[pic] Real Estate and Construction Services (RECS)
RECS-SW-16 Standard Work
for Archiving Project Documents and Non-Project Documents in PWA (Project Web Application/ Project Management Software System) & Documents Pre-PWA/Post File Net
Standard for:
Archiving of project and non-project documents in the division’s project management software system.
Purpose:
To achieve consistency in the types of electronic documents to be filed and by whom and to have a document retrieval source that meets record retention requirements
Background:
The division has a software application for managing construction projects. This system has document storage capability and was designated the source for project and non-project document archiving and retrieval.
References or related documents:
MN Statute Section 15.17 and 138.17 – Records Retention & MN Data Practices Act
Estimated time for completion:
When documents are finalized or prior to closeout of project.
Process for revising standard:
Submit electronic document of this standard with tracked and redline changes.
Attachments:
Attachment A: Document Types, Archiving Responsibilities and file location
Attachment B: Electronic Document Naming Standards
RECS Records Retention and Archiving Policy dated 8/16/2016
Date:
August 9, 2013
Revision Date:
11/22/2016
Standard:
|Step |TASK |TIME |
| | | |
|1 |Review the Attachment (A) to this Standard of Work for the documents that are to be filed / archived in|As occurs |
| |the division’s project management software system; the staff who is responsible for filing the | |
| |document; and the location to file the electronic document. | |
| | | |
|2 |File the final version of project and non-project document(s)* in the system using Attachment |As occurs or prior to project|
| |B-Electronic Document Naming Standards. |closeout |
|3 |Contracting staff (for P/T consultant related contracts) or Accounting staff (for construction related | |
| |contracts) will print appropriate Contract Checklist and attach to contract file. Persons responsible |At time of filing for each |
| |for filing documents should review, initial and date checklist found in the file folder once documents |contract |
| |have been appropriately filed. Accounting will scan into PWA when final pay is complete and contract is| |
| |closed. | |
| | | |
| |Project Checklist will be added to PWA by Accounting staff. Project documents should be verified by all| |
| |appropriate persons, initialed and dated so project can be closed out. |After project closeout |
|Notes: |Contracts for non-Construction Services projects are in the Non Project Contract Data tab in PWA in the| |
| |Contract section and archived (attached) by line item. | |
| |Grants, Joint Powers Agreements and other special agreements are entered in the Agreements List in the | |
| |Non Project Contracts tab in PWA. The documents are saved in the Non Project Archive Data tab, in | |
| |separate Libraries based on the agreement type. | |
| |RFPs for non-project contracts are in the Non Project Contract Data tab in PWA in the RFP section and | |
| |archived (attached) by line item. | |
| |Master Contract documents are located in the Master Contract section in the Non Project Archive Data | |
| |tab with just data entry in the Non Project Contract Data tab in PWA. | |
| |Predesigns for are located in the Predesign section in the Non Project Archive Data tab. | |
| |PBEEEP RECS projects in PWA, box up PBEEEP MNSCU and keep indefinitely | |
|Contracting File | | |
|Folders | | |
| |Accounting Tech moves file folders from active contract files after the entire project is final paid. | |
|1 | |After Final Pay |
|1a |For those files archived in PWA: | |
| |Accounting Tech to verify documents in contract file folders are in PWA by reviewing closeout | |
| |checklist. | |
| |Put in cabinets or boxes for storage. | |
| |Keep for five (5) years plus current fiscal year for audit access. | |
| | | |
| |How to know if contract archived in PWA: | |
| |Accounting Clerk’s “Archived” stamp will be in the file on the final pay document. | |
| |Prior to using the stamp, Accounting Clerk initialed final pay document, which indicates it was | |
| |archived in PWA. Accounting Clerk also puts a colored flag on the folder tab that says “Closed” with | |
| |the Date. The flag color will be changed each fiscal year. | |
| |For those files not archived in PWA or the previous FileNet system (May 2011 and earlier), move to | |
|1b |“Archived” file cabinets and keep for eleven (11) years. | |
|Notes: |Vendor invoices to be kept for five (5) years plus current fiscal year. | |
| |Bundled projects – filed with first project number listed. | |
| |Since PWA archiving began, files are archived by contract file, not by project. | |
| |Construction related contracts must be retained for eleven (11) fiscal years after the end date of the | |
| |contract or the last payment date, whichever is later. A paper copy of a contract must be retained for| |
| |five (5) plus current fiscal year years for auditing purposes. However, a paper copy is not needed if | |
| |there is an electronic copy, that is backed up and easily retrievable. | |
| |Beginning 2/1/2014, archiving pay requests in PWA commenced. When a contract is final paid, the pay | |
| |requests are scanned by project and saved in PWA under the project number. (See Attachment A for file | |
| |location.) | |
| |Documents needing to be archived should NOT be placed in the shelving area outside of conference room | |
| |C. This is no longer an archive collection area and instead is used for archiving file storage. See | |
| |Attachment A for staff responsible for archiving electronically. | |
End of Standard
Attachments
Attachment A: Document Types, Archiving Responsibilities and file location
Attachment B: Electronic Document Naming Standards
ATTACHMENT A – Document Types, Archiving Responsibilities and File Location
PROJECT CONTACTS - in PWA under Project Number > Project Documents
|Contract File |Document |Filed By |Folder |
|Consultant Design & Study (red files) | | | |
| |Contract |Support |03 Contracts - 01 Consultants |
| |Supplemental Agreements |Support |03 Contracts - 01 Consultants |
| |DEs |Support |03 Contracts - 01 Consultants |
| | | |(at the end of applicable SA) |
| |Insurance Certificate |Support |03 Contracts - 01 Consultants (with contract) |
| |Cover Sheets |Support |03 Contracts - 01 Consultants |
| |Certification Form |Contracting |03 Contracts - 01 Consultants |
| |RFP/RFQ |Contracting |03 Contracts - 01 Consultants |
| |State Register Notices, if applicable |Contracting |03 Contracts - 01 Consultants |
| |Successful RFP response |Contracting |03 Contracts - 01 Consultants |
| |RFP Evaluation documents |Contracting |03 Contracts - 01 Consultants |
| |SDSB documents (use SDSB File Checklist at |Contracting |03 Contracts - 01 Consultants |
| |S:\SDSB\FORMS\RFP related forms\Current Forms| | |
| |for full list of documents) | | |
| |Pay Requests |Accounting | |
| |16A/C |Support |03 Contracts - 01 Consultants |
|Consultant - Construction Testing | | | |
| |Same as Consultant red file above |Support |03 Contracts - 04 Testing |
|CM at Risk or Design Build (blue files) | | | |
| |Same as Consultant red file above | | |
| |Payment & Performance bonds |Support |03 Contracts - 02 Contractors |
|Consultant - other (green files) | | | |
|Specialty consultant files such as: Owners |Same as Consultant red file above | |03 Contracts - 01 Consultants |
|Representatives, contract workers, annual | | | |
|contract/Master Design contract | | | |
|Construction/Contractor (yellow files) | | | |
| |Contract |Accounting |03 Contracts - 02 Contractors |
| |Supplemental Agreements |Support |03 Contracts - 02 Contractors |
| |DEs |Support |03 Contracts – 02 Contractors (at the end of |
| | | |applicable SA) |
| |Payment & Performance bonds |Accounting |03 Contracts - 02 Contractors |
| |Insurance Certificate |Accounting |03 Contracts - 02 Contractors |
| |Notice to proceed letter |Accounting |03 Contracts - 02 Contractors |
| |Pay requests & Invoices (includes FFE, all |Accounting |06 Closeout Documents - 01 Documents |
| |back-up & TG info) | | |
| |Asbestos POs & back-up |Accounting |03 Contracts - 05 Environmental / Haz Mat |
| |POs & back-up |Accounting |06 Closeout Documents - 01 Documents ; If for |
| | | |FF and E - 01 Budget and Financial - 03 FF and|
| | | |E |
|Abatement Consultant (blue files) | | | |
|Standalone Haz Mat project |Same as Consultant red and Construction | |03 Contracts - 05 Environmental/Haz Mat |
| |yellow files above. | | |
|Part of a construction project | | |03 Contracts - 05 Environmental/Haz Mat |
|All Projects | | | |
| |Original PIF |PM |01 Budget and Financial - 01 PIF |
| |Updated PIFs |Accounting |01 Budget and Financial - 01 PIF |
| |CAPRA Request - approved form |PM |01 Budget and Financial - 01 PIF |
| |Design kick-off and design meeting notes |PM |04 Communications - 02 Design |
| |Design guideline checklist sign-offs |PM |04 Communications - 02 Design |
| |Precon checklist and meeting notes |PM |04 Communications - 04 Construction |
| |Construction meeting notes |PM |05 Construction Documents-06 Meeting Notes |
| |Letters authorizing consultant to proceed to |PM |04 Communications - 02 Letters |
| |DD-CD-Bidding phases | | |
| |Legislative/Bonding Bill language |PM |04 Communications - 02 Legislative |
| |Legislative notification letters |PM |04 Communications - 02 Legislative |
| |Legislative response letters |PM |04 Communications - 02 Legislative |
| |Emergency Authorization Form - Approved |PM |01 Budget and Financial - 01 PIF |
| |version | | |
| |Intent to Award letter |PM |04 Communications - 03 Bidding |
| |Bid request form (completed version) |PM |04 Communications - 03 Bidding |
| |Bid award/rejection memo |Accounting |04 Communications - 03 Bidding |
| |Bid results (tabulation) |PM |04 Communications - 03 Bidding |
| |Consultant's recommendation to award letter |PM |04 Communications - 03 Bidding |
| |Project Directory |PM |04 Communications - 02 Project |
| |Final Project accounting worksheet |PM |01 Budget and Financial - 02 Project Budget |
| |Test results |PM |03 Contracts - 04 Testing |
| |Building permit and other permits |PM |06 Closeout Documents - 01 Documents |
| |Code, Fire Marshal, SHPO authority letters |PM |06 Closeout Documents - 01 Documents |
| |Certificate of Occupancy w/punchlist |PM |06 Closeout Documents - 01 Documents |
| |Certificate of substantial completion |PM |06 Closeout Documents - 01 Documents |
| |(w/punch list) | | |
| |Signed off punch lists from contractor |PM |06 Closeout Documents - 01 Documents |
| |Acceptance by agency |PM |06 Closeout Documents - 01 Documents |
| |Final Report (if predesign, study, |PM |07 Reports - 01 Project Reports |
| |investigative work, geotech report) | | |
| |As-Built Record Documents (CD of both plans |PM |RECS PLANNING |
| |and specs); Note; A CD of the bid set goes to| | |
| |RECS planning | | |
| |Documentation on any claims & disputes |PM |04 Communications - 10 Conflict Resolution, |
| | | |Mediation, Litigation |
| |Significant correspondence (decision making |PM |04 Communications - 02 Design or 04 |
| |correspondence) | |Construction |
| |Specialty docs: FF&E packages, move company,|PM |Small Projects: 01 Budget and Financial - 03|
| |etc. | |FF and E |
| | | |Large Projects: Obtain IT Support to create |
| | | |new Document Group 08 FF and E |
NON PROJECT ARCHIVE DATA – in PWA
|Contract File |Document |Filed By |Folder |
|Predesign |Predesign Manual, Letters | Project Operations|In Predesign section, organized by Department |
| | |Manager |or other Government Entity |
| Master Contracts |Contract |Support |In Master Contract section -> Type of Master |
| | | |Contract -> Program Year -> Original Contract |
|Master Contract SAs |Contract |Support |In Master Contracts section -> Type of Master |
| | | |Contract -> Program Year -> Supplemental |
| | | |Agreement |
NON PROJECT CONTRACTS – in PWA under Non Project Contracts tab
|Contract File |Document |Filed By |Folder |
|Non Project Contracts (Assignment Agreements, Land, | | | |
|Grants, Interagency Agreements, MOU’s, JPA’s, and | | | |
|License Agreements) Please note that only Master | | | |
|Contract Data is entered in this section. See above | | | |
|for location Master Contracts and SAs. | | | |
| |Contract |Support |Add document to contract line item |
| |Contract Coversheet |Support |Add document to contract line item |
| |Insurance Certificate |Support |Add document to contract line item ( with the |
| | | |contract) |
| |Supplemental Agreements |Support |Add document to Supplement Agreement line item|
| |DEs |Support |Add document to Supplement Agreement line item|
| | | |(at the end of applicable SA) |
| |16A/C |Support |Add document to contract line item |
| |Pay Requests |Accounting | Add document to contract line item |
| |RFP & Addenda |Contracting |Add document to awarded vendor/first RFP line |
| | | |item |
| |State Register Notices, if applicable |Contracting |Add document to awarded vendor/first RFP line |
| | | |item |
| |RFP Evaluation Material |Contracting |Add document to awarded vendor/first RFP line |
| | | |item |
| |Successful RFP response |Contracting |Add document to awarded vendor/first RFP line |
| | | |item |
| |Certification form |Contracting |Add document to awarded vendor/first RFP line |
| | | |item |
| |Grants |Support |Add document to Agreement line item |
| |Interagency Agreement |Support |Add document to Agreement line item |
| |Joint Powers Agreement |Support |Add document to Agreement line item |
| |Memorandum of Understanding |Support |Add document to Agreement line item |
| |License Agreement |Support |Add document to Agreement line item |
ATTACHMENT B
|Electronic Document Naming Standards for PWA |
|General Notes |Using two digits for number allows 01 to proceed 10. If a single digit is used 10 comes before 1 in a list because the computer reads from the left. |
| | | |
| |Number symbols ## do not work in PWA. Other characters to avoid: / : * ? < > [ ] & $ |
| | |
| |Computers do not like spaces, an underscore is the preferred separation. Spaces are translated to %20 in a web environment. |
| |If a file is named "Addenda 11" it may appear as "Addenda%2011" when printed or copied. |
| | | |
| |"BBC" throughout this document represents the vendor's initials | |
| | |
|Project Number |G02RC02HP0003 this is the SWIFT number for the project and must be used as the primary project name. |
| | |
|Project Name |02HP0003_REPLACE_WINDOWS |
| |Files will also be searchable if documents are abbreviated with 02HP0003_REPLACE_WINDOWS |
|Executed Contract |BSA_Design_BBC_45576_Executed ("BBC" represents vendor's initials) |
| | |
|Master Contracts |MC_IHS_BBC_45576_Executed | |
| | | |
|Work Orders |WO_Testing_BBC_45576_Executed |
| | | |
|Work Order Amendment |WO_Testing_BBC_45576_SA_01_Executed |
| | |
|Supplemental Agreements |SA_01 thru SA_99 BSA_Design_BBC_45576_SA_01_Executed (or PT_Study_BBC_45576_SA_01_Executed or MC_Testing_BBC_45576_SA_01_Executed) |
| |If construction contract with multiple bid packages, add "BP1" or BP2" to the end. |
| |When a DE is included in an SA, the signed copy of the DE should be scanned/attached with the SA to fulfill MN Stat. 16C.05, subd.2(d) |
| | | |
|CM @ Risk Executed Contracts |CMR_BBC_45576_Executed | |
| | | |
|CM @ Risk Supplemental Agreements |CMR_BBC_45576_SA_01_Executed | |
| | | |
|Developing Encumbrances |DE_BBC_01 thru DE_BBC_99 |
| | | |
|Bid Request Form |Const_Bid _Request | |
| | | |
|Award Recommendation |Const_Award_VendorName | |
| | | |
|Construction Agreements |Constr_BBC_45576_Executed | |
| | | |
|Construction Supplemental Agreements |Constr_BBC_45576_SA_01_Executed | |
| | | |
|PO |PO_BBC_PO# | |
| | | |
|Invoices |Inv_3-1234_VendorName_12345 (3-1234 represents the PO# and 12345 represents the invoice #) |
| | | |
|PIF |PIF_Project Name ie: PIF_02HP0003_REPLACE_WINDOWS | |
| | | |
|RFI |RFI_01 thru RFI_99 |
| | |
|RFQ |RFQ_01 thru RFQ_99 |
| | |
|RFQ Addenda |RFQ_ADDENDA_01 |
| | |
|SWIFT Consultant RFP |RFP_Design_1234 φ(SWIFT Event ID) |
| | | |
|SWIFT Consultant RFP Proposal |RFP_Design_1234_Proposal_BBC | |
| | | |
|SWIFT Consultant RFP Evaluation Summary |RFP_Design_1234_Evaluation_Summary | |
| | | |
|SWIFT Consultant RFP Evaluation Score Sheets|RFP_Design_1234_Evaluation_Score_Sheets | |
| | | |
|SWIFT Consultant RFP Non Award Letters |RFP_Design_1234_NonAward_Letter_BBC | |
| | | |
|Mandatory Meeting Sign In Sheets for RFP’s |RFP_Design_1234_Sign_in_sheet | |
| | | |
|SWIFT Certification Forms when w/RFP |RFP_Design_1234_Certification_Executed (won't be signed, approved in SWIFT) | |
| | | |
|Consultant RFP (pre-SWIFT) |RFP_Design |
| | | |
|Consultant RFP Proposal (pre-SWIFT) |RFP_Design_Proposal_BBC | |
| | | |
|Consultant RFP Evaluation Summary |RFP_Design_Evaluation_Summary | |
|(pre-SWIFT) | | |
| | | |
|Consultant RFP Evaluation Score Sheets |RFP_Design_Evaluation_Score_Sheets | |
|(pre-SWIFT) | | |
| | | |
|Consultant RFP Non Award Letters (pre-SWIFT)|RFP_Design_NonAward_Letter_BBC | |
| | | |
|Certification Forms when w/RFP (pre-SWIFT) |RFP_Design_Certification_Executed | |
| | | |
|Certification Forms when no RFP |BSA_Design_BBC_45576_Certification_Executed | |
| | | |
|Pay Requests |Pay_Request_BBC_1234 ("1234" represents contract number); If saved as separate documents, add pay request number at the end |
| | | |
|Substantial Completion Form |Substantial_Completion_2012_01_12 | |
| | | |
|Dates |2012_01_12 |
| | | |
|Email attachment or scan |Site_visit_2012_01_12 Use a naming strategy that identifies the content. Project number can be included. |
| | | |
|Memo, Letters, Reports |Sign_in_sheet_2012_01_12 Use a naming strategy that identifies the content. Project number can be included. |
| | |
|Bundled Projects |Each project number will have its own file. File notes will list other project numbers bundled with each other. |
| | |
|Pre Design Submittals | Facility_Building_Document Type_Project_Date (General Format) (Document type is generally Predesign, Submittal_Ltr Response_Ltr, or Narrative) |
| | | |
|Joint Powers Agreement |JPA_BBC_Project_Contract#_Executed_Date ( Where BBC is who agreement is with and Contract # is if applicable) For Example: |
| |JPA_UofMN_B3_111578_Executed_2016-07-01 |
| | | |
|Grants |Grant_Grantee_Project_Contract#_Executed Date |
| |For Example: Grant_Hastings_Vets_Mem_15657_Executed_2016-07-01 |
| | | |
|Additional source information | |
| | | |
|Following these standards will allow for |For other documents, use a consistent naming convention, similar to those above. | |
|consistency and better file searching in the| | |
|future. | | |
|Draft files should not be saved in PWA. | | |
................
................
In order to avoid copyright disputes, this page is only a partial summary.
To fulfill the demand for quickly locating and searching documents.
It is intelligent file search solution for home and business.
Related download
- standard work for new changing employee form
- verification of social security numbers
- final private placement memorandum
- this project has a targeted group tg economically
- usa national highway traffic safety administration
- state of minnesota
- administration of insured home mortgages
- property course outline
- state licensing board for contractors
- 2017 short resume
Related searches
- standard work hours per year
- supervisor standard work template
- leader standard work template excel
- leader standard work example
- healthcare leader standard work examples
- 1099 form for new employee
- standard work week by country
- standard work template word
- standard work excel template
- bio for new employee sample
- employee form for essential worker
- standard work year in days