3. (Chapter 10 – Project Scheduling) A set of activities in a project, their immediate predecessors and expected times are listed below. A part of the Management Scientist output has also been provided. (a) Some activity slacks are given. Determine the slacks of the remaining activities. (b) Which activities are critical and why? ................
................