Creating the Microsoft Project Schedule

Enter the actual start date and the expected actual duration. Enter the actual start date and the percentage completed so far. Enter the actual start date, the actual duration so far, and the remaining duration needed to complete the task. For detailed tracking of Task activity use the Update Tasks Dialog Box. ................
................