | | |

| | |Provide temporary road or bridges to existing | | |

| | |communities and houses wherever there is a | | |

| | |disturbance to community traffic flow. | | |

|36. |Accidents |Construction site vehicles will enter and |Contractor/SPIU/Kaduna State Ministry of |N150,000/site monitoring visit |

| |Conflict with community members due to |leave the site at controlled points only; |Works and Transport | |

| |failure to Control environmental nuisance, |Use workers to direct vehicles and pedestrians| | |

| |damage to abutting land uses and traffic |to prevent accidents while vehicles are moving| | |

| | |in and out of the site; | | |

| | |Erect construction barriers for safety and to | | |

| | |direct pedestrian traffic safely around the | | |

| | |construction site; | | |

| | |Mount adequate and clear road warning signs. | | |

5.3 Environmental and Social Mitigation- Principles and Clauses

A comprehensive list of environmental and social clauses to be observed as appropriate in the implementation of this EMP is presented in Appendix 5.1. In addition, to further assist the contractors in achieving environmental and social objectives of the project, Good Construction Practices Guidelines have been outlined in Appendix 5.2 as Contractor Checklist. The Guidelines for the Contractor on good-practices for key activities and operation are not exhaustive or complete and thus the contractor may adopt practices which are more suitable or specific to the nature and type of actual works to be undertaken considering the possible/potential risks/hazards involved with regard to proposed environmental and social mitigation measures.

SECTION 6: ENVIRONMENTAL MONITORING PLAN

6.1 Introduction

Monitoring is a key component of the EMP during project implementation. The significance of monitoring stems from the fact that the inputs derived from the designed EMP into the project design and planning, including mitigation measures are based largely on “predictions”. It is essential that the basis for the choices, options and decisions made in formulating or designing the project and other environmental and social safeguard measures are verified for adequacy and appropriateness. Hence the need for this aspect of the EMP

Also, monitoring verifies the effectiveness of impact management, including the extent to which mitigation measures are successfully implemented.

Monitoring specifically helps to:

• Improve environmental and social management practices;

• Check the efficiency and quality of the environmental management processes;

• Establish the scientific reliability and credibility of the EMP for the project and

• Provide the opportunity to report the results on safeguards and impacts and proposed mitigation measures implementation.

General monitoring will be conducted daily and weekly throughout the construction stage and annually during the operation and maintenance phase. Routine monitoring and reporting will be undertaken by the Contractor during the construction stage. The Supervising consultant and the SPIU shall develop an auditing schedule and undertake audits in accordance with the schedule.

6.2 Monitoring Procedure

Environmental monitoring activities shall be based on direct or indirect indicators of emissions, effluents, and resource use applicable to the particular project. Monitoring frequency shall be sufficient to provide representative data for the parameter being monitored. Monitoring should be conducted by trained individuals following monitoring and record-keeping procedures and using properly calibrated and maintained equipment.

Monitoring data shall be analyzed and reviewed at regular intervals and compared with the operating standards so that any necessary corrective actions can be taken.

Table 6.1 contains a list of parameters to monitor during the construction stage while in Table 6.2 parameters for either continuous or periodic monitoring are spelt out even during construction and operation.

Table 6.1: Summary of Implementation of Phase Mitigation Measures - design & construction

|No |Activity |Potential Impacts |Mitigation Measures |Implementation |Responsibility |

|A |Pre-construction Phase Mitigation Measures |

|1 |Project Design |Conflict with realities on the |Ensure that there is proper site analysis |Undertake survey of site |Contractor |

| | |site due to inadequate site |to provide adequate site information | | |

| | |analysis | | | |

|2 |Development of contractor|Community agitation |Ensure contractor provides acceptable work|Develop checklist for requirements and provide to |Contractor |

| |work plan |Delays in project; |plan |contractor | |

| | |commencement because contractor |Ensure plan addresses requirements of EMP |Establish Hold Point for acceptance of work plan. No | |

| | |has not submitted acceptable work|Apply QA principles to work plan |physical site works to be undertaken until written | |

| | |plan |acceptance. |release of hold point by site supervisor. | |

|3 |Preparation of Contractor|Social conflict, (Community |Include requirement for CCMP in |Include a requirement for preparation of acceptable CCMP|Contractor |

| |Camp Management Plan |agitation); |specifications |and drawings in specifications | |

| |(CCMP) |Reduction in community and |Apply QA principles to CCMP acceptance |Establish Hold Point for acceptance of CCMP. No physical| |

| | |government support; |Discuss contractor proposals with |site works to be undertaken until written release of | |

| | |Increased risk of work force |community |hold point by site supervisor. | |

| | |injury; | |Undertake consultation with local council part of the | |

| | |Increased risk of damage to built| |CCMP acceptance process | |

| | |environment; | | | |

| | |Delays in project commencement | | | |

|4 |Erection of contractor |Inconvenience to the community |Identify suitable camp site |Identify suitable camp site in consultation with |Contractor |

| |construction camp |Noise and vibration generation |Obtain relevant approvals for camp |Community | |

| | |from camp site; |location | | |

| | |Over stretching of community | | | |

| | |infrastructure due to unsuitable | | | |

| | |site location | | | |

|5 |Obtain required |Loss of government support; |Ensure that required applications for |Submit Building Plan Approval to Town Planning Office |Contractor |

| |government approvals |Delays & cost increases due to |approval are lodged with KEPA and KASUPDA |Submit Environmental Assessment Report/EMP to KEPA | |

| | |absent of relevant approvals | | | |

|6 |Contractor provide |Low quality/unacceptable work; |Give priority to indigenes in employment |Include in contracting documents requirements for |Contractor |

| |evidence of key staff |Delays and cost increases due to |Include requirements for key staff |Contractor to provide documentary evidence of key staff | |

| |qualifications |lack of evidence of contractor’s |qualifications in contracting documents; |qualifications; | |

| | |key |Non-acceptance of Contractor work plan |Include in contracting documents documented evidence | |

| | |staff qualifications |until evidence is provided |requirement as a criterion for acceptability of | |

| | | | |Contractor work plan. | |

|B. |Construction Phase |

|1 |Materials testing |Failure to meet QA and QC |Include requirement for independent |Ensure that contracting documents include requirement |Contractor/IEC |

| | |requirement; |materials testing in contracting documents|for independent materials testing. | |

| | |Material quality unsuitable for |Ensure Contractor complies with all |Ensure Contractor complies with all specifications | |

| | |the task; |specifications including those in QA and |including those in QA and QC manuals. | |

| | |Delays and cost increases due to |QC manuals | | |

| | |failure to undertake required | | | |

| | |materials testing | | | |

| | | | | | |

| | | | | | |

|2 |Environmental training |Environmental degradation due to |Conducting special briefing and/or onsite |The contractor to conduct briefing session as and when |Contractor/IEC |

| | |failure to provide adequate |trainings for the contractor’s personnel |required. | |

| | |awareness of environmental |on the environmental requirement of the |Consultant to ensure that the contractor conducts | |

| | |requirements |project |trainings for his personnel both, before construction | |

| | | | |and during the implementation | |

|3 |Operation of Contractor |Increased levels of dust in the |Undertake watering of camp site |Include requirement for regular watering of camp site |Contractor |

| |construction camp |project site |Implement approved work plan |and construction sites during dry windy weather in | |

| | |Loss of community support; |Restrict vehicle movements |contracting documents | |

| | |Community inconvenience |Submit regular monitoring reports |During dry windy weather Contractor to undertake water | |

| | |Contamination of soil, surface |Include requirement for implementation of |spraying each day before start of work and regularly | |

| | |and groundwater; |mitigation measures in the contracting |throughout the day thereafter and as otherwise directed | |

| | | |documents; |by the site supervisor | |

| | |From: |Provide workers with appropriate |Implement approved work plan | |

| | |Pollution and nuisance to the |sanitation facilities; |Monitor and submit monthly reports on contractor | |

| | |community from lack of latrines, |Undertake regular monitoring; |implementation of approved work plan and mitigation | |

| | |bathrooms, potable water, |Implement QA requirements |measures | |

| | |uncontrolled dust generated | |Contracting documents to include requirements for | |

| | | | |workers to be provided with the following facilities: | |

| | | | |Adequate numbers of functional bathrooms and latrines | |

| | | | |(latrines may be portable) | |

| | | | |Covered rubbish bins for scraps | |

| | | | |Adequately stocked first aid medical kit | |

| | | | |Trained person to provide first aid assistance if | |

| | | | |required | |

| | | | |Contracting documents to include requirement for | |

| | | | |provision of facilities for collection and regular | |

| | | | |disposal of solid & liquid wastes | |

| | | | |Undertake regular monitoring to ensure compliance with | |

| | | | |requirements | |

|4 |Excavation |Increased dust pollution from |Contracting documents to include |In the contracting documents include requirements for |Contractor/Project Proponent/IEC/KEPA |

| |Generally |material stockpiles (dry season);|requirements in relation to removal and |the Contractor to remove and dispose of surplus | |

| | |Delays and cost increases; |disposal of excavated material; |excavated material at approved sites | |

| | |Accidents & injuries to workers &| | | |

| | |residents disposal of the |Contracting documents to include |Include the following requirements for the Contractor in| |

| | |excavated materials and during |requirements in relation to: |contracting documents: | |

| | |excavation. |Provision of temporary services to |Provision of temporary services to acceptable standard | |

| | | |acceptable level for any disruptions |where required; | |

| | | |caused by construction; |Permanent repair works for disrupted services within | |

| | | |Undertaking permanent repair works for |specified times; | |

| | | |disrupted services; |Provision of temporary access to acceptable standard | |

| | | |Provision of warning and safety signs in |across open trenches | |

| | | |Hausa and English at excavation sites; |Provision of warning and safety signs in local language | |

| | | |Provision of PPE for workers; |at excavation sites | |

| | | | |Provision of PPE for workers including safety helmets, | |

| | | | |footwear, eye and hearing protection | |

|5 |Management of spills and|Loss of community and government |Include requirements relating to spill |Ensure that requirements relating to spill management |Project Proponent/Contractor/IEC/KEPA |

| |construction debris |support; |management and debris removal in |and debris are included in contracting documents; | |

| | |Contamination of soil, surface |contracting documents; |Ensure that the Contractor addresses spill management | |

| | |water and groundwater; |Include spill and debris removal on |and debris removal as inclusions in acceptable | |

| | |Increased risk of injury due to |Contractor work plan; |Contractor work plan; | |

| | |failure to promptly attend to |Promptly attend to oil spill; |Include requirements for Contractor to promptly attend | |

| | |spills. Failure to appropriately |Collect and dispose of construction debris|to oil spills in contracting documents; | |

| | |dispose of construction debris |in designated locations; |Ensure any oil spills are attended to promptly | |

| | | |Monitor performance in accordance with QA |Ensure Contractor collects and disposes of construction | |

| | | |provisions |debris in designated locations | |

| | | | |Monitor Contractor performance in accordance with QA | |

| | | | |requirements | |

|6 |Water Quality |Impact on water quality due to |Contractor shall avoid pollution of water |The constructor shall store lubricants, fuels and other |Contractor |

| | |failure to consider importance of|bodies caused by the operation of |hydrocarbons in self contained enclosures | |

| | |water quality |construction machinery and equipment; |Contractor to ensure proper disposal of solid waste from| |

| | | |Proper disposal of water and wastewater |construction activities and labor camps | |

| | | |generated by construction activities; | |Contractor |

| | | |Vehicles and equipment shall be maintained| | |

| | | |in good operable condition, ensuring no | | |

| | | |leakage of oil or fuel | | |

|7 |Air Quality |Impacts on air quality/dust due |All heavy equipment and machineries shall |No exceedance of regulator limits on air pollutants; |Contractor |

| | |to failure to consider/count air |be in full compliance with national |The contractor shall document that all liquid and solid | |

| | |quality/dust |regulations for emissions |hazardous and non-hazardous waste are separated, | |

| | | |Stockpiled sand and aggregate shall be |collected and disposed off according to regulations. | |

| | | |slightly wetted before loading, | | |

| | | |particularly in dry windy conditions; | | |

| | | |Spraying of water during delivery and | |Contractor |

| | | |handling of dust generating materials; | | |

| | | |Covering of materials during | | |

| | | |transportation. | | |

| | | | | | |

| | | | | | |

|8 |Soil Erosion/runoff |Land degradation from failure to | Compacted backfill properly in accordance|Good engineering practice |Contractor |

| | |ensure good engineering |with design standards; | | |

| | |practices. |In the short-term, either temporary or | | |

| | | |permanent drainage works shall protect all| | |

| | | |areas susceptible to erosion, flood damage| | |

| | | |and silt transport/sedimentation; | | |

| | | |Measures shall be taken to prevent ponding| | |

| | | |of surface water and scouring of slopes; | | |

| | | |Newly eroded channels shall be backfilled | | |

| | | |and restored to natural contours; | | |

| | | |Use of silt traps where earthworks are | | |

| | | |carried out adjacent to water bodies; | | |

| |Safety requirement |Increases risk of injuries for |Providing adequate warnings signs; |The constructor shall instruct his workers in health and|Contractor |

| | |the project labors; |Providing workers with skull guard or hard|safety matters and require the workers to use the | |

| | |Increase public risk due to |hat and other safety devices; |provided safety equipment; | |

| | |failure to conduct adequate |Arranging for regular safety checks of |Constructor to establish all relevant safety measures as| |

| | |safety and precaution for the |vehicles and materials, and allocation of |required by law and best engineering practices; | |

| | |workers |responsibility for checking; |Contractor to ensure that vehicles and equipment | |

| | | |Ensuring that materials extractions are |operators are properly licensed and trained | |

| | | |supervised and carried out by trained and | | |

| | | |experienced staff | | |

|9 |Social Impacts |Conflicts with local community; |Conflicts with local community shall be |Engage community consultation meetings; |Contractor/Community |

| | |Nuisance to the community due to |avoided; |Contractor shall ensure that his workers are not | |

| | |failure to count/consider |Potential for spread of vector borne and |infected with serious diseases; | |

| | |community health |communicable diseases from labor camps |Contractor to arrange for regular medical checks of his | |

| | | |shall be avoided |workers; | |

| | | |Competition with locals for resources will|Contractor shall select sites for materials extraction | |

| | | |be avoided; |away from residential areas; | |

|10 |Public Health |Accidents |Construction vehicles will enter and leave|As a rule, the contractor shall conduct training for |Contractor |

| | |Conflict with community members |the site at controlled points only. |employees, operation of heavy equipments in daylight | |

| | |due to failure to Control |Use workers to direct vehicles and |hours. | |

| | |environmental nuisance, damage to|pedestrians to prevent accidents while |Isolate all construction equipment, which generates | |

| | |abutting land uses and traffic |vehicles are moving in and out of the |excessive noise. | |

| | | |site. | | |

| | | |Erect construction barriers for safety and| | |

| | | |to direct pedestrian traffic safely around| | |

| | | |the construction site. | | |

Table 6.2: Project Site Activity Monitoring and Frequency during Construction

|Activity |Mitigation Measure Implementation |Monitoring Activity |Frequency |Monitoring Responsibility |Budget |

| | | | | |(N) |

|Obtain required Govt. |Submit EIA/ EMP to FMEnv/KEPA |Retain copy of approval |Once |Contractor/ER |N500,000.00 |

|Approvals | | | | | |

|Erection of contractor |Contractor to identify suitable camp site |Retain a record of discussions |After each discussion |Contractor/ER/ET |N150,000/monitoring site visit|

|construction camp |in consultation with local | | | | |

| |community/local government |Retain a record of approval | | | |

| |Contractor obtain approval for camp site | |Once | | |

| |from KASUPDA/Local government | | | | |

|Community consultation |Continue to undertake community |Retain copies of minutes of discussions |After each discussion |Contractor/ER/ET |N150,000.00/visit site |

| |consultation | | | | |

|Materials testing |to include requirement for independent |Retain copy of contracting documents with the |Once |Contractor/ER/ET |N300,000.00/sample |

| |materials testing in contracting documents|requirement |Weekly when materials are | | |

| |to ensure that Contractor complies with |Check record of materials testing |delivered | | |

| |requirements | | | | |

|Operation of Contractor |Inclusion of requirement for regular |Retain copy of contracting documents with the |Once |Contractor/ER |N150,000.00/monitoring site |

|construction camp |watering of camp site and construction |requirement | | |visit |

| |sites in contracting documents | | | | |

| |Contractor to implement approved |Maintain record of implementation activities | | | |

| |Contractor work plan |Daily monitoring |Daily during dry weather | | |

| |submit monthly reports on Contractor |Ensure all complaints are recorded in the |condition | | |

| |implementation of approved work plan and |register | | | |

| |mitigation measures |Maintain a record of working hours |Daily | | |

| |Establish and maintain public complaints |Maintain a record of discussions with local | | | |

| |register |community in relation to requests for | | | |

| |Include the following requirements for |extension of working hours |As required | | |

| |worker facilities in contracting documents|Maintain a record of any agreements for | | | |

| |Adequate numbers of functional bathrooms |extension of working hour | | | |

| |and latrines |Retain copies of contracting documents with |As required | | |

| |Covered rubbish bins for scraps |requirement | | | |

| |Adequately stocked first aid medical kits |Retain copies of contracting documents with |As required |Contractor/ER | |

| |Trained person to provide first aid |requirement | | | |

| |assistance if required |Retain copies of waste disposal dockets | | | |

| |include requirement in contracting |Maintain a photographic record of disposal | | | |

| |documents for Contractor to provide |activities | | | |

| |facilities for disposal of solid and | | | | |

| |liquid wastes |Maintain documentary record of monitoring | | | |

| |Contractor to undertake regular disposal |activities | | | |

| |of solid and liquid wastes | | | | |

| |undertake frequent regular monitoring to | | | | |

| |ensure compliance with requirements | | | | |

|Heavy machinery operation |Ensure contracting documents include |Retain copy of contracting documents on |Once | |N141,375.13/hr |

| |specifications relating to type, weight |project files | | | |

| |and operation of heavy machinery |Include reference in acceptance advice | | | |

| |ensure that acceptance of CCMP includes |Maintain record of inspections and public |Once | | |

| |consideration of heavy machinery operation|complaints | | | |

| |Contractor to operate machinery in | |Weekly | | |

| |accordance with accepted CCMP | | | | |

|Excavation generally |Include requirement in contracting |Maintain photographic and documentary record |Daily | |N150,000/monitoring |

| |document for Contractor to remove and |of Contractor material disposal activities | | |site visit |

| |dispose of surplus material at approved |Retain copy of approved list on project files | | | |

| |sites |Retain copy of contracting documents on | | | |

| |Include the following requirements for |project files | | | |

| |Contractors in the contracting documents: |Retain copy of contracting documents on | | | |

| |Provide temporary services acceptable |project files | | | |

| |standard where required |Maintain duplicate copies record of Contractor| | | |

| |Undertake permanent repair works for |performance | | | |

| |disrupted services within specified times |Maintain photographic and documentary record |Once | | |

| |Provide warning and safety signs in local |of Contractor performance | | | |

| |language at excavation sites | | | | |

| |Provide PPE for site workers | | | | |

| | | | | | |

| | | | | | |

|Management of spills and |Ensure that requirements relating to spill|Retain copy of contracting documents on |Once | |N50,000/truck Load |

|construction debris |management and debris are included in |project files | | | |

| |contracting documents |Maintain photographic and documentary record | | | |

| |Ensure that Contractor addresses spill |of Contractor performance |Daily | |N50,000/landfill fee/truck |

| |management and debris removal as criteria | | | |load |

| |for acceptable Contractor work plan | | | | |

| |Ensure that Contractor to promptly attend | | | | |

| |to any spills | | | | |

| |Ensure that Contractor collects and | | | | |

| |disposes of construction debris in | | | | |

| |designated locations | | | | |

| |Monitor Contractor performance in | | | | |

| |accordance with QA requirements | | | | |

Table 6.3: Environmental Monitoring Criteria

|Component |Parameters |Method |Frequency |Responsible |Remarks |Budget (N) |

|Air quality |Dust |Visual Observation |Everyday during construction |Contractor | | |

| | | | | | | |

| | | | | | | |

| | | | | |FMEnv. limits | |

| |PM, TOC, HCl, HF, SO2, CO, NOX |Ambient air monitoring using standard |Annually or where visual observations| | | |

| |, Hg, Cd, Tl, Sb, As, Pb, Cr, |method of sampling and analysis around|indicate unpleasant scenario | | |N150,000/air sample |

| |Co, Cu, Mn, Ni and V, PCDD/F |the premises | | | |analysis |

|Noise |75dB – Day time |Disturbance/pinch |Everyday during construction |Contractor | | |

| |65dB – Evening | | | |FMEnv. limits |N75,000/monitoring |

| |35dB - Night | | | | |sample |

| |Level |Sensor measurement around the premises|annually | | | |

|Erosion |Top soil movement/ground |Visual assessment |Routinely during construction |Contractor |- | |

| |cutting | | | | | |

|Water Quality |pH, TSS, Cd, Cr, Pb, Hg, |Standard method of sampling and |Where it is established that |Contractor/ Consultant | | |

| |Chlorine, total residual, |analyses |construction caused impact |Regulator | | |

| |Phenols, Total coliform | |Annually | |FMEnv. limits |N150,000/water sample |

| |bacteria, | | | | |analysis (all relevant |

| |Temp, turbidity | | | | |parameters) |

|General Waste |Reduction, |Visual Assessment, General Aesthetics,|Routinely, Daily |Contractor/HSE Officer | | |

|Management |Segregation protocols, |hazard free environment | | | |N50,000/ |

| |proper handling, storage, | | | | |truck load |

| |treatment, and transportation | | | | |N50,000/landfill |

| | | | | | |fee/truck load |

|HSE |Public and Workers Health, |Hazard and risk assessment |Annually | |Maintain records of |N100,000/worker/month |

| | | | | |occupational accidents| |

| | | | | |and diseases and | |

| | | | | |dangerous occurrences | |

| | | | | |and | |

| | | | | |accidents | |

|Health & Safety |Public health & Safety |Hazard assessment |Before Start of work and routinely | |- |N25,000/worker/month |

| |Occupational Health of workers,|Hazard Assessment |Before Start of work and routinely | |- |N50,000/worker |

| | | | | | |month |

Table 6.4: EMP Implementation - Budget

Other Mitigation Activities

|S/No. |Mitigation Activity |Responsible |Time |Cost |Remarks |

|1. |Dust Abatement |SPIU, Contractor |Daily during construction |N150,000/air sample analysis | |

|2. |Capacity Building | |Yearly |N3,000,000/year for all staff | |

|3. |HIV/AIDS Control | |Yearly |N1,000,000/year for all staff | |

6.4 Site Environmental Audit

Site environmental auditing is essentially to ensure that both legal and contractual requirements of the construction contract are complied with. There are contractual environmental protection and pollution control requirements as well as environmental protection and pollution control laws in Nigeria and Kaduna State which the construction activities are required to comply with.

All the works method statements submitted by the contractor to the ER for approval should also be sent to the ET leader for vetting to see whether sufficient environmental protection and pollution control measures have been included.

The ET leader should review the progress and programme of the works to check that relevant environmental laws have been violated, and that any foreseeable potential for violating the laws can be prevented.

The contractor should regularly copy relevant documents to the ET leader so that the checking of works can be carried out. The documents should at least include the updated Work Progress Reports, the updated Works Programme, the application letters for different license/permits under the environmental protection laws, and all the valid license/permit. The site diary should also be available for the ET Leader’s inspection upon his/her request.

On reviewing the document, the ET Leader should advise the ER and the contractor of any non-compliance with the contractual and legislative requirements on environmental protection and pollution control for them to take follow-up actions. If the ET Leader’s review conclude that the current status on license/permit application and any environmental protection and pollution control preparation works may not cope with the works programme or may result in potential violation of environmental projection and pollution control requirements by the works in due course, he should advise the contractor and the ER accordingly.

Upon receipt of the advice, the contractor should undertake immediate action to remedy the situation. The ER shall follow up to ensure that appropriate action has been taken by the contractor in order that the environmental protection and pollution control requirements are fulfilled.

6.5 EMP Organization

The implementation of the EMP requires the involvement of the principal partners. These

include the project proponent or client, the Contractor, the Contractor’s Management Team, the

Engineers Representative/Engineering Supervision Consultant and the Independent

Environmental Consultant. The Kaduna State RAMP has to organize and put these parties in

place in order to ensure the successful and effective implementation of the project EMP.

Although these are meant to work towards achieving the same goal, each has his own role in the

process. These roles are spelt out as follows:

(i) The Project Proponent/Client

The project proponent here is represented by the Project Coordinator. He representing the project (which include Kaduna State). He is responsible for the project environmental performance during its construction and operational phases.

(ii) The Environmental Team

The Environmental Team (ET) is appointed by the Contractor. The team in headed by a leader who is saddled with a wide range of responsibility. His duties include but not limited to the following.

a. Sampling, analysis and evaluation of monitoring parameters with reference to the EIA report and EMP recommendations and requirements;

b. Carry out environmental site surveillance to investigate and audit the contractors’ site practice, equipment and work methodologies with respect to pollution control and adequacy of environmental mitigation implemented;

c. Review the success of EM&A programme to cost-effectively confirm the adequate of mitigation measures implemented;

d. Monitor compliance with environmental protection, pollution prevention and control measures, and contractual requirements;

e. Monitor the implementation of environmental mitigation measures;

f. Audit and prepare audit reports on the environmental monitoring data and site environmental conditions;

g. Complaint investigation, evaluation and identification of corrective measures;

h. Advise to the contractor on environment improvement, awareness, proactive pollution prevention measures;

i. Follow the procedures in the EMP and recommend suitable mitigation measures to the contractor in the case of non-compliance/discrepancies identified. Carry out additional monitoring works within the specified timeframe instructed by the ER; and

j. Liaison with the contractor, and IEC on all environmental performance matters, and timely submission of EM&A reports to the project proponent, IEC and relevant administrative authorities, if required.

(iii) The Contractor

The Contractor’s duties include but not limited to the following:

a. Compliance with relevant environmental legislative requirements;

b. Work within the scope of contractual requirements and other tender conditions;

c. Organize representatives of the construction team to participate in the joint site it sections undertaken by the ET, and undertake any corrective actions instructed by the client and/or IEC;

d. Provide and update information to the ET regarding works activities which may contribute, or be continuing to the generation of adverse environmental conditions;

e. In case of non-compliances/discrepancies, carry out investigation and submit proposals on mitigation measures, and implement remedial measures to reduce environmental impact;

f. Stop construction activities which generate adverse impacts upon receiving instructions from the client/IEC. Propose and carry out corrective actions and implement alternative construction method. If required, in order to minimize the environmental impact;

g. Adhere to the procedures for carrying out compliant investigation; and

h. Take responsibilities and strictly adhere to the guidelines of the EM&A programme and complementary protocols developed by their project staff;

i. The contractor shall read and understand the EMP and implement same as contain there in.

(iv) The Engineer Representative (ER)

The Engineer Representative is generally responsible for overseeing the construction of the project and monitors the works undertaken by the Contractor. His duties include but not limited to the following:

a. Monitor the contractor compliance with contract specifications, including the implementation and operation of environmental mitigation measures and ensure their effectiveness, and other aspects of the EM&A programme;

b. Provide assistance to the ET as necessary in the implementation of the environmental monitoring and auditing programme;

c. Regularly monitor the performance of the ET, verifying monitoring methodologies and results. In case the ER considers that the ET leader or any member of the ET fails to discharge duties or fails to comply with the contractual requirements, instruct the contractor to replace the ET leader or the member of the ET;

d. Instruct the contractor to take actions within a specified timeframe, and carry out additional monitoring, if required, according to the contractual requirements and procedures in Event and Action Plan of EMP in the event of non-compliances or complaints;

e. Supervise the contractor activities and ensure that the requirements inn the EMP and contract specifications or complaints;

f. Instruct the contractor to take actions to reduce impacts and follow the required EMP procedures in case of non-compliance/discrepancies identified;

g. Instruct the contraction to stop activities which generate adverse impacts and/or when the contractor failed to implement the EMP requirements/remedial actions instructed by the ER/IEC;

h. Participate in the joint site inspection undertaken by the ET; and

i. Adhere to the procedures for carrying out compliant investigation.

(v) Independent Environmental Consultant

The Independent Environmental Consultant is a person who can independently and professionally, examine records, processes and procedures relating to the EMP of the project. He should be a person who is familiar with the project works through review of reports, including the EMP. His duties shall include but not limited to the following:

a. Review and audit in an independent, objective and professional manner in all aspects of the EMP;

b. Validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers;

c. Carry out random sample check and audit on monitoring data and sampling procedures, etc;

d. Conduct random site inspection;

e. Audit the EIA recommendations and requirement against the status of implementation of environmental protection measures;

f. Review the effectiveness of environmental mitigation measures and project environmental performance;

g. On as needed basis, verify and certify the environmental acceptability of the construction methodology (both temporary and permanent works), relevant design plans and submissions. Where necessary, the IEC shall seek the least impact alternative in consultation with the designer, the contractor and HPCD;

h. Verify the investigation results of any non-compliance of the environmental quality performance and the effectiveness of corrective measures; and

i. Feedback audit results to the client and ER team according to EMP procedures of non-compliance in the EMP.

(vi) Other Stakeholders

Other stakeholders such as the Federal Ministry of Environment and the Kaduna State Ministry of Environment and Natural Resources are line Ministries which have vital roles to play in the implementation of the EMP. These Ministries are fundamental as lead environmental regulators which oversee compliance with EIA requirements in Nigeria and Kaduna State respectively. Thus the have an important role in the implementation of the ESMP. Similarly, the Kaduna State Ministry of Works and Transport as the line ministry has a vital role to play. The other institutions, on the other hand, come in as and when relevant areas or resources under their jurisdiction or management are likely to be affected.

Most important among their roles include:

• The issues of consent or approval for an aspect of a project;

• Allow impact to a certain extent or impose restrictions or conditions.

They may also have monitoring responsibility or supervisory oversight during construction in an area of concern or interest to them.

Local Level: The Local Government Areas where the projects are located have roles to play in the EMP implementation. They have the duty of overseeing the operations going on within their jurisdictions and it would appropriate fir them to contribute in one way or another. Infact the Local Governments have the responsibility to inform the people about the project.

The Local Clients, District Heads, Village and Ward Heads are local authorities who should be involved at some level in the implementation of the EMP. They can be informed in the case where the contractor contravenes the terms of the EMP.

The Communities of the projects sites should be involved in the EMP implementation, more so, because they are directly involved with workers at the project sites.

vii. The World Bank

The World Bank is a co-financier of the project. One of its major roles is to ensure the timely release of funds for the execution of the project. Since its funds are involved, it should be interested in ensuring that such funds are applied judiciously. This will entail sending missions to Kaduna State periodically to monitor the progress of the project. It will also ensure that all its policies regarding the project design, construction and operation are complied with. It is the duty of the Bank to ensure that all documents and reports relating to the project meet its standard requirements.

6.6 Capacity Development and Training

It is important that the EMP is supported by a well trained staff with the capacity and skills to carry out the duties of monitoring and reporting on the implementation of the EMP. Where such trained staff are not readily available, the project proponent, namely here, the Kaduna State RAMP may draw staff from the Kaduna State Environmental Protection Authority (KEPA) or the Kaduna State Ministry of Environment and Natural Resources. In the absence of both, the project proponent may resort providing training on environmental technical assistance programmes.

The EMP shall be part of the terms of reference for all contractors, sub-contractors and suppliers. All contractors, sub-contractors and suppliers have to give some assurance that they understand the EMP and that they will undertake to comply with the conditions therein. Therefore, Contractors have the responsibility to ensure that all those people involved in the project are aware of and familiar with the environmental requirements for the project (this includes sub-contractors, casual labour, etc.).

Generally, it is expected that all senior and supervisory staff members shall familiarize themselves with the full contents of the EMP. They shall know and understand the specifications of the EMP and shall be able to assist other staff members in matters relating to the EMP.

6.7 Non Compliance of the EMP

Difficulties may be encountered with carrying out mitigation measures that could result in future non-compliance. The responsible person shall put in place measures to motivate staff members to comply with the EMP, and to deal with acts of non-compliance, or malicious damage to the environment by any staff member.

6.8 Environmental Emergency Procedures

i. Environmental emergence procedures relate primarily to the event of accidental leaks, spills or emissions. Events related to adverse weather conditions should be addressed through the Project Activity Safety Plan (PASP) as part of the Contractor’s Safety Plan, which should be submitted to the ER before commencement of project construction works. The Safety Plan shall be reviewed on regular basis and updated if necessary. The PASP shall include procedures such as the prevention of slope slide/soil erosion during the rainfall season.

ii. In the event that accidental leakage or spillage of diesel/chemicals/chemical wastes takes place, standard response procedures should be followed immediately by the contractor such as:

• The person who has identified the leakage/spillage shall immediately check if anyone is injured and shall then inform the contractor, ET and ER;

• The contractor shall ensure any injured persons are treated and assess what has spilled/leaked;

• Should the accidents/incidents generate serious environmental pollution or in the option of ER, has the potential of resulting in serious environmental pollution problems (e.g spillage/leakage of toxic or chemicals, large scale spillage/leakage, or spillage/leakage into the nearby water bodies which are used for irrigation/portable water), the ER immediate inform Environmental Protection Authority and the Kaduna State Water Board;

• In such cases, the contractor shall take immediate action to stop the spillage/leakage and divert the spilled/leaked liquid to a nearby non-sensitive areas;

• The contractor shall arrange maintenance staff with appropriate protective clothing to clean up the chemicals/chemical waste. This may be achieved through soaking with sawdust (if the quantity of spillage/leakage is small), or sand bags (if the quantity is large); and/or using a shovel to remove the topsoil (if the spillage/leakage occurs on bare ground); and

• Depending on the nature and extent of the chemical spill, evacuation of the activity/site may be necessary.

iii. Spilled chemicals must not be flushed to local surface drainage systems. Instead, sawdust or sandbags used for clean-up and removed contaminated soil should be disposed of by following the procedures for chemical waste handling and disposal already described.

iv. The possibility exists for environmental emergencies of an unforeseen nature to occur during the course of the construction and operational phases of the project. By definition, the nature of such emergencies cannot be known. Therefore, the contractor should respond on a case-by-case basis to such emergencies and should initiate event-specific measures in terms of notifications and reactions.

v. The contractor should prepare a report on the incident detailing the accident, clean-up actions taken, any pollution problems and suggested measures to prevent similar accidents from happening again in future. The incident report should then be submitted to the ER, IEC for review and keep in the records. The incident report should also be submitted to EPB, if required.

vi. The contractor should ensure that all site staff members are aware of the above emergence response procedures through training.

6.9 Environmental Complaints

Complaints may arise in the course of the project preparation or construction. Serious complaints should be referred to the ET Leader for carrying out complaint investigation procedures. The ET leader should undertake the following procedures upon receipt of complaint:

i. Log complaint and date of receipt onto the complaint database and inform the ER and/or IEC immediately;

ii. Investigate the complaint to determine its validity, and to assess whether the source of the problem is due to works activities;

iii. If a complaint is valid and due to works, identify mitigation measures;

iv. If mitigation measures are required, advice the Contractors accordingly;

v. Review the contractor’s response on the identified mitigation measures, and the updated situation;

vi. If the complaint is transferred from EPB, submit interim report to EPB on status of the complaint investigation and follow-up action within the time frame assigned by EPB;

vii. Undertake additional monitoring and audit to verify the situation if necessary, and review that any valid reason for complaint does not recur;

viii. Report the investigation results and the subsequent actions to the source of complaint for responding to complainant( if the source of complaint is EPB, the results shall be reported within the time frame assigned by EPB); and

ix. Record the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.

x. During the complaint investigation work, the Contractor and ER should cooperate with the ET Leader in providing all the necessary information and assistance for completion of the investigation. If mitigation measures are identified in the investigation, the Contractor shall promptly carry out the mitigation. The ER should ensure that the measures have been carried out by the Contractor. A copy of complaint log is shown in Annex D.

xi. A flow chart of the complaint response procedures is shown in Annex C.

APPENDIX 1.1

List of Prioritized River Crossings – Structures Sizes and Contract Lot

APPENDIX 1.1

RURAL ACCESS MOBILITY PROJECT (RAMP)

List of Prioritized River Crossings – Structures Sizes and Contract Lot 1

|L.G. A. |Route/Site |Easting |Northing |Structures Sizes |

| |U/Tata /Makoyi |370007 1254780 |2Nos. 2m x 2m box culvert |

|KUDAN |Nasarawan Kudan / Randa |365486 1252554 |2Nos. 900mm Ø pipe |

| |Zabi / Kudan |360897 1249919 |Minor repair and protection work |

| |Garu / Lafia |359452 1244042 |2Nos. 2m x 2m box culvert |

| |U/Tata / Makoyi |370231 1253614 |1No. 1200mm Ø pipe |

| |U/Samaila / Doka |367313 1255324 |2Nos. 2.0m x 2.0m box culvert |

| |K/Wali South / Taba |371102 1250211 |3Nos. 1.5m x 2.0m box culvert |

| |Gidan Sharu / Mayere |391957 1251488 |3Nos. 1.5m x 2.0m box culvert |

|MAKARFI |Mayere / Ang. Lili |391449 1250374 |3Nos. 900mm Ø pipe |

| |Abamalam / Nasarawa Doya |378679 1240793 |2Nos. 1.5m x 1.5m box culvert |

| |Gangarau / Makaurata |385033 1262765 |3Nos. 1200mm Ø pipe |

| |Feleke / Dan Ayamaka |375755 1251101 |Vented drift 7.5m x 22m with 12Nos. 900mm Ø pipe |

| |Feleke / Dan Ayamaka |374789 1252117 |4Nos. 1.5m x 2m box culvert |

| |Maitukurwa Bridge Mayere – Ang. Karoti |393189 1250412 |4Nos. 1200mm Ø pipe |

| |Malikanchi / Hayin Turawa |422753 1233645 |4Nos. 1.5m x 2.0m box culvert |

|IKARA |Gimbawa / Asakale |421939 1238204 |2Nos. 2m x 2m box culvert |

| |Kurmin Kogi / Dallawal |410054 1239383 |3Nos. 1.5m x 1.5m box culvert |

| |Kargo Bridge |426570 1237374 |3Nos. 2.0m x 3.0m box culvert |

| |Saulawa / Janmaramara |400263 1255925 |2Nos. 1.5m x 1.5m box culvert |

| |Janmaramara / Saulawa |401131 1254489 |2Nos. 1.5m x 1.5m box culvert |

| |Kapo Pala / Gidan Guza - Garki |436486 1226756 |2Nos. 2m x 2m box culvert |

| |T/Kaya – Madarzai-Sabongari – Turawa |396417 1223176 |2Nos. 2m x 2m box culvert |

|SOBA |Lungu – Takalafia – Rahama |406816 1218379 |Additional 4m long 2Nos. 2m x 2m box culvert |

| |Kinkiba-Zanko Tamba |381594 1210137 |2Nos. 1.5m x 1.5m box culvert |

| |Tashan Adamu – Gedege |424623 1227406 |4Nos. 2m x 3m box culvert |

|KUBAU |Pambegwa – Dan Maliki |424499 1173647 |3Nos. 3.5m x 3.5m box culvert |

| |Anhau – Haskiya – Ung Gata |435836 1216434 |2Nos. 900mm Ø pipe |

| |Kanar Mai Molo – Banki |445165 1196886 |1No. 2m x 3m box culvert |

| |Mah-Nasarawa Mah |416488 1224193 |2Nos. 2m x 2m box culvert |

| |Kanar mai Molo-Leren Dutse |439869 1199770 |Vented drift with 4Nos. 900mm Ø pipe |

| |Kanar mai Molo-Leren Dutse |442760 1197615 |Vented drift with 4Nos. 900mm Ø pipe |

RURAL ACCESS MOBILITY PROJECT (RAMP)

List of Prioritized River Crossings – Structures Sizes and Contract Lot 2

|L.G. A. |Route/Site |Easting |Northing |Structures Sizes |

| |Kuyit |433867 1063758 |2Nos. 1200mm Ø pipe |

|KAURA |Mikunat Sabon Gari - Zakan |445853 1067338 |3Nos. 3m x 3m box culvert |

| |Bailey Fadan Daji - Chenchichuong |432560 1063082 |Replace timber deck |

| |Dusaigada |436265 1063678 |2- 10.0m span RC bridge (20m) |

| |Swanta - Kongu |434886 1062880 |3Nos. 2.5m x 3m box culvert |

| |Bailey Fadan Daji - Chenchichuong |430907 1064189 |2Nos. 1.5m x 3m box culvert |

| |Bailey Fadan Daji - Chenchichuong |429534 1064795 |2Nos. 1.5m x 1.5m box culvert |

| |Koko – Kussom - Mada |408919 1027673 |Vented drift with 6Nos. 1200mm Ø pipes |

|JAMA’A |Ungwa Gwandara Jagindi |415395 1032080 |2Nos. 1200mm dia pipe culvert |

| |Godogodo - Nindem |427517 1042413 |2Nos. 3.5m x 3.5m box culvert |

| |U Pa – Bakin Kogi - Kaninkon |420417 1049542 |2Nos. 1.5m x 1.5m box culvert |

| |Ungwa Fari - Rafindadi |420895 1051644 |2Nos. 3m x 3m box culvert |

| |Gidan Waya – Hayin Gada |431993 1046012 |Replace RC deck 5 span |

| |Antor – Gwanigu Road |457992 1033377 |Vented drift with 10Nos. 900mm Ø pipes |

|SANGA |Agom Road |433195 1017154 |3Nos. 1.5m x 1.5m box culvert |

| |Mayir – Tari-Ninche |454716 1021949 |3Nos. 3.5m x 3.5m box culvert |

| |Mayir – Tari-Ninche |453841 1021181 |2Nos. 2m x 3m box culvert |

| |Antor – Gwanigu Road |458591 1033840 |2Nos. 1.5m x 1.5m box culvert |

| |Abu - Kanri |449209 1003113 |Open drift 7.5m x 8m with 4Nos. 900mm Ø pipes |

| |Mayir – Tari-Ninche |452312 1018978 |3Nos. 3m x 3m box culvert |

RURAL ACCESS MOBILITY PROJECT (RAMP)

List of Prioritized River Crossings – Structures Sizes and Contract Lot 3

|L.G. A. |Route/Site |Easting |Northing |Structures Sizes |

| |Udawa – Rimi |274121 1162941 |3 cell 2.5m x 2.5m box culvert |

|CHIKUN |Udawa - Rimi |273665 1164473 |2Nos. 2m x 3m box culvert |

| |Udawa - Rimi |273728 1165457 |3Nos. 2m x 2.5m box culvert |

| |Udawa - Rimi |273413 1170568 |2Nos. 2m x 2m box culvert |

| |Udawa - Rimi |273519 1172308 |2Nos. 2m x 2m box culvert |

| |Udawa – Rimi |273634 1173881 |2Nos. 1.5m x 1.5m box culvert |

| |Maraba Iri-Iri Station Maro |373299 1172308 |2- 112.5m span RC bridge (25m) |

|KAJURU |Danbagudu - Afago |367782 1142645 |3Nos. 1.5m x 1.5m box + 2Nos. 1200mm Ø pipe |

| |Fadama Kororo-Kutura-Maro |356324 1146499 |Increase length of 2Nos. 900mm Ø pipe by 4.5m |

| |U. Rana Kufana – Rafin Kunu |362651 1138382 |3Nos. 2m x 2m box culvert |

| |Maraban Kajuru - Tantatu |350395 1135195 |2Nos. 1.5m x 1.5m box culvert |

| |Maraban Kachia – Aduma |392170 1117181 |2- 112.5m span RC bridge (25m) |

RURAL ACCESS MOBILITY PROJECT (RAMP)

List of Prioritized River Crossings – Structures Sizes and Contract Lot 4

|L.G. A. |Route/Site |Easting |Northing |Structures Sizes |

| |Kwalakwangi |276947 1253360 |3Nos. 2m x 2m box culvert |

| |Kwalakwangi |273894 1256548 |4Nos. 2m x 2m box culvert |

|BIRNIN GWARI |Kwalakwangi |276841 1253401 |3 rows 1200mm Ø pipe |

| |Kwalakwangi |272891 1256521 |1 Cell of 1.5m x 1.5m box culvert |

| |Kwalakwangi |277392 1253410 |2Nos. 2m x 2m box culvert |

| |Rafin Gungume |192108 1158062 |3 Cell 2m x 2m box culvert + 4Nos. 1200mm Ø pipe relief |

| |Ang Bagwai / Alh. Babandi |341722 1253540 |2Nos. 1.5m x 1.5m box + 1200 Ø PC |

| |Ang. Lelle Doka / Dan Magaji |330940 1243403 |3Nos. 1.5m x 1.5m box culvert |

| |Matsiyach Raf / Ganuwa |341879 1249850 |4Nos. 1.5m x 1.5m box culvert + 2Nos. 1200 Ø PC |

|GIWA |Nasara / Balabus |327959 1251409 |2Nos. 1200mm Ø pipe culvert |

| |Gangara / Dundubus |330756 1256583 |5Nos. 2m x 2m box culvert |

| |Sabon Fili / Bula |297102 1211795 |3Nos. 2m x 2m box culvert |

| |Sabon Fili / Bula |298324 1216829 |6Nos. 1200mm Ø pipe relief |

| |Hayin Danmani – Gadan Toro Toro |327800 1165201 |2Nos. 3.5m x 3.5m box culvert |

| |Rigachukun – V/Tatau - Zaure |373347 1168428 |2Nos. 2.5m x 2.5m box culvert |

| |Rigachukun – V/Tatau - Zaure |336705 1174481 |2Nos. 900mm Ø pipe culvert |

|IGABI |Tsohon Telwa – Farin Ruwa |348243 1203582 |2Nos. 1.5m x 1.5m box culvert |

| |Farin Ruwa - Kuzizigi |348766 1204837 |2Nos. 1.5m x 1.5m box culvert |

| |Kemfa – A/Dano – Baku – Sayawa Wadaza |385412 1202658 |2Nos. 2m x 2m box culvert |

| |Birnin Yero – Kwarau – Tami |330420 1191622 |10Nos. 900mm Ø pipe @ 10m c/c |

| |Baban Abu-R/Gora |335622 1218199 |Vented drift 7.5m x 15m with 10Nos. 900mm Ø pipes |

| |Dakace –R/Gura |350415 1216770 |Vented drift 7.5m x 15m with 10Nos. 900mm Ø pipes |

| |Dambo – Rafin Giwa |366941 1225244 |3Nos. 1.5m x 1.5m box culvert |

|ZARIA |K/Doka – Magume |358996 1225496 |2Nos. 900mm Ø pipe culverts |

| |Rafin Albasa – Gwargwaje |356404 1221768 |2Nos. 1.5m x 1.5m box culvert |

| |Zura – Dorayi |355914 1217951 |3Nos. 1.5m x 2m box culvert |

| |Zura – Dorayi |355214 1216951 |Vented drift 8.2m x 15m with 10Nos. 900mm Ø pipes |

RURAL ACCESS MOBILITY PROJECT (RAMP)

List of Prioritized River Crossings – Structures Sizes and Contract Lot 5

|L.G. A. |Route/Site |Easting |Northing |Structures Sizes |

| |Kwassam – Kibangari |426342 1122759 |Bailey bridge – Need 74m timber deck & approaches |

|KAURU |Kamaru – Kiza Koro |454454 1084452 |1No. 900mm Ø pipe culvert |

| |Pari - Rahama |449493 1087306 |Vented drift with 12Nos. 1200mm Ø pipes |

| |Kaura Dawa - Ibada |417195 1171756 |3Nos. 2m x 3m box culvert |

| |Kaura Dawa - Ibada |417479 1170991 |3Nos. 1.5m x 2.0m box culvert |

| |Sabon Gari – Kauru – Makau Saleh |410864 1161725 |2Nos. 1.5m x 2.0m box culvert |

| |Sabon Gari – Kauru – Makau Saleh |411120 1163203 |Vented drift with 12Nos. 1200mm Ø pipes |

| |Maraba Warsa – Piti |454917 1114948 |1No. 1.5m x 1.5m box culvert |

|LERE |Gure Rewa |448642 1146810 |Recontruction of 2 abutments & pier and re errection |

| |Garu – Baban Fadama Road |455043 1124686 |3Nos. 900mm Ø pipe culvert |

| |Mararaba – Arande – Warsa Piti |453651 1116286 |2Nos. 1200mm Ø pipe culvert |

| |Kayarda – Goron Dutse |455503 1163756 |2Nos. 900mm Ø pipe |

| |Maigamo – Jankasa |431535 1179517 |3Nos. 2m x 3m box culvert |

| |Kayarda – Goron Dutse |455320 1164215 |3Nos. 2.5m x 2.5m box culvert |

| |Zonkwa – Wadon |424247 1079762 |1No. 2m x 2m box culvert |

|ZANGO KATAF |Kamantan - Ashafa |410491 1085638 |Replace failed pier and timber deck |

| |Kabam – Gidan Maga |408437 1071524 |3Nos. 1.5m x 1.5m box culvert |

| |Zaman Dabo – Doka 2 |442705 1087983 |3Nos. 1.5m x 1.5m box culvert |

| |Zaman Dabo – Doka |442423 1088006 |Deck rehabilitation |

| |Kamantan – Ashafa Road |410331 1085507 |2Nos. 1200mm Ø pipe culvert |

| |Zonkwa – Ramai Road |420912 1082491 |1No. 2m x 3m box culvert |

RURAL ACCESS MOBILITY PROJECT (RAMP)

List of Prioritized River Crossings – Structures Sizes and Contract Lot 6

|L.G. A. |Route/Site |Easting |Northing |Structures Sizes |

| |Nasarawa – Adege |397676 1095785 |Vented drift with 12Nos. 1200mm Ø pipes |

|KACHIA |K/Mazuga - Nasarawa |396804 1094489 |Vented drift with 10Nos. 1200mm Ø pipes |

| |Doka - Akilibu |333707 1088776 |Vented drift 40m x 7.5m with 15Nos. 900mm Ø pipes |

| |Mai Ido |366942 1097312 |3Nos. 2m x 2m box culvert |

| |Yarbung - Magajiram |397107 1072834 |2Nos. 1.5m x 1.5m box culvert |

| |Dangalmi |395903 1068974 |2Nos. 2.5m x 2.5m box culvert |

| |Insane – Itah |381056 1095450 |3Nos. 2.5m x 2.5m box culvert |

| |Gidan Kundi- Shadalafiya - Inkojo |370863 1043021 |2Nos. 2m x 2.5m box culvert |

|KAGARKO |Gidan Kundi- Shadalafiya - Inkojo |371005 1042776 |1No. 1.5m x 1.5m box culvert |

| |Kubacha – Kushe Fada |369952 1044710 |Vented drift 12Nos. 1200mm Ø pipes |

| |Kubacha – Kushe Fada |369994 1046581 |2Nos. 1.5m x 1.5m box culvert |

| |Kubacha – Kushe Fada |369807 1047666 |2Nos. 2m x 3m box culvert |

| |Kushe Fada Kafarma - Kasabere Gidan Kundi Shadalafiya |368273 1051673 |2Nos. 2m x 3m box culvert |

| |Inkojo |372105 1042045 |2- 10.0m span RC bridge (20m) |

| |Sambam – Ungwa Zuma - Chori |395706 1048688 |2Nos. 2m x 2m box culvert |

|JABA |Chori Makama – K. Musa |392935 1058272 |Replace timber deck |

| |Sambam – Ungwa Zuma - Chori |395530 1049328 |2Nos. 1.5m x 1.5m box culvert + 2Nos. 900mm Ø pipes |

| |Daddu – Kurmi Zomo - Kyari |405422 1057817 |2Nos. 2.5m x 2.5m box culvert |

| |Daddu – Tsakiya Road |406394 1056447 |2Nos. 2.0m x 2.5m box culvert |

| |Keffi - Kaf |392438 1042068 |2Nos. 2m x 2m box culvert |

| |Sambam – Ungwa Zuma – Chori |396598 1045709 |25m Vented drift with 10Nos. 900mm Ø pipe |

Source: Environmental Screening Report (2008)

APPENDIX 2.1

CATEGORY I PROJECT

MANDATORY STUDY ACTIVITIES

1. AGRICULTURE/AGRO-ALLIED

2. FISHERIES

3. FORESTRY

4. INDUSTRY(MANUFACTURING)

5. FOOD, BEVERAGES AND TOBACCO PROCESSING

6. INFRASTRUCTURE

7. PORTS

8. HOUSING

9. AIRPORT

10. DRAINAGE AND IRRIGATION

11. RAILWAYS

12. TRANSPORTATION

13. RESORT AND RECREATIONAL DEVELOPMENT

14. POWER GENERATION AND TRANSMISSION

15. PETROLEUM

16. MINING

17. QUARRIES

18. WASTE TREAMENT AND DISPOSAL

19. WATER SUPPLY

20. LAND RECLAMATION

21. BREWERY

APPENDIX 5.1

Environmental and Social Clauses

Appendix 5.1: Environmental and Social Clauses

Objective

This Clause/guide provides operational instructions on how to integrate environmental and social actions associated with the execution of RAMP Project River Crossings. It is neither a legal document nor a book of recipes to be followed mechanically. However, it is rather a set of instruments and options from which road authorities, consulting engineers and contractors can choose relevant sections to their works and contracts.

1.0 General

a) The Contractor shall comply with the Environmental Management Plan (EMP) for the works he is responsible for and to which this clause is added as Appendix. The Contractor shall inform himself about the content of the EMP, and prepare his work strategy and plan to fully take into account relevant provisions of the EMP.

b) The Contractor shall prepare method statements indicating the period within which he /she shall maintain status on site after completion of civil works to ensure that significant adverse impacts arising from such works have been appropriately addressed.

c) The Contractor shall adhere to the proposed activity implementation schedule and the monitoring plan/strategy to ensure effective feedback of monitoring information to project management so that impact management can be implemented properly, and if necessary, adapt to changing and unforeseen conditions.

d) The Contractor shall implement all measures necessary to avoid undesirable adverse environmental and social impacts wherever possible, restore work sites to acceptable standards, and abide by any environmental performance requirements specified in an EMP.

e) If the Contractor fails to implement the approved EMP after written instruction by the Engineer Representative (ER) to fulfil his obligation within the requested time, the Owner reserves the right to arrange through the ER for execution of the missing action by a third party on account of the Contractor

f) Besides the regular inspection of the sites by the Engineer Representative (ER) for adherence to the contract conditions and specifications, the Owner may appoint an Inspector to oversee the compliance with these environmental conditions and any proposed mitigation measures. The Kaduna State Environmental Protection Authority (KEPA), Federal Ministry of Environment, or other relevant stake holders may carry out similar inspection duties. In all cases, as directed by the ER, the Contractor shall comply with directives from such inspectors to implement measures required to ensure the adequacy of rehabilitation measures carried out on the bio-physical environment and compensation account of the Contractor.

2.0 Dust Abatement

a) The contractor shall minimize the effect of dust on the surrounding environment resulting from earth mixing sites, vibrating equipment, temporary access roads, etc. to ensure safety, health and the protection of workers and communities living in the vicinity of dust producing activities.

b) During the performance of the work and any operations appurtenant thereto, the contractor shall carry out proper and efficient measures, such as sprinkling with water or other means, whenever necessary to reduce the dust nuisance, and to prevent dust which has originated from his operations from damaging crops, cultivated fields, and dwellings or causing a nuisance to persons. The contractor will be held liable for any damage resulting form dust originating from his operations.

3.0 Noise Due to Construction Activities

The contractor shall ensure the noise levels emanating from machinery, vehicles and noisy construction activities (e.g. excavation, blasting) are kept at a minimum for the safety, health and protection of workers within the vicinity of high noise levels and nearby communities. The national noise limit standard for the residential area in day time is 55 dB while at night is 45dB.

4.0 River, Stream and Natural Channels obstruction

a) The contractor shall ensure the existing water flow regimes in rivers, streams and other natural or irrigation channels are maintained and/or re-established where they are disrupted due to works being carried out.

b) The contractor shall take all possible steps to prevent pollution of streams, rivers and other natural water bodies/reservoirs.

c) Oils, lubricants and waste water used or produced during the execution of works will not be released directly into rivers, streams, irrigation channels and other natural water bodies/reservoirs without prior treatment and also ensure that stagnant water in uncovered burrow pits is treated in the best way to avoid creating possible breeding grounds for mosquitoes.

5.0 Quarrying, Earth Burrowing, etc.

a) Prevent and minimize the impacts of quarrying, earth burrowing, piling and building of temporary construction camps and access roads on the bio physical environment, including protected areas and arable lands, local communities and their settlements. In as much as possible restore/rehabilitate all sites to acceptable standards.

b) At the end of the construction phase, all construction sites shall be landscaped and rehabilitated to acceptable standards. The affected areas shall be first landscaped, dressed with topsoil and covered with tree planting, field sods or grass seeding.

6.0 Protection of Archaeological and Historical Sites

a) Upon discovery of ancient heritage, relics or anything that might be or is believed to be of archaeological or historical importance during the execution of works, immediately suspend activity and report such findings to the SE so that the National Museums and Monuments Board may be expeditiously contacted for fulfillment of the measures aimed at protecting such historical or archaeological resources.

b) The contractors shall take the necessary measures to prevent any person or equipment that may damage the article or things and shall provide barricades, fences, and signals and, if necessary, protect against atmospheric agents, as directed by the engineer, also guard service may be required by the engineer.

c) The Engineer Representative shall take the following measures:

• Notify the National Museums and Monuments Board

• Request that a representative make a site inspection;

• Cessation of work in the vicinity of the find until the visit of the representative; and

• Decision by the National Museums and Monuments Board on possible salvage or excavation within 48-72-hours of notification.

7.0 Vegetation and Wildlife

a) Discourage construction workers from engaging in the exploitation of natural resources such as hunting, fishing, and collection of forest products or any other activity that might have a negative impact on the social and economic welfare of the local communities.

b) The contractor shall care, in planning, constructing, maintaining and operating temporary works such as camps, roads, spoil, stockpile and construction facilities areas, to avoid unnecessary damage to areas of particular environmental interest, such as patches of remaining forest, valuable trees and erosion of sensitive areas, as well as areas in which the presence of wildlife has been noted.

c) In case some part of a forest or single trees have to be removed, or where erosion problems that may affect some portion of the permanent or temporary works are expected, and in any case where in the engineer's opinion it is beneficial for land conservation, the contractor may be required to carry out landscaping, seeding and planting of trees, as well as executing drainages and water control works according to the prescriptions contained in the pertinent sections of these specifications.

d) No valuable trees or crops shall be damaged or removed by the contractor during the execution of the works without the prior consent of the engineer.

e) Hunting in the proximity of camps and facilities and in general in the project area is strictly prohibited, even if allowed by local rules or regulation in force in Kaduna and/or in the project region.

8.0 Use of Materials

The contractor, in as much as possible, shall use local materials to avoid importation of foreign material and long distance transportation.

9.0 Worksite/Camp Site Waste Management

a) All vessels (drums, containers, bags, etc.) containing oil/fuel/surfacing materials and other hazardous chemicals shall be banded in order to contain spillage. Used oil and hydraulic fluid generated on the construction sites must be collected in a closed container and stored temporarily in a safe place and sent to an authorized recycling depot.

b) All drainage and effluent from storage areas, workshops and camp sites shall be captured and treated before being discharged into the drainage system in line with applicable government water pollution control regulations.

c) The contractor shall take all possible steps to prevent pollution of streams, rivers, and other water supplies, at or in the vicinity of the site and shall comply with applicable laws, orders and regulations in force in Kaduna concerning the control and abatement of water pollution.

d) Entry of runoff to the site shall be restricted by constructing diversion channels or holding structures such as banks, drains, dams, etc. to reduce the potential of soil erosion and water pollution.

e) Construction waste shall not be left in stockpiles along the road, but removed and reused or disposed of on a daily basis.

f) If disposal sites for clean spoil are necessary, they shall be located in areas, approved by the ER, for landfill and where they will not result in material being easily washed into drainage channels. Whenever possible, spoil materials should be placed in low lying areas and should be compacted and dressed with top soil and then planted with species indigenous to the locality.

g) The contractor shall provide all sanitary facilities (e.g. garbage collection and disposal, drinking water facilities, etc.) in construction workers' camps.

10.0 Material Excavation and Deposit

a) The Contractor shall obtain appropriate licenses/permits from relevant authorities to operate quarries or burrow areas.

b) The location of quarries and burrow areas shall be subject to approval by relevant local and national authorities, including traditional authorities if the land on which the quarry or burrow areas fall in traditional land.

c) New extraction sites:

• Shall not be located in the vicinity of settlement areas, cultural and historical sites, wetlands or any other valued ecosystem component, or on high or steep ground or in areas of high scenic value.

• Shall not be located in archaeological areas. Excavations in the vicinity of such areas shall proceed with great care and shall be done in the presence of government authorities having a mandate for their protection.

• Shall not be located in forest reserves. However, where there are no other alternatives, permission shall be obtained from the appropriate authorities and an environmental impact study shall be conducted.

• Shall be rehabilitated. Areas with minimal vegetation cover such as flat and bare ground, or areas covered with grass only or covered with shrubs less than 1.5m in height, are preferred.

• Shall have clearly demarcated and marked boundaries to minimize vegetation clearing and to avoid any unnecessary damage on other resources.

d) Vegetation clearing shall be restricted to the area required for safe operation of construction work. Vegetation clearing shall not be done more than two months in advance of operations.

e) Stockpile areas shall be located in areas where trees can act as buffers to prevent dust pollution. Perimeter drains shall be built around stockpile areas. Sediment and other pollutant traps shall be located at drainage exits.

f) The Contractor shall deposit any excess material in accordance with the principles of these general conditions, and any applicable EMP, in areas approved by local authorities and/or the ER.

g) Areas for depositing hazardous materials such as contaminated liquid and solid materials shall be approved by the SR and appropriate local and/or national authorities before the commencement of work. Use of existing, approved sites shall be preferred over the establishment of new sites.

11.0 Rehabilitation and Soil Erosion Prevention

a) To the extent practicable, the Contractor shall rehabilitate the site progressively so that the rate of rehabilitation is similar to the rate of construction.

b) Always remove and retain topsoil for subsequent rehabilitation. Soils shall not be stripped when they are wet as this can lead to soil compaction and loss of structure.

c) Topsoil shall not be stored in large heaps. Low mounds of no more than 1 to 2m high are recommended.

d) Re-vegetate the stockpiles with recommended grass species to protect the soil from erosion, discourage weeds, and maintain an active population of beneficial soil microbes.

e) Locate stockpiles where they will not be disturbed by future construction activities.

f) The contractor shall reinstate natural drainage patterns where they have been altered or impaired.

g) The contractor shall collect toxic materials from construction areas and keep them protected in designated sites until proper disposal. Backfill excavated areas with soils or overburden that is free of foreign material that could pollute groundwater and soil.

h) Identify potentially toxic overburden and screen with suitable material to prevent mobilization of toxins.

i) Ensure reshaped land is formed so as to be inherently stable, adequately drained and suitable for the desired long-term land use, and allow natural regeneration of vegetation.

j) Minimize the long-term visual impact by creating landforms that are compatible with the adjacent landscape.

k) Minimize erosion by wind and water both during and after the process of reinstatement.

1) Compacted surfaces shall be deep ripped to relieve compaction unless subsurface conditions dictate otherwise.

m) Re-vegetate with plant species that will control erosion, provide vegetative diversity and, through succession, contribute to a resilient ecosystem. The choice of plant species for rehabilitation shall be done in consultation with local research institutions, the Forestry Department, and the local people.

12.0 Water Resources Management

a) The Contractor shall, at all costs, avoid conflicting with water demands of local communities.

b) Abstraction of both surface and underground water shall only be done with the consultation of the local community and after obtaining a permit from the Water Resources Commission.

c) Abstraction of water from wetlands shall be avoided. Where necessary, permission has to be obtained from relevant authorities.

d) No construction water containing spoils or site effluent, especially cement and oil, shall be allowed to flow into natural water drainage courses.

e) Waste water from washing out of equipment shall not be discharged into water courses without pre treatment.

f) Site spoils and temporary stockpiles shall be located away from the drainage system, and surface runoff shall be directed away from stockpiles to prevent erosion.

13.0 Traffic Management

a) Location of access roads shall be done in consultation with the local community especially in important or sensitive environments. Access roads shall not traverse wetland areas.

b) Upon the completion of civil works, all access roads shall be ripped and rehabilitated.

c) Access roads shall be watered regularly to suppress dust emission

14.0 Disposal of Unusable Elements

a) Unusable materials and construction elements such as electro-mechanical equipment, pipes, accessories and demolished structures will be disposed of in a manner approved by the ER. The Contractor has to agree with the ER which elements are to be surrendered to the Client's premises, which will be recycled or reused, and which will be disposed of at approved landfill sites.

b) Unsuitable and demolished elements shall be dismantled to a size fitting on ordinary trucks for transport.

15.0 Repair of Private Property

a) Should the Contractor, deliberately or accidentally, damage private property, he shall repair the property to the owner's satisfaction and at his own cost. For each repair, the Contractor shall obtain from the owner a certificate that the damage has been repaired satisfactorily in order to indemnify the Client from subsequent claims.

b) In cases where compensation for inconveniences, damage of crops etc. are claimed by the owner, the Client has to be informed by the Contractor through the ER. This compensation is in general settled under the responsibility of the Client before signing the Contract. In unforeseeable cases, the respective administrative entities of the Client will take care of compensation.

16.0 Contractor's Environment, Health and Safety Management Plan (EHS-MP)

Within 6 weeks of signing the Contract, the Contractor shall prepare an EHS-MP to ensure the adequate management of the health, safety, environmental and social aspects of the works, including implementation of the requirements of these general conditions and any specific requirements of an EMP for the works. The Contractor's EHS-MP will serve two main purposes:

a) For the Contractor, for internal purposes, to ensure that all measures are in place for adequate EHS management, and as an operational manual for his staff.

b) For the Client, supported where necessary by ER, to ensure that the Contractor is fully prepared for the adequate management of the EHS aspects of the project, and as a basis for monitoring of the Contractor's EHS performance. The Contractor's EHS-MP shall provide at least:

• A description of procedures and methods for complying with these general environmental management conditions, and any specific conditions specified in an EMP;

• A description of specific mitigation measures that will be implemented in order to minimize adverse impacts;

• A description of all planned monitoring activities (e.g. sediment discharges from burrow areas) and the reporting thereof; and

• The internal organizational, management and reporting mechanisms put in place.

The Contractor's EHS-MP will be reviewed and approved by the Client before start of the works. This review should demonstrate if the Contractor's EHS-MP covers all of the identified impacts, and has defined appropriate measures to counteract any potential impacts.

16.1. Health and Safety

a) In advance of the construction work, the Contractor shall mount an awareness and hygiene campaign. Workers and local residents shall be sensitized on health risks particularly of AIDS.

b) Adequate road signs to warn pedestrians and motorists of construction activities, diversions, etc. shall be provided at appropriate points.

c) Construction vehicles shall not exceed a maximum speed limit of 40km per hour.

16.2. Traffic Safety

a) Ensure public safety, and meet traffic safety requirements for the operation of work to avoid accidents.

b) The contractor shall be responsible for the safety along the roads related to the site, and he shall take all necessary precautions for the protection of the work and the safety of the public on the roads affected by his activities.

c) Roads subject to interference by the work shall be kept open or suitable detours shall be provided and maintained by the contractor, who shall provide, erect, and maintain all necessary barricades, suitable and sufficient flashlights, flagmen, danger signals, and signs.

d) The contractor shall submit his weekly activities schedule and the locations of his work along the existing public roads to the authorities concerned, and obtain all necessary approvals prior to commencement of the respective work.

e) At the road crossings or in heavy traffic locations, the contractor shall carry out the work within the working hours as directed by the engineer, and after the completion of the work he shall immediately make the necessary backfill and pavement at the crossings.

f) The contractor shall provide temporary passes and bridges to give an access to the existing villages, houses, etc., to the satisfaction of the engineer and the authorities concerned whenever he disturbs such existing way during the execution of the works.

17.0 Reporting

The Contractor shall prepare monthly progress reports to the SE on compliance with these general conditions, the project EMP if any, and his own EHS-MP. It is expected that the Contractor's reports will include information on:

• EHS management actions/measures taken, including approvals sought from local or national authorities;

• Problems encountered in relation to EHS aspects (incidents, including delays, cost consequences, etc. as a result thereof);

• Lack of compliance with contract requirements on the part of the Contractor;

• Changes of assumptions, conditions, measures, designs and actual works in relation to EHS aspects; and

• Observations, concerns raised and/or decisions taken with regard to EHS management during site meetings.

It is advisable that reporting of significant EHS incidents be done "as soon as practicable". Such incident reporting shall therefore be done individually. Also, it is advisable that the Contractor keeps his own records on health, safety and welfare of persons, and damage to property. It is advisable to include such records, as well as copies of incident reports, as appendices to the bi-weekly reports. Details of EHS performance will be reported to the Client through the SE's reports to the Client.

18.0 Training of Contractor's Personnel

The Contractor shall provide sufficient training to his own personnel to ensure that they are all aware of the relevant aspects of these general conditions, any project EMP, and his own EHS-MP, and are able to fulfil their expected roles and functions. Specific training should be provided to those employees that have particular responsibilities associated with the implementation of the EHS-MP. General topics should be:

• EHS in general (working procedures);

• Emergency procedures; and

• Social and cultural aspects (awareness creation).

19.0 Cost of Compliance

It is expected that compliance with these conditions is already part of standard good workmanship and state-of-the-art as generally required under this Contract. The item "Compliance with Environmental Management Conditions" in the Bill of Quantities covers these costs. No other payments will be made to the Contractor for compliance with any request to avoid and/or mitigate an avoidable EHS impact.

APPENDIX 5.2

Contractor’s Checklist on Environmental and Social Issues

Appendix 5.2 a: Contractor’s Checklist on Environmental and Social Issues

Project Name: _____________________________________________ Contract No. _________________________

Contractor Details: _____________________________________________________________________________________________

Project Description: _____________________________________________________________________________________________

|Question |Response |

|Activities | |

|1 |Outline the activities you will be undertaking during the works such as trench excavation, borrow and| |

| |quarry operation, laying asphalt, etc. | |

|Responsibilities | |

|2 |Indicate the name of the qualified / experienced person that will manage the environmental and safety| |

| |aspects of your job. Indicate qualification | |

|Materials | |

|4 |Outline the base materials you will transport to the site such as stone, soil, diesel, lubricant | |

|4 |Name where you will source these materials from (non-manufactured material such as sand, soil, stone)| |

|5 |Where will you store these materials? | |

|6 |How will you ensure materials brought to site will be stored and handled with care to avoid | |

| |contamination of soil and water, reduce dust, and minimize disruption of traffic, not impairing | |

| |safety? | |

|Emissions to water, soil and air (Pollutants) | |

|7 |How will you ensure that any materials and works will: | |

| |Not restrict access to other road uses, properties and carriageways. | |

| |Not damage existing trees | |

| |Be protected from rain to reduce the loss of soil and materials washing down roads and entering | |

| |drains and waterways. | |

| |Be stored to reduce leaks (such as Diesel) into the soil or waterways. | |

| |Not generate dust or cause nuisance air emissions. | |

|8 |How will you ensure proper drainage from the works so that water does not pond and become a hazard to| |

| |health? | |

|9 |How will you reduce sediment from the construction activities? | |

|Fauna and Flora | |

|10 |How many trees will you have to remove to undertake the works? | |

|11 |What will you do with any trees that are removed? | |

|12 |How will you protect existing trees from construction activities? | |

|Waste management | |

|13 |How do you plan to store and dispose of : | |

| |Construction debris? | |

| |Workers refuse and effluent? | |

| |General litter? | |

|Noise and Vibration | |

|14 |Will you be using any noisy equipment that may cause nuisance? | |

|15 |What will be your working hours? | |

|Construction camp/ Workers’ Camp | |

|18 |Where are you planning to set up construction and workers camp? | |

|19 |Does it meet the stipulated siting criteria? | |

|20 |How are you going to control pollution from contraction plant and equipment? | |

|21 |What facilities will you provide at the camp for workers? | |

|Community, Awareness, Consultation, Coordination | |

|22 |How will you keep the community, who are affected informed about the works? | |

|23 |How will you ensure all the sub-contractors, supervisor and others on the site, are aware of these | |

| |environmental and social aspects? | |

|24 |How will you coordinate with utility works (such as electricity, telephone, cable)? | |

|25 |Can you satisfy the special regulations or environmental conditions identified in the contract for | |

| |this project? | |

|26 |Have you attended any training course on environment, health and safety for similar construction | |

| |project? | |

Prepared By: ________________________________ Date __________________________

Approved By: _______________________________ Date __________________________

Agreed Comments: ___________________________________________________________

Appendix 5.2 b: Construction Camp and Laborer Camp

| |Workers Camp |

|Fencing |Provide fencing around the camp to protect the area and to prevent damaging the surrounding land |

|Drainage |Site should be well drained for storm water and should be graded, ditched and rendered free from depressions in |

| |which water may become a nuisance |

|Dwelling Units |All sites should be adequate in size to prevent overcrowding of necessary structures |

| |If twenty or more women are employed as contract labour, two rooms of reasonable dimensions are to be provided for|

| |the use of their children under the age of six years, one for playing and another as bedroom for children |

| |Each room used for sleeping purposes should contain adequate floor space for each occupant |

| |At least a 7-foot ceiling should be provided |

| |Beds, cots, or bunks and suitable storage facilities such as wall lockers for clothing and personal articles are |

| |to be provided in every room used for sleeping purposes |

| |The floors of each shelter is to be constructed of wood, asphalt, or concrete |

| |All living quarters are to be provided with adequate windows |

| |At least one-half of each window should be so constructed that it can be opened for purposes of ventilation |

|Water Supply |Adequate and convenient water supply to be provided in each camp for drinking, cooking, bathing and laundry |

| |purposes |

| |Ensure at least 80 litre per capita per day water supply |

|Sanitation |Provide separate toilets for men and women distinctly marked “for men only” and “for women only” by signs printed |

| |in English and in the native language of the persons occupying the camp, and also bear the system of man or woman |

| |as the case may be |

| |Number of toilet unit min 2, and max @ 1 in 15 persons |

| |Toilets are to be cleaned at least once in a day |

| |Provide and maintain separate urinals for male and female workers @ 1 in 50 persons |

| |Water to be provided by the means of tap or otherwise so as to be conveniently accessible in or near the latrine |

| |and urinals |

| |Clean nightsoil and dispose at designated areas only |

|Lighting |At least one ceiling type light fixture in each living room, kitchen, toilet, bathroom |

| |The name and address of any individual in the camp known to have or suspected of having a communicable disease to |

| |be intimated to Engineer local health officer |

| |In case of suspected food poisoning or an unusual prevalence of any illness in which fever, diarrhoea, sore |

| |throat, vomiting, or jaundice is a prominent symptom, it should be reported immediately to Engineer/local health |

| |officer and appropriate action to be taken. |

|Kitchen/Dining |If one hundred or more labour is likely to be employed for six months canteen to be provided within 60 days |

| |No person with any communicable disease to be employed or permitted to work in the preparation, cooking, serving, |

| |or other handling of food, foodstuffs, or materials used therein, in any kitchen or dining room operated in |

| |connection with a camp or regularly used by persons living in a camp |

| |Canteen should consist of at least a dining hall, kitchen, storeroom, pantry and washing places separately for |

| |workers and for utensils |

| |The precincts of the canteen to be maintained in a clean and sanitary condition |

| |Wastewater to be carried away in suitable drains and should not be allowed to accumulate so as to cause a nuisance|

| |Provide, use and maintain separate bins for collection of biodegradable plastic waste and other waste |

| |Dining should accommodate at a time at least 50 percent of the labour staying at camp and working same time |

| |Provide and maintain sufficient utensils, cookery, cutlery, furniture and any other equipment necessary for the |

| |efficient running of the canteen |

|First Aid |Provide and maintain first aid in a specified dispensary room |

|Health check- up |Carry out regular health check by local medical practitioner |

|Entertainment |Provide entertainment facilities such as TV/Video shows to discourage workers going out in the evenings |

| |Storage & handling of hazardous material |

|Person |Authorize a person for up-keep of each of the storage area and provide necessary training |

|Planning |Underground storage bunker or impervious raised platform |

| |Prefer bulk storage tank with mechanized handling system instead of small drums to avoid/minimize spillage during |

| |handling |

| |Keep and maintain adequate open space around HSD storage area |

| |Keep and maintain adequate ventilation/open space for storage of lubes, engine oils etc. in drums |

| |All premises of HSD, lubes, engine oil storage area should be adequately segregated by fencing, barrication etc. |

| |(with 5-8m buffer zone) at least 1.8m height |

| |No other substances should be stored along with inflammable liquids |

| |No other works should be undertaken inside the storage premises |

|Regular checking & |Label all storage tanks/drums indicating the content and with cautionary marking i.e. “Hazardous & Handle with |

|compliance |care” in red colour on fluorescent yellow background; content, name & address of manufacturer/importer and |

| |physical, chemical and toxicological data i.e. toxicity (for toxic chemicals), ignition temperature (for flammable|

| |gases), flash point, initial & final boiling points (for flammable liquids) etc. |

| |Check all valves and trigger guns regularly |

| |Storage area inside the premises to be kept clean and free from any accumulation |

| |Drums/closed containers should only be opened within specified isolated area |

| |Empty containers not to be stored along with full containers |

| |Vehicles carrying inflammable liquid to be stopped before loading and unloading |

| |Maintain fire extinguisher in the form of dry chemical powder, foam, wetting agents or gas as mentioned in the |

| |attachment |

| |Use protective equipments for personnel involved in handling i.e. safety jackets, gloves, goggles, etc |

| |Collect spillage in cane, re-used and/or disposed of at designated sites with prior approval of Engineer and |

| |concerned authorities |

| |Display and maintain sufficient “Danger”, “ No Smoking”, “Fire” warning signs |

| |Display and maintain Notice Board in bold letters indicating action to be taken by the employees in an emergency |

| |Display and maintain telephone number of local fire station in the Notice Board |

| |Welding & Cutting |

|Person |Designate an individual responsible for authorizing cutting and welding operations in areas not specifically |

| |designed for such processes (issuing authority for Hot-Work-Permit) |

|Control |Hot-Work-Permit from concerned person for permitting welding/cutting is mandatory. The concerned person must |

| |inspect the site before issuing permit |

|Areas not permitted |Cutting & welding should not be permitted in the presence of explosive atmospheres (mixture of flammable gases, |

| |vapors, liquids, or dust with air), or explosive atmospheres that may develop inside unclean or improperly |

| |prepared tanks or equipment which have previously contained such materials, or that may develop in areas with an |

| |accumulation of combustible dusts |

| |Welding & cutting should not be permitted in areas near the storage of large quantities of exposed, readily |

| |ignitable materials such as bulk sulphur, baled paper, or cotton |

| |Cutting or welding on pipes or other metal in contact with combustible walls, partitions, ceilings or roofs should|

| |not be undertaken if the work is close enough to cause ignition by conduction |

|Fire safety |Relocate combustible, material at least 35ft from the welding/cutting area |

| |Keep ready suitable fire extinguishing equipment e.g. pails of water, buckets of sand, hose or portable |

| |extinguisher depending upon nature and quantity of inflammable matter exposed |

|PPE |Helmets or hand shields should be used during all welding or all cutting operations, excluding submerged welding. |

| |Helpers or attendants should be provided with proper eye protection |

| |Goggles should be used during all gas welding or oxygen cutting operations. Spectacles without side shield, with |

| |suitable filter lenses are permitted for use during gas welding operations on light work, for torch brazing or for|

| |inspection |

| |All operators and attendants of resistance welding or resistance brazing equipment should use transparent face |

| |shield or goggles |

|Medical Help |If chest pain, cough, or fever develops after use call physician immediately |

Appendix 5.2 c: Excavation Works

|Site clearance |Check presence of underground electrical cable |

| |If electrical isolation is required, refer to appropriate authority |

| |Check presence of underground water pipe line |

| |Shifting of water pipeline in consultation with concerned department |

|Traffic safety measures |Plan detour/diversion of traffic from working area |

| | |

| |Delineate excavated area by painted poles, safety ribbon or any other |

| |appropriate means |

| |Provide and maintain strong barrication if excavation is > 2m |

| |Provide reflective tape on delineators |

| |Install necessary traffic signs |

| |Depute flagmen, as may be required to control traffic |

|Planning & Control |Construction of subgrade/sub-base and layers should start as soon as |

| |excavation is completed, as is the case |

| |Ensure that soil/stone aggregate is used from approved borrow/quarry |

| |areas only |

|Traffic management during construction |Ensure proper entry and exit points of earth moving vehicles without |

| |interfering traffic |

| |Restrict movement of construction equipment and workers within |

| |delineated working zone only |

| |Maintain traffic signs, delineators, barricades |

| |Deploy flagmen to regulate traffic |

| |Clean diversion from spill of aggregates regularly |

| |Provide water sprinkling on regular basis to avoid dust generation |

| |Do not allow any child within construction zone |

| |Personal Protective Equipment must. be worn by workers and visitors to|

| |work sites |

|Use must be enforced |Shoes/gumboot and helmet for all workers |

|General Safety Measures |

|Ensure that working zones are adequately delineated from traffic and public movement |

|Deploy flagmen at both ends of working zone to regulate traffic |

|Only required persons are to be allowed within the working zone |

|Personal Protective Equipment |

|Every workers/supervisors must wear/safety shoes and reflective yellow jacket/vest |

|Workers involved in cleaning of surface should wear air mask and goggle in addition to jacket and safety shoes |

Appendix5.2 d Construction Plants Operation

|Crusher Operation |

|Water sprinklers should be kept operational all the time |

|Start operation of water sprinkling and crusher simultaneously |

|Ensure that adequate water is available in the tank (for sprinkling) before start of crusher operation daily |

|Maintain spare sprinklers at store to ensure immediate replacement in the event of damage, and not to hamper operation |

|Do not operate crusher without water sprinkling |

|Hot Mix Plant Operation |

|Ensure air pollution control (APC) equipment is kept operational all the time |

|Start operation of water air pollution control equipment and HMP simultaneously |

|Do not operate HMP if APC equipment is not functioning |

|Ensure maintenance of APC and pumps to avoid mal-functioning during operation of HMP |

|DG Sets |

|Provide stack of about 5m above roof level for heavy Diesel Generator (DG) set |

|DG set will have enclosure else install inside a room with solid wall and roof |

|Do not keep open any enclosure while generator is operating because it will not help in internal cooling |

|Preferably having valid certificates of “Type Approval” and “Conformity of Production” |

|General Safety Measures at Plant Site |

|Explain safe work-procedures to all workers (and whoever is newly inducted) |

|Establish communication system and explain it to the workers |

|All work platforms to be of adequate strength and ergonomically suitable |

|Fabricated make shift arrangements are to be checked for quality and type of material welding, anchoring, etc. |

|Avoid working at more than one elevation at the same segment |

|Ensure that walk ways are provided with adequate hand-rail, mid-rail & toe guard |

|Ensure that all chequered plates and gratings are properly welded/bolted |

|Ensure that ladders are maintained in good condition and inspected |

|Ladders are to be spliced |

|Ensure that ladders are properly secured to prevent slipping, sliding or falling |

|Side-rails are to be extended 36” above top of landing |

|Built up ladders are to be constructed of sound materials |

|Ensure rungs and cleats not over 12” on centre |

|Do not use metal ladders around electrical hazards |

|Ensure that ladders, staircases are welded/bolted properly |

|There should not be any obstruction on the stairs |

|Check whether landings are provided with handrails, knee-rails, toe-boards, etc |

|Walkways, aisles & all overhead workplaces should be cleared of loose material |

|Ensure flammable material (if any) are cleared |

|Ensure platforms and walkways free of oil/grease or other slippery spillage |

|Collected scrap should be brought down or lowered down and not dropped from height |

|Ensure plug mills (for wet mix plant) are covered enough to protect anybody from falling inside |

|Personal Protective Equipment |

|Do not allow any person near plant without wearing safety shoes, helmet, air mask, ear muff and goggle |

|Enforce use of safety belts for workers working at height |

|Proper fall arrest system to be deployed at critical work places. |

APPENDIX 6a

Environmental Complaint Log

Appendix 6a-Environmental Complaint Log

|Complaint |Complaint Received |Complaint |Nature of Complaint |IEC Notified |Is Complaint Due to |To be completed by site |

|Ref. No. | | | |on |Project Works? | |

| |Date |Time |Name & Contact Info |Env. Media |Description | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

| | | | | | | |

Remark *Media code: W-Water; A-Air Quality; N-Noise Level; O-Other.

APPENDIX 6b

Environmental Complaint Record Form

Appendix 6b-Environmental Complaint Record Form

|Project/ Contract Name: | |

| Complaint Ref No: | |

|Complaint Received |

| Date: | |

| Time: | |

| By: | |

|Complainant |

| Name: | |

| Telephone: | |

| Address: | |

|Nature of Complaint |

| Date of Complaint: | |

| Time of Complaint: | |

| Media*: | |

| Description: | |

|To Be Completed By Site |

| IEC Notified on: | |

| Complaint Verified on: | |

|Is Complaint Attributable to the Project | |

|Works? | |

| Response: | |

| Recommendations: | |

Remark: * Please indicate whether the non-compliance is related to air quality, noise, water quality or other aspects.

APPENDIX 6c

Compliant Response Procedures

Appendix 6c- Compliant Response Procedures

COMPLAINT

DIRECTOR

REFERRED

IS THE

PROJECT THE SOURCE

OF COMPLAINT NO

YES

IS ET

NO SATISFIED? YES YES

YES

NO IS THE

COMPLAINANT

NOW SATISFIED?

PERIODIC

FOLLOW-UP YES

CONTACT WITH

COMPLAINANT

APPENDIX 6d

Field Data Record Sheet for TSP Monitoring

Appendix 6d-Field Data Record Sheet for TSP Monitoring

|Monitoring Location: |` |

|Description of Location: | |

|Date of Monitoring: | |

|Weather Condition: | |

| Equipment: | Equipment No |

| High Volume Sampler: | |

|Sampling Start Time | |

|Sampling End Time | |

|Initial Elapsed Time Reading | |

|Final Elapsed Time Reading | |

|Initial Flow Rate(m3/min) | |

|Final Flow Rate(m3/min) | |

|Average Flow Rate(m3/min) | |

|Total Volume(m3) | |

|Filter Identification no. | |

|Initial Weight of Filter(g) | |

|Final Weight of Filter(g) | |

|Weight of Particulate(g) | |

|Particulate Concentration(µ/m3) | |

|Site Construction Activities | |

| | |

|Remarks | |

| | |

| | Name | Signature | Date |

|Recorded by | | | |

|Checked by | | | |

APPENDIX 6e

Field Data Record Sheet for Water Quality Monitoring

Appendix 6e-Field Data Record Sheet for Water Quality Monitoring

|Monitoring Location | |

|Date | |

|Start Time (hh mm) | |

|Weather | |

|Sea/Watercourse Conditions | |

|Tidal Mode | |

|Water Depth (m) | Surface | Middle | Bottom |

|Monitoring Depth | | | |

| | S1 | S2 | S1 | S2 | S1 | S2 |

|Monitoring Parameter 1, unit | | | | | | |

|Monitoring Parameter 2, unit | | | | | | |

|Monitoring Parameter 3, unit | | | | | | |

|Monitoring Parameter 4, unit | | | | | | |

|Monitoring Parameter 5, unit | | | | | | |

|Monitoring Parameter 6, unit | | | | | | |

|Observed Construction Activities During Monitoring | |

| | |

|Other Observations | |

| | |

| | Name | Signature | Date |

| Recorded by | | | |

| Checked by | | | |

APPENDIX 6f

Field Data Record Sheet for Noise Monitoring

Appendix 6f-Field Data Record Sheet for Noise Monitoring

|Monitoring Location | |

|Description of Location | |

|Date of Monitoring | |

|Weather Condition | |

|Wind Strength (m/s) | |

| Equipment | Equipment No. |

|Sound Level Meter | |

|Sound Pressure Calibrator | |

|Calibration before measurement (dB(A)) | |

|Calibration after measurement (dB(A)) | |

|Measurement Start Time | |

|Measurement Time Length (min) | |

|Measurement Results (dB(A)) | 1st | 2nd | 3rd | 4th | 5th | 6th | Average |

|Noise Parameter 1 | | | | | | | |

|Noise Parameter 2 | | | | | | | |

|Noise Parameter 3 | | | | | | | |

|Major Construction Noise Source(s) | |

|During Measurement | |

|Other Noise Sources(s) | |

|During Measurement | |

|Remarks | |

| | Name | Signature | Date |

| Recorded by | | | |

| Checked by | | | |

APPENDIX 6g

Corrective and Preventive Action Request Form

Appendix 6g- Corrective and Preventive Action Request Form

|Project/ Contract Name: |Ref. No.: |

|Date of Inspection: |Time: |

|Work Inspected: |

|Works Location: |

|Observation During the Inspection: |

| |

|Corrective/ Preventive Action Taken/ To be Taken: |

| |

Inspected by: . Time: .

Date: .

Received and approved by: Time: .

Date: .

Copy of this Notification Sent to: contractor(s), ER, IEC, EPB, if appropriate.

APPENDIX 6h

Environmental Site Inspection Report

APPENDIX 6h- Environmental Site Inspection Report

|Project/Contract Name: |Report No: |

|Date of Inspection: |Time: |

|Weather Condition: | |

|Works Inspected: | |

|Location: | |

|Remarks: | |

|Environmental Non-Compliance/Exceedances: Yes No |

|1. Non-Compliances with PRC laws and regulation | | |

|2. Non-Compliances with the recommendations and requirements in the Project | | |

|EIA Report, EM & A Manual, and the Environmental License/Permit | | |

|3. Non-Compliances with the Action & Limit Levels listed in the Project EMP. | | |

| | | |

| | | |

|Description of Environmental Non-compliance (if any): |

|1. Description of Non-compliance Identified |

|2. Description of Non-compliance Identified |

|Potential Environmental Contractual/Management Issues/Variances: Yes No |

|1. Contractual Requirements | | |

|2. Contractual Requirements | | |

| | | |

|Description of Potential Environmental Contractual/Management Issues/Variances (if any): |

|1. Description of Observations | |

|2. Description of Observations | |

|Remedial Actions – Mitigation Measures implemented or Proposed (if any): |

|Findings of Previous Inspection Report |

| |

| |

|Current Inspection Report |

| |

Inspected by

(ET): ________________________ Title: ________________________

________________________ Date: ________________________

Contractor’s

Representative: ________________________ Title: ________________________ ________________________ Date: ________________________

Reviewed and

Approved by ER: ________________________ Title: ________________________ ________________________ Date: ________________________

Copy of report sent to: Contractor (s), ER, IEC and EPB, if appropriate

APPENDIX 6i

Interim Notification of Environmental Quality Limit Exceedances Report Sheet

APPENDIX 6i- Interim Notification of Environmental Quality Limit Exceedances Report Sheet

|Project/Contract Name: |Notification: |

|Date of Notification: |Time: |

|Works Inspected/Env. Monitoring Results Received: |

| |

|Works Location/Monitoring Location |

| |

|Env. Aspects/Parameter |

| |

|Action & Limit Level AL LL/Measured Level: |

| |

|Possible Reason for Action Limit Level Non-compliance: |

| |

|Action taken / to be taken |

| |

Inspected by

(ET): ________________________ Title: ________________________

________________________ Date: ________________________

Reviewed and

Approved by ER:________________________ Title: _______________________ ________________________ Date: ______________________

Copy of Notification Sent to: Contractor (s), ER, IEC and EPB, if appropriate

References

1. Federal Republic of Nigeria (1992); Environmental Impact Assessment

Decree No. 86 of 1992.

2. Federal Republic of Nigeria (1992); National Policy on the Environment.

3. Construction Industry Research and

Information Association (1994); Special Publication 96, Environmental.

4. World Bank Technical Paper No. 140

(1991); Environmental Assessment Source Book

Volume II Sectoral Guidelines.

5. Federal Republic of Nigeria (1991); Guidelines and Standards for Environmental

Pollution Control in Nigeria.

6. New South Wales Government (1998); Environmental Management Systems

Guidelines.

7. European Committee for Standardization:

EN ISO 14001 (1996); Environmental Management Systems –

Specifications with Guidance for use.

8. Standard Organizations of Nigeria

(SON) (2000); Nigeria Industrial Standards (NIS): Quality

Management Systems.

9. Cunningham VP and

Cunningham M.A (2004); Principles of Environmental Science – Inquiring and Application.

10. El-Tauil, Anwar (1998); ISO/Swigs Government Regional & itinnevant Training Seminar for African

Countries on Environmental Management and ISO 14000, Lagos, Nigeria, October 1998.

11. World Bank (2007) Final Generic Environmental Management

Plan (EMP) Implementation Manual

-----------------------

Institutional development

Health programmes

Family planning programmes

Nutritional programmes

Educational programmes

Environmental awareness

Category III

Agriculture and Rural Development

Any reforestation/afforestation project

Small scale irrigation and drainage

Small scale agriculture/mariculture

Saw milling/wood logging

Rubber processing

Any fish processing

Any other Agro-allied industry

Industry and infrastructure

Mini hydro power development

e.g textiles chemical industries etc

Small scale power transmission

Any renewable energy development

Telecommunication facilities

Rural water supply and sanitation

Public facilities (Hospitals and related facilities, schools, housing etc)

Small scale tourism development

Small scale development of petroleum or related facilities

Road rehabilitation

Any form of Quarrying or mining

but if the project involves

Physical interventions in the environment

then

but if the project is located or close to

Category II

Environmentally sensitive areas

Coral reefs

Mangrove swamps

Small islands

Tropical rainforests

Areas with erosion prone soils e.g

Mountain slopes

Areas prone to desertification (and semi arid zones)

Natural conservation areas

Wetlands of National or international importance

Areas which harbor protected and or endangered species

Areas of unique scenery

Areas of particular scientific interest

Areas of historic or archeological interest

Areas of importance to threatened ethnic groups

then

See Appendix 2.1

ET TO CONTACT THE COMPLAINANT

OBTAIN DETAILS OF COMPLAINT

STEP PROGRAMME FOR INVESTIGATION TO COMPLAINANT

REGISTER IN THE COMPLAINT LOG

INVESTIGATION COMPLAINT

FOLLOW EMRA AT THE

COMPLAINT AREA

NOTIFY ER and EC

REPOR[pic][?]QRW[`dsåæçèU e ‹ Œ º » ìÕÈ»¤»¤»–ƒpbWKBK3W3jh˜Eh‰KOJQJU[pic]h‰K5?OJQJh˜Eh‰K5?OJQJh˜Eh‰KOJQJh˜Eh‰K5?CJ(OJQJ$h˜Eh‰K5?B*CJ(OJQJph”64$h˜Eh‰K5?B*CJ OJQJphpÀh˜Eh‰K5?CJ$OJQJ,T TO EPB OUTCOME OF

ACTI ON PLAN

REPLY TO COMPLAINANT

COMPLETE COMPLAINANTS LOG

INCLUDECOMPLAINANT DETAILS IN REGULAR MONTHLY REPORT

COPY TO EPS

E1472 V2

................
................

In order to avoid copyright disputes, this page is only a partial summary.

Google Online Preview   Download