Marine Archaeological Reporting Plan (MARP) KINCARDINE ...
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 1 of 25
Marine Archaeological Reporting Plan (MARP) KINCARDINE OFFSHORE WINDFARM PROJECT
Document Category
X
Prepared
08-1-2018 Organisation:
KOWL Name / signature: [Redacted]
Checked
22-01-2018 Organisation:
KOWL Name / signature:
Reviewed
22-01-2018 Organisation:
KOWL Name / signature:
Approved
01-02-2018 Organisation:
KOWL Name / signature:
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 2 of 25
Revision History
Date
Rev. Status
08-12-2017
00
12-01-2018
02
Purpose of Issue* DRAFT FOR COMMENT
Issue for MS LOT
Remarks First Issue Updated with HES comments
Initials RJW RJW
*Purpose of Issue: for information, for review, for approval
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 3 of 25
Detailed Change Log
Date
Rev. Status
References
08-01-2018
V2
Section 5.9
08-01-2018
V2
Section 5.9
08-01-2018
V2
Appendix E
Description of changes Minor comment (Archiving, instead of Arching) Add in OASIS reporting Protocol for reporting finds added in App E.
Initials RJW RJW RJW
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 4 of 25
Table of Contents
1. Introduction .................................................................................................................................. 6 2. KOWL Commitments ................................................................................................................... 8 3. Scope of MARP and PAD ............................................................................................................ 8 4. Archaelogical Written Scheme of Investigation........................................................................ 9
4.1. Introduction ............................................................................................................................ 9 4.2. Consultation......................................................................................................................... 10 4.3. Proposed Development and Cable Route........................................................................... 10 4.4. Known Archaeological and Cultural Heritage Assets and Targets ..................................... 10 4.5. Development Area............................................................................................................... 10 4.6. Cable Route......................................................................................................................... 11 4.7. Archaeological Exclusion Zones (AEZs) ............................................................................. 12 i Location and Extent of AEZs ................................................................................................... 12 ii Monitoring of AEZs .................................................................................................................. 12 5. Protocol for Archaeological Discoveries (PAD)...................................................................... 13 5.1. Scope .................................................................................................................................. 13 5.2. Types of Fields .................................................................................................................... 13 5.3. Potentially Significant Materials........................................................................................... 13 5.4. Circumstances of Discovery ................................................................................................ 14 5.5. Roles and Responsibilities .................................................................................................. 14 5.6. Lines of Communication ...................................................................................................... 15 5.7. Discoveries on the seabed and on the deck of works vessels............................................ 15 i Preliminary Actions by KOWL or its Contractors..................................................................... 15 ii Initial Actions by the Client Representative ............................................................................. 15 iii Initial Actions by the ECoW and Client Representative .......................................................... 16 iv Contacting the Relevant Authority........................................................................................... 16 v Establishing new AEZs............................................................................................................ 16 vi Alternating AEZs...................................................................................................................... 17 5.8. Finds recovered within the UK twelve nautical mile limit..................................................... 17 5.9. Reporting and Archiving ...................................................................................................... 17 5.10. Health and Safety ................................................................................................................ 18 6. Appendix A ? ES and SEIS Commitments............................................................................... 19 Mitigation.......................................................................................................................................... 19 7. Appendix B ? Location of Wrecks identified and Sidescan Imagery.................................... 20
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 5 of 25
8. Appendix C ? Protocol for Infringement of Archaeological Exclusion Zone....................... 22 22 9. Appendix D ? Preliminary Record Form .................................................................................. 23 10. Appendix E ? Protocol for Reporting Finds of Archaeological Interest .......................... 25
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 6 of 25
1.
Introduction
In April 2016 Kincardine Offshore Windfarm Limited (KOWL) submitted applications for consent to
construct and operate the Kincardine Offshore Windfarm known hereafter as the `Project'.
The Project is considered a commercial demonstrator site, which will utilise floating foundation technology, and will be one of the world's first array of floating wind turbines. It has been included within the Survey, Deploy and Monitoring scheme for offshore renewable systems (similar to wave and tidal devices).
The Project is located south-east of Aberdeen approximately 8nm (15km) from the Scottish coastline and provides suitable water depth for a floating offshore wind demonstrator development (approximately 60-80m) (Figure 1-1).
The project is split into the following areas:
?
The Development Area ? the wind farm area including the Wind Turbine Generators
(WTG) and inter-array cables.
?
The Offshore Export Cable Corridor ? the area within which the proposed export cables
will be laid, from the perimeter of the Development Area to the onshore area at Mean
High Water Spring (MHWS).
?
The Onshore Area ? the onshore area above Mean High Water Spring (MHWS)
,including the underground cables connecting to the onshore substation at Redmoss.
In March 2017 consent under Section 36 and Section 36A of the Electricity Act 1989, and the associated Marine Licence under the Marine (Scotland) Act 2010 were awarded by the Scottish Government.
A Marine Archaeology Reporting Protocol ("MARP") and Protocol for Archaeological discovery (PAD) has been prepared to enable the Conditions of the Section 36 Consent and the relevant Marine Licence conditions to be dicharged. Both of these have been prepared within this document.
This report contains the followin sections:
?
Scope of the MARP and PAD;
?
MARP; and,
?
PAD.
Table 1.1 sets out the consent conditions which this Archaeology and WSI and PAD provides
information required to discharge.
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 7 of 25
Table 1-1 Consent Condition
Consent Condition Condition description Document Reference
Section 27 36
The Company must, no later than 6 months or at such a time as agreed with the Scottish Ministers, prior to the Commencement of the Development, submit a Marine Archaeology Reporting Protocol ("MARP") which sets out what the Company must do on discovering any marine archaeology during the construction, operation, maintenance and monitoring of the Development, in writing, to the Scottish Ministers for their written approval.
Reference to relevant Section of this MARP and PAD Addressed within this MARP. See Appendices for details and reporting protocols
Figure 1-1 Project site and indicative turbine locations
KINCARDINE OFFSHORE WINDFARM PROJECT
Marine Archaeological Reporting Plan (MARP)
Doc. No.:
KIN-DC-FMS-KO-0003
Rev.: 02 Page 8 of 25
2.
KOWL Commitments
In addition to condition 27 noted above, condition 7 of the Section 36 Consent states "The
Development must be undertaken in accordance with the Application, the Environmental Statement
(as supplemented or amended by the further environmental information submitted by the Company
on 22nd September 2016) and any other documentation lodged in support of the Application".
The ES sets out a number of KOWL commitments in relation to the heritage and archaeological resouce. These commitments were made to ensure that the development followed appropriate practice in relation to its interaction with archaeological interests. These commitments can be found within the Original ES documents.
3.
Scope of MARP and PAD
This Archaeological MARP and PAD has been prepared based on COWRIE & Wessex Archaeology (2007), The Crown Estate (2014) and The Crown Estate & Wessex Archaeology (2010) guidelines for:
? Desk-based assessments; ? Geotechnical surveys; ? Geophysical surveys; and, ? Historic environment and setting appraisals.
This MARP establishes the mitigation procedures that must be followed in order to seek to avoid damage to cultural heritage assets and targets of archaeological potential for the lifespan of the Project. These assets and targets were identified during the Environmental Impact Assessment (EIA) for the Development.
This PAD is based on the Offshore Renewables Protocol for Archaeological Discoveries (ORPAD) which was developed for The Crown Estate by Wessex Archaeology, and has been in effect since 2010. The Protocol was revised and reissued in 2014 (The Crown Estate, 2014). This PAD sets out the protocols and procedures that must be followed in the event of any unexpected archaeological discoveries whilst undertaking work related to the Project.
The main objectives of this Archaeological MARP and PAD, following the Model Clauses for Archaeological Written Schemes of Investigation (The Crown Estate & Wessex Archaeology 2014), are to:
? Set out the respective responsibilities of KOWL, their Contractors, the ECoW, the Client Representative and the Archaeological Consultant prior to and during the Project, and formal lines of communication between these parties and Marine Scotland Licensing and Operation Team (MS-LOT) and Historic Environment Scotland (HES);
? Establish mitigation procedures to seek to avoid damage to cultural heritage assets and targets of archaeological potential;
? Propose measures for mitigating effects upon archaeological material that may be encountered during the Project;
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- archaeology an introduction to the world s greatest sites
- issue 20 january 2018
- 139 years of archaeology archaeological institute of
- marine archaeological reporting plan marp kincardine
- the society for pennsylvania archaeology inc newsletter
- discovery 2018
- revised archaeological monitoring plan for phase i
- 2018 british archaeological awards
- archaeological compliance guidance
Related searches
- new archaeological discoveries 2019
- recent archaeological discoveries
- recent archaeological discoveries in america
- most recent archaeological discoveries
- newest archaeological discoveries 2019
- 45 strange archaeological discoveries
- 2019 archaeological finds
- most recent archaeological discoveries 2018
- recent major archaeological finds
- latest archaeological discoveries in 2018
- 2018 archaeological discoveries
- 2019 archaeological discovery israel