Archived Construction Variances Requested



Published: July 2015

Variances Requested - Construction

Part number and rule number from which variance is requested RULE R408.40115, Rule 115 (4) & (5) and R408.41113, Rule 1113 (5) (6) (8) & (14), and R408.41140, Rule 1140

Summary of employer's request for variance To allow employee to paint steel lattice and pole tower ranging from 120 kV to 345 kV in the International Transmission Company territory located in Michigan. The work would commence immediately following the variance approvals and continue until the end of the 2015 painting season.

Name and address of employer Location for which variance is requested

Morris Painting Inc Various locations in the International Transmission Co

Territory located in Michigan.

Published: July 2014

Variances Requested - Construction

Part number and rule number from which variance is requested RULE R408.40115, Rule 115 (4) & (5) and R408.41113, Rule 1113 (5) (6) (8) & (14), and R408.41140, Rule 1140

Summary of employer's request for variance To allow employee to paint steel lattice and pole towers ranging from 120 kV to 345 kV in the International Transmission Company territory located in Michigan. The work would commence immediately following the variance approvals and continue until the end of the 2012 painting season.

Name and address of employer Location for which variance is requested

Morris Painting Inc Various locations in the International Transmission Co

Territory located in Michigan.

Part number and rule number from which variance is requested Rule 1926.602 Part 13-Mobile Equipment

Summary of employer's request for variance To allow employer to operate a CAT 304C and 303C without the Roll over Protection System (ROPS) in the lower level of the building, for the removal of concrete slabs, backfill and replacement of concrete provided the following stipulations are adhered to:

Name and address of employer Location for which variance is requested

Eagle Excavation U of M West Quad Hall, Ann Arbor

Hardman Construction U of M West Quad Hall, Ann Arbor

Part number and rule number from which variance is requested R408.41065a (1), R408.41065a (2) and R408.41072a (15), Part 10 - Lifing and Digging Equipment

Summary of employer's request for variance To allow the use of a temporary personnel hoist systems to transport workers, tools, and materials to and from elevated worksites in a personnel cage during chimney construction work provided employer comply with all the requirements set forth in the OSHA chimney-related permanent variance published in the Federal Register as Number 2013-23625 on October 2, 2013 and all the requirements of Construction Safety Standard, Part 10, Lifting and Digging Equipment except for Rules 1065a (1), 1065a (2) and 1072a (15) which are met as follows

Name and address of employer Location for which variance is requested

International Chimney Corporation DTE Energy, Monroe Power Plant, 3500 East Front Street, Monroe, MI 48161

Published: April 2014

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms, R4084.3216 (3) & 3216(4)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach due to overhead obstructions to complete the installation and finishing of a metal stud and drywall partition provided the following stipulations are adhered to

Name and address of employer Location for which variance is requested

Conti Mechanical GM Powertrain, Engineering Lab, Pontiac

Conti Fire Protection GM Powertrain, Engineering Lab, Pontiac

Motor City Electric Co GM Pontiac Powertrain Center, General Motors.

Pontiac Ceiling & Partition Co., LLC Cobo Hall, Detroit

Rival Insulation LLC Cobo Center Phase II, Southside Renovations,

Detroit

Superior Electric Great Lake Co., GM Proving Grounds, Milford

Published: December 2013

Variances Requested - Construction

Part number and rule number from which variance is requested

PART: 32 – Aerial Work Platforms R408.43216; Rule 3216 (3) & Rule 3216 (4)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach due to overhead obstructions

Name and address of employer Location for which variance is requested

CONTI CORPORATION Consumers Energy, Karn Weadock Power Plant, Essexville

MOTOR CITY ELECTRIC CO GM Warren Technical Center Campus Design Dome Renovation Project, Warren

NATIONAL MAINTENANCE GM Proving Grounds (Data Center Project), Milford

SERVICES, LLC

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach due to overhead obstructions

Name and address of employer Location for which variance is requested

CARRIER CONSTRUCTION Western Michigan University School of Medicine,

COMPANY, INC Kalamazoo

CASADEI STEEL INC GM Data Center, Proving Grounds, Milford

PRO SERVICES INC WMU School of Medicine, Kalamazoo

Published: July 2013

Variances Requested – Construction

Part number and rule number from which variance is requested

Part I – General Rules: R408.40115, Rule 115 (4) & (5) and

Part II – Fixed and Portable Ladders: R408.41113, Rule 1113 (5) (6) (8) & (14), and R408.41115, Rule 1115 (8)

Summary of employer's request for variance

To allow employee to paint steel lattice and pole towers ranging from 120 KV to 345 KV in the International Transmission Company territory located in Michigan.

Name of employer Location for which variance is requested

Morris Painting, Inc. Various Locations in the International Transmission Company Territory located in Michigan

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41213; Rule 1213 (1)

Summary of employer's request for variance

To allow employer to use a warning line system in addition to the designed guardrail of a SafeSpan scaffold under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Seaway Painting, LLC Mackinac Bridge over the Straits of Mackinac, Mackinaw City

Part number and rule number from which variance is requested

Part 13 – Mobile Equipment: R1926.602; Rule 1926.1000

Summary of employer's request for variance

To allow employer to operate a CAT 304C and 303C without the Roll over Protection System (ROPS) in the lower level of the building, for the removal of concrete slabs, backfill and replacement of concrete provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Eagle Excavation U of M South Quad Hall Renovation Project, Ann Arbor

Hardman Construction U of M South Quad Hall Renovation Project, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach, due to overhead obstructions provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Barton Malow Company U of M Institute for Social Research Addition, Ann Arbor

Consumers Energy D.E. Karn, Essexville

Dee Cramer GM Pontiac – Hydrogen, Pontiac

U of M South Quad, Ann Arbor

Consumers Energy De-Karn Plant, Essexville

Edwards Glass Co. U of M Institute for Social Research Addition, Ann Arbor

JM & Sons Plumbing Co. U of M GG Brown Engineering Lab, Ann Arbor

John E. Green Company U of M Institute for Social Research Addition, Ann Arbor

Michigan Automotive Compressor Inc., Parma

Limbach Company LLC Western Michigan University School of Medicine, Kalamazoo

SCI/Steelcon WMU Medical School, Kalamazoo

Superior Electric GM Powertrain Facility, Pontiac

Turner Brooks Pfizer Building, Kalamazoo

Western Mechanical Contr. Inc. Cobo Center Phase II Southside Renovations, Detroit

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

CA Hull/Hardman Construction JV US 231 over the Grand River, Nunica, & Grand Haven

Hardman Construction JH Campbell Plant Intake/Discharge Channel, West Olive

US 131 over the St. Joseph River, Constantine

Milbocker & Sons, Inc. M-222, Allegan

Slagter Construction I-196 at Market St., Grand Rapids

Published: April 2013

Variances Requested – Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches under controlled conditions, with stipulations.

Name of employer Location for which variance is requested

ANM Construction Company St. Mary Mercy Momentum 2012, Livonia

Acoustic Ceiling & Partition Co. St. Joseph Mercy Oakland, Pontiac

Barton Malow Company St. Joseph Mercy Oakland Hospital – Campus Regeneration Project, Pontiac

Crittenton Hospital – Cornerstone South Tower Project,

Rochester Hills

Brinker Team Interiors Detroit Receiving Hospital, Detroit

1 Woodward Blvd., Floors 3, 4, 5, 7, 8, & 9, Detroit

Quicken Loans, Troy

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach, due to overhead obstructions provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Barton Malow Company St. Joseph Mercy Oakland Hospital – Campus Regeneration Project, Pontiac

Crittenton Hospital – Cornerstone South Tower Project, Rochester Hills

De-Cal, Inc. COBO Arena, Detroit

Denn-Co Construction Inc. Detroit Medical Center Cardiovascular Institute Multispecialty Building, Detroit

Dobson Industrial Warren Transmission GFE Project, Warren

FM Sylvan, Inc. GM – Powertrain Facility, Pontiac

Interstate Fire Protection Inc. General Motors Transmission, GFE Project, Warren

John E. Green Company Sparrow Hospital – Main Campus Tower, Lansing

Kruse Construction Inc. GM Warren Transmission, GFE Project, Warren

LaSalle General Contractors GM Warren Transmission, GFE Project, Warren

National Maintenance Services GM Pontiac Powertrain, HQ (Fuel Cell Construction Site), Pontiac

Partlan-Labadie Sheet Metal Co. GM Warren Transmission, GFE Project, Warren

R. L. Bondy Insulation Inc. Crittenton Hospital Medical Center, Rochester Hills

URS Corporation DTE Monroe Power Plant FGD & SCR Projects, Monroe

Ventcon Inc. COBO Arena/Atrium, Detroit

Western Mechanical Contractors St. Joseph Mercy Oakland South Patient Tower & Regeneration, Pontiac

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Davis Construction Cleveland St. over Grand River, Ionia County

Published: October 30, 2012

Variances Requested – Construction

Part number and rule number from which variance is requested

Part 10 – Lifting & Digging Equipment: R408.41005a (2), Rule 1005a (2): Reference ANSI Standard B30.5 Mobile and Locomotive Cranes, 1994 Edition, Section 5-3.2.1.2b.

Summary of employer's request for variance

To allow employer to rig certain loads to the load line of a crane above the overhaul weight in accordance with certain stipulations.

Name of employer Location for which variance is requested

Wm. Crook Fire Protection Co. Ford Motor Company, Dearborn Stamping Plant, Dearborn

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches under controlled conditions, with stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition, Inc. Monroe Community College, Monroe

ANM Construction Company Lincoln High School Performing Arts, Ypsilanti

Barton Malow Company Varsity Ann Arbor Project, Ann Arbor

Brinker Team Interiors Lambert Edwards Associates, Detroit

Price Waterhouse & Cooper Project, Detroit

Mid Thumb Contracting Group McKinley Elementary School, Warren

North American Construction Ent. McKinley Elementary School, Warren

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach, due to overhead obstructions provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

De-Cal, Inc. GM Powertrain, Warren

John E. Green Company General Motors Tech Center, Warren

Hoyt, Brumm & Link Inc. General Motors Power Train Facility, Pontiac

Ventcon, Inc. St. Joseph Mercy Oakland Campus Regeneration Project, Pontiac

Published: July 27, 2012

Variances Requested – Construction

Part number and rule number from which variance is requested

Part I – General Rules: R408.40115, Rule 115 (4) & (5) and

Part II – Fixed and Portable Ladders: R408.41113, Rule 1113 (5) (6) (8) & (14), and

R408.41115, Rule 1115 (8)

Summary of employer's request for variance

To allow employee to paint steel lattice and pole towers ranging from 120 kV to 345 kV in the International Transmission Company territory located in Michigan. The work would commence immediately following the variance approvals and continue until the end of the 2012 painting season.

Name of employer Location for which variance is requested

Morris Painting, Inc. Various Locations in the International Transmission Co. territory

Part number and rule number from which variance is requested

Part 10 – Lifting & Digging Equipment: R408.41005a (2), Rule 1005a (2): Reference ANSI Standard B30.5 Mobile and Locomotive Cranes, 1994 Edition, Section 5-3.2.1.2b.

Summary of employer's request for variance

To allow employer to rig certain loads to the load line of a crane above the overhaul weight in accordance with certain stipulations.

Name of employer Location for which variance is requested

Wm. Crook Fire Protection Co. Chrysler Sterling Heights Assembly Plant, Sterling Heights

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches under controlled conditions, with stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition, Inc. University of Michigan East Quad, Ann Arbor

Washtenaw Comm College Student Center Renovation, Ann Arbor

Barton Malow Company Chrysler GLBC, Detroit

University of Michigan Crisler Arena Project, Ann Arbor

North American Construction Ent. Huron Park Elementary, Roseville

L’Anse Creuse North High School, Macomb

Ritsema Associates Spectrum Health United Memorial Hospital, Greenville

Part number and rule number from which variance is requested

Part 13 – Mobile Equipment: 1926.602, Rule 1926.1000

Summary of employer's request for variance

To allow employer to operate mobile equipment without the Roll Over Protection system (ROPS) provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Eagle Excavation Inc. U of M East Quad Hall Renovation Project, Ann Arbor

Hardman Inc. U of M East Quad Hall Renovation Project, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach, due to overhead obstructions provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Barton Malow Company DTE GO – 9th Floor Auditorium Restoration Project, Detroit

University of Michigan Crisler Arena Project, Ann Arbor

Dee Cramer, Inc. Crittenton Hospital Medical Center, Rochester Hills

John E. Green Company Crittenton Hospital, Rochester Hills

Moote Electrical, Inc. Crittenton Hospital Cornerstone Tower Addition, Rochester

Shaw Electric Company University of Michigan Chrysler Arena Expansion, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Anlaan Corporation Blue Star Highway Bridge over Kalamazoo River, Douglas

Milbocker & Sons, Inc. Kalamazoo County River Road, Comstock

Published: April 27, 2012

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 10 – Lifting & Digging Equipment: Rule 1015a (2) (d)(f)(g)(h)(i), 1015a (3), 1015a (4); 1018a (1)(2)(21); 1019a (1); and 1021a (4)

Summary of employer's request for variance

To allow the use of a suspended work platform to hoist or suspend personnel or to provide access to elevated work areas in a manner that exposed employees to the least hazard practicable. All requirements of Construction Safety Standard, Part 10. Lifting and Digging Equipment except Rule 1015a (2) (d)(f)(g)(h)(i), 1015a (3), 1015a (4); 1018a (1)(2)(21); 1019a (1); and 1021a (4)

Name of employer Location for which variance is requested

Pullman Power LLC St. Clair Power Plant, East China Twp.

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41213, Rule 1213 (1)

Summary of employer's request for variance

To allow employer to use a warning line system in addition to the designed guardrail of a SafeSpan scaffold under controlled conditions and according to certain stipulations. The SafeSpan guardrail does not meet the requirements of Part 12.

Name of employer Location for which variance is requested

Seaway Painting, LLC Ambassador Bridge over the Detroit River, Detroit

Walter Toebe Construction Co. Ambassador Bridge over the Detroit River, Detroit

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches under controlled conditions, with stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition, Inc. Chelsea Community Hospital Addition, Chelsea

Costco, Ann Arbor

Sterling Contracting, Inc. Broderick Tower, Detroit

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach, due to overhead obstructions provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Buist Electric Target Store Remodel Project, Walker

Dee Cramer, Inc. Lincoln High School Performing Arts, Ypsilanti

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Davis Construction Lansing Board of Water and Light, Lansing, MI

Milbocker & Sons, Inc. M-223 over the Raisin River, Lenawee County

Published: February 3, 2012

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches under controlled conditions, with stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition, Inc. Oakland University Campus, Rochester

Barton Malow Company St. Mary Mercy Hospital Southwest Addition, Livonia

Children’s Specialty Center Detroit Medical Center, Detroit

BLUnite Project, Detroit

U of M NCRC Building #16 Project, Ann Arbor

Brinker Team Interiors First National Building, Detroit

Finney Crockett High School, Detroit

Jasman Construction Greenleaf Trust Building, Birmingham

Ritsema Associates Western Michigan University, Kalamazoo

Turner Brooks Western Michigan University, Kalamazoo

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach, due to overhead obstructions provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Conti DMC Pediatric Specialty, Detroit

John E. Green Company Chelsea Hospital Project, Chelsea

Published: October 24, 2011

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 13 – Mobile Equipment: R1926.602; Rule 1926.1000

Summary of employer's request for variance

To allow employer to operate mobile equipment without the Roll Over Protection system (ROPS) provided stipulations are adhered to

Name of employer Location for which variance is requested

Eagle Excavation, Inc. U of M Alice Lloyd Hall Renovation Project, Ann Arbor

NSS Construction, Inc. Alice Lloyd, Ann Arbor

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212; Rule 1212 (5) and Rule 1212 (6)

Summary of employer's request for variance

To allow employer to move a scaffold past 110/220 volt insulated service conductors closer than the clearances prescribed in table 1 of Part 12, Scaffolds and Scaffold Platforms proviced certain stipulations are adhered to.

Name of employer Location for which variance is requested

Davenport Masonry, Inc. Zaragon Place 2, Ann Arbor

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches under controlled conditions, with stipulations.

Name of employer Location for which variance is requested

AMN Construction Co. Brick Elementary, Ypsilanti

Brinker Team Interiors Children’s Specialty Center, Detroit Medical Center, Detroit

Northwest Acoustical Inc. West Bloomfield High School, West Bloomfield

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) & Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform for use in areas only where the aerial lift cannot reach, due to overhead obstructions. The platform shall only be used to install Metal Studs, Drywall and finish drywall provided certain stipulation are adhered to.

Name of employer Location for which variance is requested

Brinker Team Interiors Children’s Pediatric Specialty Center, Detroit Medical Center, Detroit

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

C. A. Hull Co., Inc. I-94/I-96, Port Huron

Milbocker & Sons, Inc. M-222, Allegan

Dixie Highway at Cass River, Saginaw County

Published: July 26, 2011

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: RULE R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches, under controlled conditions with stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition Co Inc EMU Mark Jefferson Building, Ypsilanti

Lincoln High School, Ypsilanti

U of M Alice Lloyd Hall, Ann Arbor

Barton Malow Co. Blue Cross-Blue Shield Lyon Meadows Project, New Hudson

McLaren Proton Treatment Center Project – McLaren Hospital, Flint

SeverStal NA – PLTCM Modernization & HDCL Projects, Dearborn

Brinker Team Construction Co Chase Building, Detroit

Clark Park School, Detroit

Gompers School, Detroit

Northwestern High School, Detroit

Turner Brooks Interior Contractors EMU Pray Harrold Renovation Project

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

Barton Malow Company McLaren Proton Treatment Center Project – McLaren Hospital, Flint

Bouma Corporation Midland Battery Park, Midland

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

C. A. Hull Co., Inc. M-3 Gratiot Ave. over the Clinton River in

Clinton Township, Macomb County

Published: April 15, 2011

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: RULE R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 30 inches, under controlled conditions with stipulations.

Name of employer Location for which variance is requested

Barton Malow Co. Urban Science Office Suites – Renovation Project, Detroit

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: RULE R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 36 inches, under controlled conditions with stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition Co Inc Pray-Harrold Building, Ypsilanti

St. Joe Hospital, Ypsilanti

Barton Malow Co. Oakland University – Renovation Project, Mount Clemens

Beaumont Hospital – Third Floor Obstetrics Project, Troy

Univ. of Michigan – Angell Hall Renovation, Ann Arbor

Brinker Team Construction Co BCBSM River East Center Tower 500, Detroit

Northwest Acoustical Inc. Blue Cross Blue Shield, Detroit

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

John Darr Mechanical Inc. University of Michigan North Campus Chiller Replacement, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Hardman Construction M-21 over the Grand River, Ada

JH Campbell Plant Intake/Discharge Channel, West Olive

Zenith Tech Inc. US-141 over Menominee River, Dickinson County

Published: January 21, 2011

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 10 – Lifting and Digging Equipment: RULE R408.41015; Rule 1015a (2) (d)(f)(g)(h)(i), 1015a (3), 1015a (4); 1018a (1)(2)(21); 1019a (1); and 1021a (4)

Summary of employer's request for variance

To allow the use of a suspended work platform to hoist or suspend personnel or to provide access to elevated work areas in a manner that exposes employees to the least hazard practicable. All requirements of Construction Safety Standard, Part 10. Lifting and Digging Equipment except Rule 1015a (2) (d)(f)(g)(h)(i), 1015a (3), 1015a (4); 1018a (1)(2)(21); 1019a (1); and 1021a (4) are met under certain stipulations.

Name of employer Location for which variance is requested

Pullman Power Monroe Power Plant, Monroe

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

Bouma Interiors Center for Family Health, Jackson

Buist Electric CS Facility Washington Remodel Project, Coopersville

John E. Green Company BPSC Facility, Midland

John E. Green Company Jackson Family Clinic, Jackson

Limbach Company LLC CS Mott Hospital Children’s & Women’s Hospital Shell Space Completion Project, Ann Arbor

Ventcon General Motors Tech Center Research & Development Bldg., Warren

Published: October 29, 2010

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212, Rule 1212 (5)

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

American Erectors, Inc. Midland Battery Park, Midland

American Erectors, Inc. Maybury K-8 School, Detroit

American Erectors, Inc. Brightmoor K-8 School, Detroit

American Erectors, Inc. Martin Luther King Jr. High School, Detroit

Brigade Fire Protection, Inc. New Accident Fund Insurance Headquarters, Lansing

Summit Contractors New Accident Fund Insurance Headquarters, Lansing

Published: July 26, 2010

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 10 – Lifting & Digging Equipment: R408.41015; Rule 1014a (2) (d)(f)(g)(h)(i), 1015a (3), 1015a (4); 1018a (1)(2)(21); 1019a (1); and 1021a (4)

Summary of employer's request for variance

To allow the use of a suspended work platform to hoist or suspend personnel or to provide access to elevate work areas in a manner that exposes employees to the least hazard practicable. All requirements of Construction Safety Standard, Part 10. Lifting and Digging Equipment except Rule 1015a (2) (d)(f)(g)(h)(i), 1015a (4); 1018a (1)(2)(21); 1019a (1); and 1021a (4) are met under certain stipulations.

Name of employer Location for which variance is requested

Hamon Custodis, Inc. Monroe Power Plant, Monroe

Part number and rule number from which variance is requested

Part 12 – Scaffolds and Scaffold Platforms: R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height, under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition Co Inc. University of Michigan Law Quad, Ann Arbor

Brinker Group Quicken Loans, Detroit

Brinker Group Univ. of Michigan Couzens Hall Renovation, Ann Arbor

Madias Brothers Mott Women’s & Childrens Hospital, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

Ventcon General Motors Corporation, Pontiac

Published: April 26, 2010

Variances Requested - Construction

Part number and rule number from which variance is requested

Part I – General Rules: R408.40115, Rule 115 (4) & (5) and

Part II – Fixed and Portable Ladders: R408.41113, Rule 1113 (5) (6) (8) & (14) and

R408.41115, Rule 1115 (8)

Summary of employer's request for variance

To allow employee to paint steel lattice and pole towers ranging from 120 kV to 345 kV in the International Transmission Company territory (See Exhibit A) located in Michigan. The work would commence immediately following the variance approvals and continue until the end of the 2010 painting season.

Name of employer Location for which variance is requested

Morris Painting, Inc. Various Locations in the International Transmission Co

Territory located in Michigan

Part number and rule number from which variance is requested

Part 12 – Scaffolds and Scaffold Platforms: R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height, under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition Co Inc. Ann Arbor City Municipal Center

Acoustic Ceiling & Partition Co Inc. Detroit Arsenal, Warren

Barton Malow Company C. S. Mott Women’s & Children’s Hospital, Ann Arbor

Rajala & Sons Finishes Michigan Tech University Student Apartments, Houghton

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

Barton Malow Company A 123 Systems, Livonia

Ferndale Electric Co Inc. A 123 Systems, Livonia

Published: January 29, 2010

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds and Scaffold Platforms: R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height, under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Barton Malow Co. A123 Systems, Livonia

Brinker Team Construction Co. Guardian Building, Detroit

Brinker Team Construction Co. Mott Hospital, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

Brunt Associates Inc. U of M North Quad Dormitory

Dee Cramer General Motors Corporation, Flint

Limbach Co LLC Dearborn Town Center, Dearborn

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Posen Construction Inc. Bridgeview Bridge, Midland

Published: October 26, 2009

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212, Rule 1212 (5)

Summary of employer's request for variance

To allow employer to erect a scaffold closer to 110/220 volt insulated service conductors than the clearances prescribed in table 1, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Owen Ames Kimball Construction St. Mary’s Church, Grand Rapids

Part number and rule number from which variance is requested

Part 12 – Scaffolds and Scaffold Platforms: R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height, under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Acoustic Ceiling & Partition Co Inc. U of M CS Mott Children & Women’s Hosp, Ann Arbor

Acoustic Ceiling & Partition Co Inc. St. Joe Hospital, Ypsilanti

Denn-Co Construction Inc. University of Michigan Stadium, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

Ideal Contracting U of M Mott Children’s & Women’s Hospital, Ann Arbor

RAM Construction Services U of M Mott Children’s & Women’s Hospital, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Milbocker & Sons Inc. US 131 over Manistee River, Wexford County

Published: July 24, 2009

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 11 – Fixed and Portable Ladders: R408.41132; Rule 1132 (2)

Summary of employer's request for variance

To allow employer to use stepladders as defined in the ANSI A14.5-1982 with the side rails painted with opaque material for identification purposed, provided certain stipulations are adhered tol.

Name of employer Location for which variance is requested

Soule & Co. Hemlock Semiconductor, Hemlock

Part number and rule number from which variance is requested

Part 12 – Scaffolds and Scaffold Platforms: R408.41221; Rule 1221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 24 inches under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

B. R. D. Inc. Huron Valley Sinai Hospital (DMC), Commerce Twp.

Barton Malow Co. Crittenton Karmanos Cancer Center, Rochester

Brinker Team Construction Co. St. Joseph Hospital, Pontiac

Part number and rule number from which variance is requested

Part 13 – Mobile Equipment: 1926.602, Rule 1926.1000

Summary of employer's request for variance

To allow employer to operate a Kubota R420 without the Roll Over Protection System (ROPS) in the parking garage to remove concrete forms and transport concrete, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Burgess Concrete Construction Inc. Blodgett Memorial Medical Center, East Grand Rapids

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6) and Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided stipulations are adhered to.

Name of employer Location for which variance is requested

R. L. Bondy C. S. Mott Children’s & Women’s Hospital, Ann Arbor

Center Line Electric, Inc. U of M Mott Children’s & Women’s Hospital, Ann Arbor

Dynalectric of Michigan U of M Mott Children’s & Women’s Hospital, Ann Arbor

Andy J. Egan Co., Inc. VanAndel Institute, Grand Rapids

Limbach Co. LLC Argonaut Campus, Detroit

Michigan Mechanical Insulation U of M Women’s & Children’s Hospital, Ann Arbor

Pipe Systems, Inc. BASF JPP Project, Wyandotte

Shaw Electric Co. C. S. Mott Women’s & Children’s Hospital, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (29)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Posen Construction Co. Sanford Lake, Sanford

Published: April 15, 2009

Variances Requested - Construction

Part number and rule number from which variance is requested

Part I – General Rules: R408.40115; Rule 115 (4) & (5) and

Part II – Fixed and Portable Ladders: R408.41113; Rule 1113 (5) (6) (8) & (14), and

R408.41115; Rule 1115 (8)

Summary of employer's request for variance

To allow employee to paint steel lattice and pole towers ranging from 120 kV to 345 kV in the International Transmission Company territory located in Southeastern Michigan. The work would commence immediately following the variance approvals and continue until the end of the 2009 painting season.

Name of employer Location for which variance is requested

Morris Painting, Inc. Various Locations in the International Transmission Co, Flint & Saginaw Area

Part number and rule number from which variance is requested

Part 12 – Aerial Work Platforms: R408.41221; Rule 11221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 24 inches under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Brinker Team Construction Co. University of Michigan Stadium, Ann Arbor

Jasman Construction, Inc. Zaragon Place, Ann Arbor

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216; Rule 3216 (6), Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform, or a self-propelled aerial lift for use as a work platform, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Ann Arbor Ceiling & Partition Co. University of Michigan North Quad Building, Ann Arbor

R. L. Bondy University of Michigan North Quad, Ann Arbor

R. L. Bondy BASF Wyandotte/JPP Project, Wyandotte

Center Line Electric, Inc. BASF Wyandotte, Wyandotte

Conti Electric University of Michigan North Quad, Ann Arbor

Dee Cramer University of MI Women’s & Children Hosp, Ann Arbor

Dependent Insulation Co Inc. University of Michigan North Quad Project, Ann Arbor

John E. Green Co. University of Michigan North Quad, Ann Arbor

Limbach Co., LLC U of M North Quad, Ann Arbor

Mechanical Heat & Frost Insulation U of M North Quad, Ann Arbor

Ventcon, Inc. University of MI Women’s & Children Hosp, Ann Arbor

Ventcon, Inc. University of Michigan North Quad, Ann Arbor

Wolverine Fire Protection Co. C. S. Mott Children’s Hospital, Ann Arbor

Published: January 26, 2009

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 13 – Mobile Equipment: 1926.602, Rule 1926.1000

Summary of employer's request for variance

To allow employer to operate a mini-excavator without the Rollover Protection System (ROPS) to pass through doorways to install electrical conduit provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Buist Electric Alticor Data Center, Grand Rapids

Part number and rule number from which variance is requested

Part 12 – Aerial Work Platforms: R408.41221, Rule 11221 (1) (c)

Summary of employer's request for variance

To allow employer to use stilts at a maximum height of 24 inches under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Barton Malow Company Madonna University, Livonia

Brinker Team Construction Co. Beaumont Hospital, Troy

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (6); Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Superior Electric Great Lakes Co General Motors Technical Center, Warren

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Posen Construction Co. Sanford Lake, Sanford

Published: October 24, 2008

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41221, Rule 1221

Summary of employer's request for variance

To allow employer use stilts at a maximum height of 24 inches under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

B.R.D. Inc. Oakwood Rd., Brandon Twp.

Brinker Team Construction Co. Fort Shelby Hotel, Detroit

Part number and rule number from which variance is requested

Part 13 – Mobile Equipment: 1926.602, Rule 1926.1000

Summary of employer's request for variance

To allow employer to operate mobile equipment without the Roll Over Protection System (ROPS) provided stipulations are adhered to.

Name of employer Location for which variance is requested

Homrich Inc. University of Michigan, Stockwell Hall Renovations

Stenco Constructon Co., LLC University of Michigan, Stockwell Hall Renovations

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43205, Rule 3205.1 (a)

Summary of employer's request for variance

To allow employer to operate an vehicle mounted elevating and rotating aerial device without an operators manual.

Name of employer Location for which variance is requested

Walter Toebe Construction Co. Gateway Project, Detroit

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Milbocker & Sons, Inc. Meridian road over the Tittabawassee River, Midland

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (6); Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Barton Malow Company William Beaumont Hospital, Sterling Heights

R. L. Bondy William Beaumont Hospital, Sterling Heights

Brinker Team Construction Co. Mott Hospital, Ann Arbor

Ferndale Electric William Beaumont Hospital, Troy

John E. Green Co. University of Michigan Mott Childrens & Womens Hospital, Ann Arbor

John E. Green Co. Troy Beaumont Hospital, Sterling Heights

John E. Green Co. Hemlock Semiconductor Plant, Hemlock

Oldcastle Glass Gerald R. Ford Airport, Grand Rapids

SCI/Steelcon Grand Rapids Airport Project, Grand Rapids

SCI/Steelcon Grand Rapids Airport Project, Grand Rapids

Valley Painting, Inc. Gerald R. Ford Airport, Grand Rapids

Western Mechanical Contr., Inc. William Beaumont Hospital EC/CCT, Sterling Heights

Published: July 31, 2008

Variances Requested - Construction

Part number and rule number from which variance is requested

Part I – General Rules: R408.40115, Rule 115 (4) & (5) and

Part II – Fixed and Portable Ladders: R408.41113, Rule 1113 (5) (6) (8) & (14), and

R408.41115, Rule 1115 (8)

Summary of employer's request for variance

To allow employee to paint steel lattice and pole towers ranging from 120 kV to 345 kV in the International Transmission Company territory located in Southeastern Michigan. The work would commence immediately following the variance approvals and continue until the end of the 2008 painting season.

Name of employer Location for which variance is requested

Morris Painting, Inc. Various Locations in the

International Transmission Company territory located in

The Flint & Saginaw area

Part number and rule number from which variance is requested

Part 10 – Lifting and Digging Equipment: R408.41021, Rule 1021 (a)

Summary of employer's request for variance

To allow employer to rig certain loads to the load line of the crane above the overhaul weight in accordance with certain stipulations.

Name of employer Location for which variance is requested

W. J. O’Neil Company BASF, Wyandotte

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41212, Rule 1212 (5) & Rule 1212 (6)

Summary of employer's request for variance

To allow employer to erect a scaffold closer to 110/220 volt insulated service conductors than the clearances prescribed, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Davenport Masonry, Inc. Zaragon Place, Ann Arbor

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41221, Rule 1221

Summary of employer's request for variance

To allow employer firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled aerial lift for use as a work platform provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

B. R. D. Inc. Oakland Technological Schools SW Campus, Wixom

B. R. D. Inc. Oakland Technological Schools NW Campus, Clarkston

Barton Malow Co. William Beaumont Hospital, Sterling Heights

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41221, Rule 1221

Summary of employer's request for variance

To allow employer use stilts at a maximum height of 24 inches under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Barton Malow Co. William Beaumont Hospital, Sterling Heights

Part number and rule number from which variance is requested

Part 13 – Mobile Equipment: 1926.602, Rule 1926.1000

Summary of employer's request for variance

To allow employer to operate mobile equipment without the Roll Over Protection System (ROPS) provided stipulations are adhered to.

Name of employer Location for which variance is requested

Kent Companies, Inc. Waterhouse Apartments, Grand Rapids

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (6); Rule 3216 (7)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the intermediate rail of the guardrail system of a self-propelled elevating work platform, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

American Erectors, Inc. United States Postal Service, Pontiac

J. B. Cain Co. St. John Hospital, Detroit

Eugenio Painting Co. GM Powertrain Engineering Consolidation Project, Pontiac

John E. Green Co. William Beaumont Hospital, Sterling Heights

Great Lakes Steel United States Postal Service, Pontiac

International Industrial Contr. Corp. GM Powertrain Engineering Consolidation Project, Pontiac

Limbach Co. LLC Eye Center Expansion and Diabetes, Ann Arbor

W. J. O’Neil Company BASF, Wyandotte

Pipe Systems, Inc. University of MI Eye Center Expansion, Ann Arbor

Sky Electric of Northern MI Bellaire High/Middle School, Bellaire

Ventilation Systems, Inc. St. John Hospital, Detroit

Ventcon William Beaumont Hospital, Troy

Walbridge Aldinger United States Postal Service, Pontiac

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43216, Rule 3216 (21)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Davis Construction Co. M-20 over the Tittabawassee River, Midland

Published: February 29, 2008

Variances Requested - Construction

Part number and rule number from which variance is requested

Part 10 – Lifting and Digging Equipment: R408.41021, Rule 1021 (a)

Summary of employer's request for variance

To allow the employer to rig certain loads to the load line of a crane above the overhaul weight in accordance with certain stipulations.

Name of employer Location for which variance is requested

Wm. Crook Fire Protection Co. Chrysler Trenton Plant, Trenton

W. J. O’Neil Company Chrysler Trenton Plant, Trenton

Part number and rule number from which variance is requested

Part 12 – Scaffolds & Scaffold Platforms: R408.41221, Rule 1221

Summary of employer's request for variance

To allow employer to use stilts, at a maximum height of 24 inches, under controlled conditions and according to certain stipulations.

Name of employer Location for which variance is requested

Barton Malow Company St. John Hospital, Detroit

Rajala & Sons Finishes University of Michigan, Flint

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43209, Rule 3209 (8) (b), and Rule 3209 (9)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the top of the intermediate rail of the guardrail system for use as a work platform, in areas where a self-propelled elevating work platform cannot reach due to mechanical obstruction, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Barton Malow Company St. John Hospital, Detroit

Boone & Darr Mechanical General Motors Powertrain Lab Consolidation, Pontiac

Buist Electric 133 E. Michigan Ave., Paw Paw

Michigan Metal Walls, Inc. GM Powertrain Engineering Consolidation Project, Pontiac

Pontiac Ceiling & Partition Co. Henry Ford Hospital, West Bloomfield

Roncelli, Inc. General Motors Powertrain Lab Consolidation, Pontiac

Published: November 27, 2007

Variances Requested: Construction

Part number and rule number from which variance is requested

Part 18 – Fire Prevention & Protection: R408.41851, Rule 1851 (2)

Summary of employer's request for variance

To allow the employer to work in the parking structure without the availability of a fire extinguisher for every 3000 sq. ft., provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Jenkins Skanska Greektown Casino, Detroit

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43209, Rule 3209 (8), Rule 3209 (8) (b), and Rule 3209 (9)

Summary of employer's request for variance

To allow employer to firmly secure scaffold planks to the top of the intermediate rail of the guardrail system for use as a work platform, in areas where a self-propelled elevated work platform cannot reach due to mechanical obstruction, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Applegate Inc. Hard Tech – Bldg., Mason

Coritech Services GM Powertrain Engineering Consolidation Project, Pontiac

Hoyt, Brumm & Link, Inc. General Motors Power Train Facility, Pontiac

MI Mechanical Insulation, Inc. General Motors Powertrain Lab Consolidation, Pontiac

Shambaugh & Son L. P. General Motors Powertrain Lab Consolidation, Pontiac

Part number and rule number from which variance is requested

Part 32 – Aerial Work Platforms: R408.43209, Rule 3209 (29)

Summary of employer's request for variance

To allow employer to operate an aerial work platform from the deck of a floating vessel, provided certain stipulations are adhered to.

Name of employer Location for which variance is requested

Anlaan Corporation 7th Street over Black River, Port Huron

Milbocker & Sons, Inc. Hagadorn Bridge, East Lansing

................
................