Lessons Learned in Project Metrics
[Pages:13]Leading Answers Inc. - Lessons Learned in Metrics
Lessons Learned in Project Metrics:
Are Your Metrics Dumb or Smart?
February 16th, 2010 Software QA Discussion Group
Mike Griffiths, PMP Leading Answers Inc.
My Background
? Project Manager and Trainer
? >20 years IT experience on utilities, defense, & finance ? 8 years PMO Agile-to-Traditional Integration
? Agile Project Management
? Helped create Agile method DSDM in 1994 ? 16 years agile project experience (DSDM, XP, Scrum, FDD) ? Board director of Agile Alliance and APLN ? Author, trainer, and presenter Agile Conference 2001-9
? Traditional Project Management
? PMP, PRINCE2 certifications ? PMBOK v3 contributor and reviewer ? Trainer for PMI SeminarsWorld 2005-2010 ? Presenter PMI Global Congress 2004-2009
Copyright ? 2010 Mike Griffiths. All Rights Reserved
1
Leading Answers Inc. - Lessons Learned in Metrics
6) Smart Metric examples
? 1 ?2 ?3 ?4 ?5
5) Leading vs. Lagging Metrics
4) Measuring Up
Agenda
1) Measurement Troubles
2) The Hawthorne Effect
3) "Design Factory" Metrics
Metrics are like fire...
Copyright ? 2010 Mike Griffiths. All Rights Reserved
2
Leading Answers Inc. - Lessons Learned in Metrics
Measurement
Not all observations are useful:
? The sun rises up in the sky in the morning and then falls down again at night ? Planets revolve around the earth ? Stars come out at night ? Heavier objects fall faster than lighter objects
"There are so many possible measures in a software process that some random
selection of metrics will not likely turn up something of value" ? Watts Humphrey Not all useful things are easily observable:
? Spouse's mood ? Sponsor Confidence ? Team Commitment
"Not everything that can be counted counts, and not everything that counts can be counted" ? Albert Einstein.
The Hawthorne Effect
You will influence what you measure... Copyright ? 2010 Mike Griffiths. All Rights Reserved
3
Leading Answers Inc. - Lessons Learned in Metrics
Design Factory Metrics
Metrics Should be: 1. Simple, self-generating 2. Relevant to the end-goal 3. Ideally, leading, future-focused
Traditional Metrics Examined
Desirable Characteristics:
The Hawthorne Effect is positive Simple, self generating Relevant to the end-goal Leading, future-focused
Traditional Metrics:
? Lines of Code Written ? poor, does not reward simplification, leads to code bloat
? Function Points Delivered ? poor, effort to generate, not relevant to the end-goal of project
? Hours Worked ? poor, leads to long hours, burn-out, defects, consumed budgets
Copyright ? 2010 Mike Griffiths. All Rights Reserved
4
Leading Answers Inc. - Lessons Learned in Metrics
Smarter Project Metrics
Since you will influence what you measure...
Choose Smarter Metrics:
? Features Accepted ? Sponsor Confidence ? User Satisfaction ? Defect Cycle Times
Smarter Metrics
? Features Accepted
Scope (points)
IPS Project Progress
Spend
3000
2500
Not Started
2000
In Progress
Accepted
SAccocpeeptBeduilt 1500
1000
500
0 1/10/06 1/12/06 1/2/07 1/4/07 1/6/07 1/8/07 1/10/07 1/12/07 1/2/08 1/4/08 1/6/08 1/8/08 1/10/08 1/12/08 1/2/09 1/4/09 1/6/09 1/8/09 1/10/09 1/12/09
Copyright ? 2010 Mike Griffiths. All Rights Reserved
5
Leading Answers Inc. - Lessons Learned in Metrics
Smarter Metrics
? Features Accepted
Features
450 400 350 300 250 200 150 100
50 0 Jan Feb Mar Apr May Jun Jul Time
NNoottSStatartretded IInnPPrrooggrersess CAocmceppletteedd
Aug
Feature Based Reporting
Example 2: Parking lot Diagrams
Feature Set Status: Not Started Work in Progress Completed Attention (i.e. behind)
Percentage Complete: Percentage Complete Bar
Target Completion Month: Not Complete Complete
FB Enter Order
Details (15)
24%
Mar 2010
Chief Programmers Initials Feature Set Name Number of Features in the Feature Set
The Feature Set called Enter Order Details has 15 features and is currently 24% complete. It is due to be completed by March 2010
Copyright ? 2010 Mike Griffiths. All Rights Reserved
6
Leading Answers Inc. - Lessons Learned in Metrics
Feature Based Reporting
CM
Create New Order (5)
100%
Jan 2010
Order Processing
DH
LF
Capture
Customer Details (9)
Enter Order Details (15)
75% Feb 2010
24%
Mar 2010
Customer Management
SW
Create New Customer
(8)
AW
Amend Customer
Details (6)
SW
Archive Customer
(4)
55%
20%
Mar 2010
Feb 2010
Feb 2010
RS
Process Payment
(11)
Apr 2010
Inventory Management
NC
KB
Stock
Search (6)
Item Details
(12)
95%
Jan 2010
75%
Feb 2010
Smarter Metrics
User Satisfaction
Copyright ? 2010 Mike Griffiths. All Rights Reserved
7
Leading Answers Inc. - Lessons Learned in Metrics
Smarter Metrics
? Sponsor Confidence
Smarter Metrics
? Defect Cycle Time
Copyright ? 2010 Mike Griffiths. All Rights Reserved
8
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- oe project charter strategic management metrics
- metrics for dummies
- defining and implementing metrics for project risk reduction
- the five most critical project metrics mavenlink
- software process and project metrics university of babylon
- project management metrics
- process and project metrics
- lessons learned in project metrics
- goals questions metrics method and sap implementation projects
- project management metrics and business key performance oracle
Related searches
- different roles in project management
- initiating process in project management
- topics in project management
- client role in project management
- initiation process in project management
- initiating in project management
- project in project management definition
- planning in project management pdf
- financial analysis in project management
- mba in project management jobs
- best practices in project management
- agile methodology in project management