The first outage event was recorded at 07:53 on 09/13/2008. The last outage event was recorded at 14:34 on 09/13/2008. 12 of the substations were back in service in approximately 24 hours, with an additional 11 restored within 36 hours. The last two stations were restored in approximately 39 and 54 hours, respectively. Mutual assistance: ................
................