Practice Problem: Chapter 15, Short Term Scheduling

Job Days to Finish Date Promised (in Days from Today) A 2 5 B 8 8 C 6 12 D 4 10 E 1 4 Compare the effect of the scheduling methods (a) FCFS (first come, first served), (b) EDD (earliest due date), and (c) SPT (smallest processing time). Problem 3: A firm has the following six jobs waiting to be processed: Job Hours to Process Time Due #407 2 7 #281 8 16 #306 4 4 #429 10 17 #038 5 15 #998 12 18 ... ................
................