Scope of Work Agreement - Dale's Remodeling Salem Oregon

August 21, 2015

Scope of Work Agreement

Dale's Remodeling proposes to provide labor & materials for your project as outlined.

KITCHEN Remove & discard of the following: o Sink, faucet & garbage disposal o Appliances. Save & protect for re-use as required o Counters & backsplash o Cabinets o Vinyl flooring, carpet & pad o Particle board sub flooring o Base trim. o Fluorescent lighting o Remove wall paper from ceiling Provide and install new: o Upgrade outlets to GFCI as per plans o (7) Electric outlets as per plans o (8) Recessed can lights as per plans o (1) Switch for under cab lights o (1) Light outlet for o (2) Pendant lights over sink. Owner to provide pendant lights o (1) Phone jack o Frame in soffits in corners as per plans o Plywood sub flooring required for hardwood o Patch drywall as needed, tape and texture o Paint walls & ceilings in Kitchen & Family room o Custom cabinets with accessories as per plans, crown molding & light rail o Under cabinet lights o Slab countertops with full height tile backsplash o Pulls & Knobs on cabinet doors & drawers o Under mount sink, faucet & Garbage disposal with air vac switch

Contractor's Initials ________ Owner's Initials ________ Owner's Initials _________

H:\Marketing\Words Out PR\Blog\DRI Scope kitchen template.doc 8/21/2015 11:13 AM Last saved by Kayla Van Lydegraf Page 1 of 3

o Leaded glass inserts for (2) cabinet doors o Overflow pan for dishwasher o Pre-finished hardwood flooring in kitchen & family room o Install new base trim o Paint base trim o Install homeowner provided new/ existing appliances o P&R light in family room with owner provided unit o P&R light in living room with owner provided unit

NOTE: See Plans, Elevations, Finish Schedule, and Product Photos.

Owner Responsibilities: Provide all surface mount light fixtures (Dale's Remodeling to install) Move all the furniture from the work area Finish Cleaning

Please provide the following selections by: _____________ [ ] Counter Top [ ] Backsplash [ ] Flooring [ ] Cabinet Color [ ] Cab Door Style [ ] Tile [ ] Sink [ ] Plumbing Fixtures [ ] Cabinet Hardware [ ] Paint Colors [ ] _______________ [ ] _____________ [ ] ____________ [ ] _______________

General Expenses (items that overlap all phases): Project setup; this includes required permits, special tools and tool maintenance. Beginning and ending project walkthrough with your lead carpenter & project manager. Dust protection, including but not limited to closing off the affected work area. This limits areas impacted by our workers and trade contractors while working in your home. Clean up; our carpenters try to maintain your home in a manner that impacts your lifestyle as little as possible. Project supervision; Our certified lead carpenters spend quality time supervising and organizing sub-contractors as well as communicating with you to ensure that all of your concerns have been addressed. This allows your job to run smoothly! Job expediting; much happens behind the scenes that is not really apparent in the construction process. There are trips to the lumber yard and other suppliers, deliveries and the hauling off of the debris on a regular basis. Builders margin; our goal is to stay in business and provide outstanding service for many years to come. Overhead; this allows us to maintain a staff that is qualified to meet your needs and provide a warrantee that protects you into the future.

We have included allowances for the following items as selections and physical measurements may change the final cost. Allowance underage will be credited back to your account. Allowance overage will be billed including a markup to cover our builder's margin:

Electrical up to: $

Contractor's Initials ________ Owner's Initials ________ Owner's Initials _________

H:\Marketing\Words Out PR\Blog\DRI Scope kitchen template.doc 8/21/2015 11:13 AM Last saved by Kayla Van Lydegraf Page 2 of 3

Plumbing, rough and finish up to: $ Cabinetry up to: $ Slab Counter up to: $ [Average Grade, Mid Grade, High Grade] Hardwood to: $ [Average Grade, Mid Grade, High Grade] Tile, labor and setting materials up to: $ [$6.98 per square foot allowed for tile] Interior Decorator Allowance for product selection included: $330.00

NOTE: All items requested and discussed must be in writing. Due to the many things covered during the course of the design process, items are sometimes missed. Please review this document and the attached finish schedule in order to verify that everything you wanted is included. Items not specified in these documents are not included! Thank You!

The estimated cost for your new kitchen remodel is: $

This estimate is good for (10) days from date of issue Payment Schedule:

1. $ 2. $ 3. $ 4. $ 5. $ 6. $

design deposit due at signing due at rough plumbing due at start of counter installation due at start of finish plumbing. due upon 100% completion.

. Date: ____________________

Accepted By: ________________________________ by: ______________________________

Dale Van Lydegraf _______________________________________________________ Remodeling Consultant Dale's Remodeling, Inc

Option 1. Dishwasher Overflow Pan

Add $310

Contractor's Initials ________ Owner's Initials ________ Owner's Initials _________

H:\Marketing\Words Out PR\Blog\DRI Scope kitchen template.doc 8/21/2015 11:13 AM Last saved by Kayla Van Lydegraf Page 3 of 3

................
................